Explain the Bolted Connections

a) Questions generally relate to the size of the bolt needed for a connection or

b) Number of bolts for a given loading and specified size

c) Shear capacity of bolts is given for single shear connections only.  Most common check is for shear in a bearing type connection.

d) The designation of X and N in the table for available bolt strength relates to the threads on the bolt being iN the shear plane (325-N) and not in the shear plane (325-X).

e) The bearing strength at a specific bolt hole typically does not govern a design but must be checked nonetheless.The edge distance from the bolt to the edge of the member in the direction of the applied force is crucial (Lc shown in supplied material).


Related Discussions:- Explain the bolted connections

Window, sliding window lowered window sash or glazed window circular window...

sliding window lowered window sash or glazed window circular window

Show the continuous piezocone penetration test, Q. Show the Continuous Piez...

Q. Show the Continuous Piezocone Penetration Test? Continuous piezocone penetration test essentiallycomprises standard cone penetration test and a measurement of pore water pre

#memory, assign for memory unit

assign for memory unit

Reduced levelling, what is the theary of reduced levelling

what is the theary of reduced levelling

Determine the coordinate for point r, For the project work points (x,y) sho...

For the project work points (x,y) shown in the figure the bearing of point R is due West. The coordinate for point R is most nearly:    Solution: Determine the length o

Traditional granular sub-base, Question For rigid pavement, what is rec...

Question For rigid pavement, what is recompense of using lean concrete sub-base instead of traditional granular sub-base? Answer There are some shortcomings of using

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd