A project consists of activities A, B, C, D, E, F, and G. The precedence relationships and the estimated times to complete each activity are given below: Activity Preceding Activity Estimated Time (in days) A - 12 B A 5 C A 10 D A 3 E D 3 F C, D 7 G E, F 5 Additionally, activity ‘B' can start after 2 days work has been completed on activity ‘A' and activity C can start after 6 days work has been completed on activity ‘A'. Activity G can start only after 3 days have elapsed after the completion of activity ‘E'. Draw an Activity on Node Network for this project. Find the ES, EF, LS, LF, TF and AF for each activity assuming that the 36 days are available to complete the project. Identify the critical activities using the TF calculated by you. Draw a Gantt chart showing all the activities as bars from ES to EF. Plot the staffing requirement plot showing staffing requirements for each day assuming each activity requires one person working on it. Show how you can smooth out the staffing requirements by taking advantage of TF and AF.
When JetBlue left their customers sitting on the tarmac for hours on Valentine's Day, and their CEO was ultimately terminated as a result, the company was responding to (pick the b
Using the competing values framework as a point of reference, how would you describe the current organizational culture? Provide examples to support your conclusions.
1 Page maximum for the whole question] : College students are "invincible". They study on the floor, spread their materials on the floor and lean over to access them, slouch in a c
"CIOs" Please respond to the following: •Assess the role of the CIO within any health care organization and describe the key characteristics a CIO would need to possess to be effec
Which of the following charts is used to monitor the total number of defects per unit when a constant subgroup size is employed? s-chart c-chart p-chart u-chart
Oregon Productivity Matrix - Performance Measures The Oregon productivity matrix (OPM) was developed in Oregon State University in 1986 and measures accomplishments against go
Hill Approach to Manufacturing Operations - Operation Management Hill's five step approach to developing manufacturing operations illustrated in table below (Hill, 1993). A
Michael Plumb's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A B C D A - 4 9 7 B - - 6 8 C - - - 10 D - - - - means the pr
Job redesign requires organizational change. What barriers to change exist within most organizations, and how might they be overcome? I know these are some barriers, but I don't fe
What do your contingency plan in case your plan of action doesn't work?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd