Q. Explain the Permissible Settlement?

Any foundation may fail in shear or by excessive settlement. The failure due to shear is checked by adopting safe value of bearing capacity. The failure due to excessive settlement can be checked by adopting values of permissible settlement for different structures which will not cause distress to the structure. The Indian Standard Code (IS 1904 - 1986, Third revision) suggests that for most of the concrete structures (flats, factories, offices, library) the angular distortion to be within 11500 normally and 111000 where it is desired to avoid any kind of damage. It also recommends that a maximum total settlement should be limited to the value given in Table 4.10.

1829_Explain the Permissible Settlement.png

Table: Permissible Dflerential Senlement


Related Discussions:- Explain the permissible settlement

Write short note on skv process of thermit welding, Q. Write short note on...

Q. Write short note on SKV  process of thermit welding? This term is used for welding by Alumino thermic process with short preheat time. The time required for preheat with pet

Sulphate-resisting cement not used in marine concrete, Question Explain...

Question Explain the reason why is sulphate-resisting cement not used in marine concrete ? Answer Major components of Portland cement are tricalcium silicate, dicalciu

Chain survrying, How do we overcome obstacle like river in chain survey?

How do we overcome obstacle like river in chain survey?

Explain stopping sight distance on horizontal curve, Explain Stopping Sight...

Explain Stopping Sight Distance on Horizontal Curve Section Obstructions along the inside of curves can limit the available (chord) sight distance. A curve must be designed tha

Moisture-density relationship, Moisture-Density Relationship: Since va...

Moisture-Density Relationship: Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-kn

#title, how to convewrt wcb into rcb

how to convewrt wcb into rcb

Verify the total active thrust on the wall per lineal metre, A smooth backe...

A smooth backed vertical wall is 6.3 m high and retains a soil with a bulk unit weight of 18 kN/m 3 and φ = 18°. The top of the soil is level with the top of the wall and is horiz

Timer, grading classification

grading classification

Project management, planking and strutting for shallow excavation

planking and strutting for shallow excavation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd