Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Electron beam focused to a fine spot, Q. How is the electron beam focused t...

Q. How is the electron beam focused to a fine spot on the face of the CRT? Sol. The functional diagram of an electrostatic focusing arrangement is shown below. The pre-accele

Thermal Transducers, what is the working of thermal transducers?

what is the working of thermal transducers?

Microprocessor, distingish between maximum and minimum modes of operations ...

distingish between maximum and minimum modes of operations of 8086 with timing diagrames

Determine the parameters of the equivalent circuit, No-load and blocked-rot...

No-load and blocked-rotor tests are conducted on a three-phase,wye-connected inductionmotor with the following results. The line-to-line voltage, line current, and total input powe

Illustrate balanced delta-connected load, Next, let us consider the case of...

Next, let us consider the case of a balanced delta-connected load with impedance of 5 45° supplied by a three-phase, three-wire 100-V system, as shown in Figure (a). We shall dete

Bad effects of armature reactions, Q.  What is meant by armature reaction....

Q.  What is meant by armature reaction. Explain briefly the bad effects of armature reactions.   Sol. By armature reaction is meant the effect of magnetic field set up

Cpi compare immediate instruction , CPI Compare Immediate Instruction ...

CPI Compare Immediate Instruction The 8 bit  data  specified  in the  instruction is  compared with the  contents of the accumulator. The comparison  is done by  subtracting

Spread time - power semiconductor devices , Spread Time (t s ) During  ...

Spread Time (t s ) During  spread time anode  voltage  falls from 10% I a  to the  on state  voltage  drop  and anode  current  rises  from 90% I a   to final  value  of anode

Discuss the need of peripheral component interconnect bus, Discuss the need...

Discuss the need of PCI bus. Peripheral Component Interconnect (PCI): It was developed by Intel and introduced in 1993 year. This is geared particularly to fifth- and sixth-

PSpice Project, I would send the project file so you can take a look at it....

I would send the project file so you can take a look at it.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd