Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Determine l and c of the band pass filter circuit, Q. Determine L and C of ...

Q. Determine L and C of the band pass filter circuit of Figure to have a center frequency of 1 MHz and a bandwidth of 10 kHz. Also find the Q of the filter.

Compute the force, Q. Consider a current element I 1 d ¯ l 1 = 10 dz ¯ az...

Q. Consider a current element I 1 d ¯ l 1 = 10 dz ¯ az kA located at (0,0,1) and another I 2 d ¯ l 2 = 5dx ¯ ax kA located at (0,1,0). Compute d ¯ F 21 and d ¯ F 12 experienc

Introduction to electronics, Explain the difference between a microprocesso...

Explain the difference between a microprocessor and an embedded microcontroller

Robotic, Ask questCompute the mean and variance of a four-level image with ...

Ask questCompute the mean and variance of a four-level image with histogram p(z\ ) = 0.1, p{zi) = 0.4, ?(1?) =0.3, p{za) = 0.2. Assume that z\ = 0, zi = 1, z$ = 2, and ? — ?. i

Find the per-phase impedance of the load, Q. The two-wattmeter method for m...

Q. The two-wattmeter method for measuring three-phase power is applied on a balanced wye-connected load, and the readings are given by W C = 836W and W A = 224 W If the system

Carrier concentrations, Carrier Concentrations For the calcu...

Carrier Concentrations For the calculation of semiconductor electrical properties and analyzing device behavior, it is necessary to know the number of charge carrier

Define amplification factor and drain resistance, Q. Define amplification f...

Q. Define amplification factor, drain resistance and transconductance and derive the relationship between drain resistance and trans conductance? Drain resistance It is the

Explain fourth group of 32 ascii character code, Explain Fourth group of 32...

Explain Fourth group of 32 ASCII character code? The fourth, and final, group of 32 ASCII character codes are set aside for the lower case alphabetic symbols, five additional

Energy band diagram, E n e r gy Band Diagram Energy band d...

E n e r gy Band Diagram Energy band diagram in qualitative form is sketched by following the following process: 1. The semiconductor device is supposed to be ma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd