Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Determine the rotor speed, A four-pole, three-phase inductionmotor is energ...

A four-pole, three-phase inductionmotor is energized from a 60-Hz supply. It is running at a load condition for which the slip is 0.03. Determine: (a) The rotor speed in r/min.

Sketch the circuit with all the relevant labelling, Question: (a) Consi...

Question: (a) Consider the subsequent LC impedance function: (i) If the function is to be realised using the Foster I Form, evaluate the values of the different compon

Commercial fm radio broadcasting, Q. Commercial FM radio broadcasting? ...

Q. Commercial FM radio broadcasting? Commercial FM radio broadcasting utilizes the frequency band of 88 to 108 MHz for the transmission ofmusic and voice signals. The carrier

Plagiarised Content, Your site is full of plagiarised content even though y...

Your site is full of plagiarised content even though you claim to be and I quote "Plagiarism Free". You should not be charging for this content, the site and service is a fraud.

Digital control system, Please suggest recent application of DCS WHICH I CA...

Please suggest recent application of DCS WHICH I CAN USE AS A TOPIC OF MY Ph.D.

Customer data management- power supply, Customer Data Management- Power Sup...

Customer Data Management- Power Supply The concept of data warehouse and data mining could be extremely useful for the management of customer data. A data warehouse is a power

Low and high pass filters - calculate the cutoff frequencies, At the comple...

At the completion of this unit, you will be able to determine the cutoff frequencies and attenuations of RC and RL low- and high-pass filters by using test circuits. UNIT FUNDA

Crossmagnetisation, what is crossmagnetisation in dc generator

what is crossmagnetisation in dc generator

find power flow solution for the system, For the 3 bus system shown below ...

For the 3 bus system shown below all values are given in pu on a 100MVA base (a) Use Matlab functions lfgauss and lfnewton to find power flow solution for the system, accurate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd