Explain the Bolted Connections

a) Questions generally relate to the size of the bolt needed for a connection or

b) Number of bolts for a given loading and specified size

c) Shear capacity of bolts is given for single shear connections only.  Most common check is for shear in a bearing type connection.

d) The designation of X and N in the table for available bolt strength relates to the threads on the bolt being iN the shear plane (325-N) and not in the shear plane (325-X).

e) The bearing strength at a specific bolt hole typically does not govern a design but must be checked nonetheless.The edge distance from the bolt to the edge of the member in the direction of the applied force is crucial (Lc shown in supplied material).


Related Discussions:- Explain the bolted connections

Concrete, if the slump of concrete drops how to rectify

if the slump of concrete drops how to rectify

Survey, Procedures of graphical interpolation

Procedures of graphical interpolation

BOLTED CONNECTIONS, compare riveted joints with welded joints

compare riveted joints with welded joints

State the loss of prestress, State the Loss of prestress Loss of prestr...

State the Loss of prestress Loss of prestress due to elastic shortening definitely occurs in pre-tensioned concrete members. But in post-tensioned members it does not occur if

What are aquifers - hydraulics system, What are Aquifers? Water bearing...

What are Aquifers? Water bearing, underground geologic formations. The subsurface formations are composed of soils and rocks with voids saturated with water.

Rolling - binder, Rolling - Binder: The layer thickness is 40-50 mm. R...

Rolling - Binder: The layer thickness is 40-50 mm. Rolling is done in three stages : Initial Rolling By 80-100 kN smooth wheeled roller. Intermediate Rolling B

Bmc, what is a masonry

what is a masonry

Som, Maximum thermal stress in circular tapering section is

Maximum thermal stress in circular tapering section is

Length is constructed in first phase of construction, In construction of a ...

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd