Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

What is meant by microcontroller, What is meant by microcontroller? A d...

What is meant by microcontroller? A device which having the microprocessor with integrated peripherals like memory, serial ports, parallel ports, timer/counter, interrupt contr

Show common signal-processing operations, Q. Show Common signal-processing ...

Q. Show Common signal-processing operations? Common signal-processing operations include the following: • Amplification to compensate for attenuation • Filtering to reduc

Derive the equations of the self bias circuit, Q. Derive the equations of t...

Q. Derive the equations of the self bias circuit? A circuit which is used to establish a stable operating point is the self biasing configuration. The circuit is shown in Fig

What is meant by thermal runaway in a transistor, Q. What is meant by therm...

Q. What is meant by thermal runaway in a transistor ? When current flows through the collector circuit, it produces heat at the collector junction. This increases the temperatu

Objectives of electricity and gas hazards, Objectives After studying th...

Objectives After studying this unit, you should be able to: 1. Describe the consequences of passing electric current through human body, 2. State and recognise the colour

Tariff policy - electricity policies, National tariff policy: The Centr...

National tariff policy: The Central Government notified the National Tariff Policy on January 6, 2006, for the power sector in line along with the Section 3 of the EA, 2003. Wi

Compute the theoretical and practical frequency ranges, Q. For an RG-290/U ...

Q. For an RG-290/U aluminum rectangular wave - guide, a = 58.42 cm and b = 29.21 cm. Compute the theoretical and practical frequency ranges of operation for the guide.

What is faithful amplification, What is faithful amplification. What are ba...

What is faithful amplification. What are basic condition for faithful amplification. Describe : (a) Peak Inverse voltage. (b) Maximum forward current. (c) Knee voltage

Factors which affect the inductance of an inductor, Factors which affect th...

Factors which affect the inductance of an inductor include:  i)  The number of turns of wire (N) - more turns the higher the inductance ii)  The cross-sectional area of the

Stop and wait flow control protocol, (a) Explain what asynchronous transmis...

(a) Explain what asynchronous transmission is and give two advantages and two disadvantages of using this type of transmission. (b) One of the goals of multiplexing is efficienc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd