Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Not gate- introduction microprocessors , Normal 0 false fals...

Normal 0 false false false EN-IN X-NONE X-NONE

Find the fourier-series expansion of the pulse train, The rectangular pulse...

The rectangular pulse train of Figure (a) consists of pulses of height A and duration D. Such pulse trains are employed for timing purposes and to represent digital information. Fo

Explain mechanisms of propagation of radio communication, Explain mechanism...

Explain mechanisms of propagation of radio communication. Radio communication deals with electronic radiation of electromagnetic energy from one point to another through atmosp

Dual beam, explane the special features of dual beam?

explane the special features of dual beam?

Explain overhead lines and transformers, Explain Overhead Lines and Transfo...

Explain Overhead Lines and Transformers? Overhead lines absorb reactive power when fully loaded. A line with a current I A, a line reactance of X L ?/phase absorbs I 2 X L V

D flip-flop - latch or delay element, Q. D flip-flop - latch or delay eleme...

Q. D flip-flop - latch or delay element? The symbol for the clocked D flip-flop is shown in Figure (a), in which the two output terminals Q and ¯ Q behave just as in the SRFF,

Illustrate the construction and working of thermistor, Illustrate the const...

Illustrate the construction and working of:- (i) Pressure Thermometer (ii) Selective Radiation Pyrometer (iii) Thermistor (iv) Laws of Thermocouple

Name the flag available in status register of 8086, What are the different ...

What are the different flag available in status register of 8086? There are Six flags are present. They are, AF - Auxiliary Carry Flag CF - Carry Flag OF - Ove

#t voice controlled mobile base, The aim of this project is to design, co...

The aim of this project is to design, construct and build a motorised base driven by two small dc motors. The motor drives are two H-bridges. The switching devices in these bridges

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd