Explain the bernoulli energy equation, Civil Engineering

Assignment Help:

Explain the Bernoulli Energy Equation

Accounts for the fluid energy at any point in a fluid flow system. Units are in ft. Developed for energy without friction. The total energy of a fluid flowing without friction losses is constant, but the energy associated with each component may vary.  Including  hƒ (head or energy lost due to friction) accounts for the loss of energy from point 1 to point 2 in a fluid system.   

(p/γ)1 + (v2 /2g)1 + (Z)1 = (p/γ)2 + (v2/2g)2 + (Z)2 + hƒ

Three components:

Pressure energy = p/γ 

γ = specific weight of fluid  

Units = ƒt = (lb/ƒt2) / (lb/ƒt3)  

Velocity energy = v2/2g 

Units = ƒt = (ƒt/sec)2/2(ƒt/sec2)  

Potential energy = Z

Units = ƒt

Total Energy = Pressure + Kinetic + Potential Energies


Related Discussions:- Explain the bernoulli energy equation

What is oil interceptors, Q. What is Oil interceptors ? Oils and Grease...

Q. What is Oil interceptors ? Oils and Grease are usually found in stormwater runoff from catchments. They come from spillage and leakage of fuels, lubricants, Vehicle coolants

Dams, types of dams

types of dams

Define types of inspection of bridge, Define Types of Inspection of Bridge?...

Define Types of Inspection of Bridge? Underwater inspections are generally categorised into five types: - Inventory - Routine - Damage - In-depth - Interim

Autocad, pls explain about this field

pls explain about this field

Spun pipes, what is flush joint and confined joint in rcc spun pipes?

what is flush joint and confined joint in rcc spun pipes?

What is the tensile strength of wood, The tensile strength of a material is...

The tensile strength of a material is the value at which the material fails when subjected to a tensile force. (Tensile means a force pulling the wood fibers lengthwise, as opposed

Variations of tendon stresses in pre tensioned concrete, Variations of tend...

Variations of tendon stresses in pre or post-tensioned concrete Variations of tendon stresses in pre or post-tensioned concrete members, along the length of tendons, may be of

Calculate the total labor cost per cubic yard, A contractor will place 90-c...

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placem

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd