Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Compute the real power inductive load, Q. A 60-Hz, 440-V, three-phase syste...

Q. A 60-Hz, 440-V, three-phase system feeds two balanced wye-connected loads in parallel. One load has a per-phase impedance of 8 + j3  and the other 4 - j1 . Compute the real po

Consider the circuit of the noninverting amplifier, (a) Consider the circui...

(a) Consider the circuit of the noninverting amplifier in Figure, including an ideal op amp. Obtain an expression for the voltage gain of the overall circuit. (b) Let R i = 10

Explain circuit with capacitive load, Circuit with capacitive load Capa...

Circuit with capacitive load Capacitors which obey the relationship of equation are linear capacitors, since the potential difference among the conductive surfaces is linearly

Encoder, decimal to BCD code encoder active low

decimal to BCD code encoder active low

Assembly language instructions, Normal 0 false false false ...

Normal 0 false false false EN-IN X-NONE X-NONE

Explain rs422a standard, Explain RS422A standard. RS422A: 1.  Date...

Explain RS422A standard. RS422A: 1.  Date Rate: 10 Mbits per second 2.  Driving capability up to 4000ft and 10 receivers 3.  This is Differential standard that is- a

Examples of attribute data relevant for a power utility, Examples of attrib...

Examples of attribute data relevant for a power utility: Examples of attribute data relevant for a power utility are given below. •          Consumer data such as categor

ET1410, MODULE 2 EXERCISE: OP-AMP CONFIGURATION

MODULE 2 EXERCISE: OP-AMP CONFIGURATION

Explain pulse-code modulation, Q. Explain Pulse-Code Modulation? PCM is...

Q. Explain Pulse-Code Modulation? PCM is the simplest and oldest waveform coding scheme for processing an analog signal by sampling, quantizing, and binary encoding. Figure sho

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd