Explain the rippl diagram or mass diagram, Civil Engineering

Assignment Help:

Explain the Rippl Diagram or Mass Diagram

For a potable water reservoir, it is the simultaneous plots of the cumulative inflow and cumulative water consumption/demand, termed "draft" in units of volume (y-axis) vs. consecutive hours, days, months or years (x- axis). In these types of problems, water demand will be at a constant rate to generate a straight, constant sloped line on the plot.

The cumulative inflow will be a curved plot based on gains and losses to the reservoir. The storage volume needed is the separation between a trough (low point on the plotted curve) and a peak (inputs greater than the demand . At some high point on the plotted curve will indicate when reservoir capacity is full releasing water over the spillway may be necessary.


Related Discussions:- Explain the rippl diagram or mass diagram

Construction, #questidisadvantage of steelon..

#questidisadvantage of steelon..

Calculate benefit cost ratio of most cost effective device, A city is tryin...

A city is trying to decide which of two traffic devices to install. Device A costs $1000 and has useful life of five years.  Device A can be expected to result in $300 savings annu

#title., Ask question #Minimum 100 words accepted2812539076# you

Ask question #Minimum 100 words accepted2812539076# you

Determine about the statement - failure at cracking load, Determine about t...

Determine about the statement - Failure at Cracking Load This brittle mode of failure is likely to occur in those pre-stressed elements that are concentrically pre-stressed wit

Method of construction of a bored cast-in-situ concrete pile, Q. Method of ...

Q. Method of construction of a bored cast-in-situ concrete pile? Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole

Can you explain curved heads, Q. Can you explain Curved heads ? In case...

Q. Can you explain Curved heads ? In case of rivers carrying high discharges of the order of 28300 m 3 Is and above, Gale's recommendations are more conservative than Spring's

Flooring, construction detail of all types of flooring

construction detail of all types of flooring

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd