Explain the permissible settlement, Civil Engineering

Assignment Help:

Q. Explain the Permissible Settlement?

Any foundation may fail in shear or by excessive settlement. The failure due to shear is checked by adopting safe value of bearing capacity. The failure due to excessive settlement can be checked by adopting values of permissible settlement for different structures which will not cause distress to the structure. The Indian Standard Code (IS 1904 - 1986, Third revision) suggests that for most of the concrete structures (flats, factories, offices, library) the angular distortion to be within 11500 normally and 111000 where it is desired to avoid any kind of damage. It also recommends that a maximum total settlement should be limited to the value given in Table 4.10.

1829_Explain the Permissible Settlement.png

Table: Permissible Dflerential Senlement


Related Discussions:- Explain the permissible settlement

Types of cement, Types of Cement In addition to ordinary Portland ceme...

Types of Cement In addition to ordinary Portland cement there are various varieties of cement. Significant varieties are briefly explained below: (i) White Cement: The ce

Doors, About Doors,windows&vendilators

About Doors,windows&vendilators

Warm mix asphalt., how it different from hot mix asphalt . is it changes an...

how it different from hot mix asphalt . is it changes any performance compared to hot mix asphalt

Improvements to public bus transport, Improvements to Public Bus Transport:...

Improvements to Public Bus Transport: Since buses carry a large number of passengers, improvements in bus transport is a cheap solution. Some of the possible improvements are

Stones, what are the different type of stones?

what are the different type of stones?

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Depth of boring for multi-storeyed building, Depth of Boring  for Multi-st...

Depth of Boring  for Multi-storeyed Building Peck has recommended that first drill hole is to be made up to depth at which the presence of a thick layer of soft clay with a hig

Explain the modular incinerators, Explain the Modular Incinerators 1. P...

Explain the Modular Incinerators 1. Prefabricated units with capacities of 4.5 to 107 tons of solid waste/day 2. Most use a system involving two combustion chambers.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd