Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Fulfilled to sustain the oscillations, Q. What are the conditions required ...

Q. What are the conditions required to be fulfilled to sustain the oscillations? The conditions required to be fulfilled to sustain the oscillations are: 1. The loop gain mu

Lda load accumulator direct instruction, LDA  Load Accumulator Direct Inst...

LDA  Load Accumulator Direct Instruction This instruction is used to copy  data from  memory whose  address is directly specified in the  instruction to th e accumulator. The i

Explain the architecture of ss7, Q. explain the architecture of SS7 and com...

Q. explain the architecture of SS7 and compare with seven-layer OSI architecture. Ans: A block schematic diagram of CCITT no. 7 signalling system is displayed in figure. Sig

General purpose registers, General  Purpose  Registers Registers B, C...

General  Purpose  Registers Registers B, C ,D, E H , and L   are 8 bit  general  purpose  registers. These  registers store  8 bit  data  temporarily  for processing. Some

Grid connected hybrid pv-wind power system, Hi there, My project title is g...

Hi there, My project title is grid connected hybrid pv-wind power system. For this topic, i need a specification of the system. For this system a matlab and homer software simulati

Determine the speed at which the machine runs as a motor, A 100-kW, dc shun...

A 100-kW, dc shunt generator, connected to a 220-V main, is belt-driven at 300 r/min, when the belt suddenly breaks and the machine continues to run as a motor, taking 10 kW from t

Determine self inductances of coils, Determine self inductances of coils: ...

Determine self inductances of coils: The number of turns in two coupled coils A and B are 600 and 1700 respectively. While a current of 6 A flows in coil B, the total flux in

Wiring a plug , Wiring a Plug : Let us consider the problem of connect...

Wiring a Plug : Let us consider the problem of connecting a 16 A plug, commonly known as 15 A or power plug to an electrical appliance. Do you use any old bit of wire, or any

Explain public mode, Explain PUBLIC For large programs several small mo...

Explain PUBLIC For large programs several small modules are linked together. In order that the modules link together correctly any variable name or label referred to in other m

Register to register , Register to Register  This  instruction  is u...

Register to Register  This  instruction  is used to copy data from the  source  register to the destitution register. The  previous contents on the  destination register wil

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd