Explain the equation for a suppressed rectangular weir, Civil Engineering

Assignment Help:

Explain the Equation for a Suppressed Rectangular Weir

If the approach velocity is negligible, velocity head can be excluded and the equation becomes the Francis weir equation:

      Q = 2/3 C1b√2g H1.5= Q = 3.33L H1.5

C1 = Rehbock coefficient to account for all assumptions, usually given as 0.61 or 0.62. The equation to calculate the Rehbock coefficient is in references.


Related Discussions:- Explain the equation for a suppressed rectangular weir

Calculate the natural frequency of the system, A machine weighing 500 kN is...

A machine weighing 500 kN is mounted on a concrete block resting on soil. The base area of the block is 25 m 2 , and the weight is 100 kN. The coefficient of elastic uniform com

Explain critical factor in design of shock transmission unit, Explain Criti...

Explain Critical factor in Design of shock transmission unit? (a) STUs are unidirectional devices for load transmission. If out of plane forces will be acting on the STU, the a

Utilisation of buoyancy effect, Q. Utilisation of Buoyancy Effect? Subm...

Q. Utilisation of Buoyancy Effect? Submerged part of the substructure will be subjected to buoyancy effect. The uplift pressure from the ground water can be utilised by constru

Theory of structure, How to convert uniformly varying load to point load

How to convert uniformly varying load to point load

Widening on curves, Widening on Curves: Pavements have to be widened ...

Widening on Curves: Pavements have to be widened on curves because of the fact that : (a) the vehicle has a wheel base and overhang on the front and rear, and the vehicle

Calculate the surface dimensions of sedimentation tank, Calculate the surfa...

Calculate the surface dimensions of Sedimentation Tank A treatment plant upgrade calls for design of sedimentation basins to handle a flow rate of 8 MGD. The basins are for a T

Need Answer, EXPLAIN THE STRUCTURE OF EXOGENEOUS TREE WITH DIAGRAM ?

EXPLAIN THE STRUCTURE OF EXOGENEOUS TREE WITH DIAGRAM ?

Construction of embankment, Construction of Embankment: The following...

Construction of Embankment: The following steps describe embankment construction : (a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd