These determine the physical and functional condition of the structure, identifying changes from the inventory, baseline, or previously recorded conditions. Routine inspections should be performed on a cyclical basis and are a proactive approach to maintenance. Routine Inspection of substructures in water must be conducted at least every five years. Structures having underwater members which are partially deteriorated or which are in unstable channels may require shorter inspection intervals.


Related Discussions:- Explain the routine inspections - inspection of bridge

About distomat, what is distomat? functipns &properties

what is distomat? functipns &properties

Design of prestressed concrete pipes, Design of prestressed concrete pipes ...

Design of prestressed concrete pipes The design of prestressed concrete pipes should cover the following five stages : (a) Circumferential prestressing, winding with or wit

Conventional incineration and refuse-derived fuel facilities, Explain the C...

Explain the Conventional Incineration and Refuse-Derived Fuel Facilities? 1. Conventional (Mass-Fired) Incineration most common form of municipal solid waste (MSW) incin

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Method to calculate the loss of prestress, Method to calculate the loss of ...

Method to calculate the loss of prestress When the consider creep in regard to loss of prestress, we have to see that the prestressed member is under compressive stresses due

3-d stress, If the resultant forces are resolved in the three co-ordinate d...

If the resultant forces are resolved in the three co-ordinate directions and divided by the area of the face of the cube we have the general state of 3-dimensional stress as shown.

Float or slack of an activity is positive or negetive, 1. What take place w...

1. What take place when float or slack of an activity is positive Ans: It represents a situation where extra resources are available and the completion of the project is not de

Construct the shear force and bending moment diagrams, A Beam A B 12 meter ...

A Beam A B 12 meter long rests on supports 9 meter apart the right hand end over hanging the supports by 1 m and the left hand end by 2 m . The beam carries a uniformity distribute

Explain interim inspection - underwater inspection of bridge, Explain the I...

Explain the Interim inspection - underwater inspection of bridge An interim inspection is an inspection scheduled at the discretion of the engineer. An interim inspection is us

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd