Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Describe the two core-excited states, Using the optimized 6-311G(d,p) geome...

Using the optimized 6-311G(d,p) geometry determined in question 1, perform the following equivalent core calculations for any two inequivalent carbons of butadiene: (a) Equivale

Ac waveform, which ckt. Or components using for irregular ac sine wave ...

which ckt. Or components using for irregular ac sine wave change into pure sine wave.......

Find the charge flowing and the number of electrons, Q. A current i(t) = 20...

Q. A current i(t) = 20 cos(2π × 60)t A fows through a wire. Find the charge flowing, and the number of electrons per second that are passing some point in the wire.

How to calculate back pitch, Q.   A 6 - pole, DC armature with 36 slots and...

Q.   A 6 - pole, DC armature with 36 slots and 2 coil - slides/slot is to be wave wound (double layer). Calculate the back pitch, front - pitch and commentator pitch. How many dumm

Basic aspects of electromechanical energy converters, Q. Basic aspects of e...

Q. Basic aspects of electromechanical energy converters? Whereas detailed differences and particularly challenging problems emerge among various machine types, this section bri

Estimate the maximum number of conversions, Q. The speed of an 8-bit A/D co...

Q. The speed of an 8-bit A/D converter is limited by the counter, which has a maximum speed of 4 × 10 7 counts per second. Estimate the maximum number of A/D conversions per secon

Pn junction, the depletion layer in the pn junction is caused by

the depletion layer in the pn junction is caused by

Data bus - bus organisation , Data bus The data  bus is the  group of 8...

Data bus The data  bus is the  group of 8 bit   used  to carry data. There  line are  bidirectional data can flow  in both  directions i e form  microprocessor to  peripherals

Generation and control of electron beam, Illustration the basic working pri...

Illustration the basic working principle, process parameters, economics, safety precautions and applications of plasma Arc Machining process(PAM) Discuss Electron Beam Machining

Induced emf, applications of dynamically induced emf

applications of dynamically induced emf

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd