Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Describe about reduction clause, Q. Describe about Reduction Clause? Re...

Q. Describe about Reduction Clause? Reduction clause specifies an operator as well as one or more list items. For every list item a private copy is created on every thread and

Define time constant, Time constant Time constant, defines as time for ...

Time constant Time constant, defines as time for current achieve maximum (IM) if this maintain the early promotion rate current.

Define the time constant of the circuit, A coil of inductance 0.04 H and re...

A coil of inductance 0.04 H and resistance 10? is connected to a 120 V, d.c. supply. Verify (a)  The final value of current     (b)  The time constant of the circuit (c)

Corrosion, I want to know whether the circuits for both methods(linear pola...

I want to know whether the circuits for both methods(linear polarization resistance and electrochemical impedance spectroscopy) are same or not?

Smart parking system, Design a smart park system using Iot sensors to udate...

Design a smart park system using Iot sensors to udate stautus to a server ?

Calculate the voltage regulation, The per-phase synchronous reactance of a ...

The per-phase synchronous reactance of a three-phase, wye-connected, 2.5-MVA, 6.6-kV, 60-Hz turboalternator is 10. Neglect the armature resistance and saturation. Calculate the vo

Realize the function f by a k map using 0s, Q. Given the following truth ta...

Q. Given the following truth table: (a) Realize the function f by a K map using 0s. (b) Realize the function f by a K map using 1s.

Mips simulator, The coursework requires you to work in pairs to write a Jav...

The coursework requires you to work in pairs to write a Java application that will take a numerical representation of a MIPS program and simulate its execution. MIPS is a Load-S

What do you mean by fm stereo, Q. What do you mean by FM Stereo? IT  sh...

Q. What do you mean by FM Stereo? IT  shows the block diagram of an FM stereo transmitter and an FM stereo receiver. The following notation is used: • f L (t), fR(t): Left a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd