Explain the coordinate system, Civil Engineering

Assignment Help:

Explain the Coordinate System

1. A Benchmark provides only elevation data.

2. Coordinate System provides northing and easting coordinates within a defined system.

3. Coordinates require a minimum of eight significant digits.

4. The project site coordinates and datum are referenced by the State Plane Coordinate System

5. State Plane Coordinate System is represented as a grid map of the United States where coordinates are referenced within the 1st Quadrant.


Related Discussions:- Explain the coordinate system

How to evaluate quality of bricks, Q. How to evaluate quality of Bricks? ...

Q. How to evaluate quality of Bricks? 1. Clour -Deep red, Carry red, Copper red, colour is indication of uniform burning and also suggests quality of clay used. Over brunt bric

What is a pressure bulb, What are the basic assumptions in Boussinesq's the...

What are the basic assumptions in Boussinesq's theory of stress distribution in soils? Illustrate the vertical stress distribution on a horizontal plane at a given depth and also t

Diffrence between single and double-cell box culvert, Q. Diffrence between ...

Q. Diffrence between Single and double-cell box culvert? The usage of double-cell box culverts is preferred to single-cell box culverts for cross-sectional area larger than abo

Water-bound macadam road construction for unpaved roads, how can I come up ...

how can I come up with the research on the water bound macadam road construction

Example for productivity analysis and improvement, Example for Productivity...

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

Assignment, on timber, varieties , preservation, and seasoning of timber

on timber, varieties , preservation, and seasoning of timber

Break even point, Break even point: EM Electricals, Inc., contains fix...

Break even point: EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200

Strength of materials, Enlongations in solids based on elastic constants

Enlongations in solids based on elastic constants

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd