Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Prepaid meters, Prepaid Meters Prepaid metering is a system whereby co...

Prepaid Meters Prepaid metering is a system whereby consumers purchase electricity by a smart card. The amount paid together along with other information is encoded in the sma

Find the forced component of the current, Q. Consider an RC parallel circui...

Q. Consider an RC parallel circuit excited by (a) i(t) = 20e -2t A, and (b) i(t) = 20 A. Find the forced component of the current through the capacitor for R = 2  and C = 2F.

Example of clamper circuits, Example of clamper circuits: Example of c...

Example of clamper circuits: Example of clamper circuits are as follow Voltage multiplier circuit: voltage circuit is employed to maintain a relatively low transformer pe

Network analysis, expain how to do proper initial approximatio for the give...

expain how to do proper initial approximatio for the given cct....... by a example

What is permeability of magnetic materials, Q. What is permeability of magn...

Q. What is permeability of magnetic material? For magnetic material media, the magnetic flux density B, expressed in tesla (T) or Wb/m 2 , and the field intensity H, expressed

Turn off time - thyristor, Turn off Time This is also known  as gate...

Turn off Time This is also known  as gate controlled  turn on  time. The time  interval between  a specified  point at the beginning  of the  gate pulse  and the  instant wh

What are transmission bridges, Q. What are transmission bridges? How do the...

Q. What are transmission bridges? How do they assist in satisfying the connectivity?  Ans: A typical transmission bridge is demonstrated in figure. Series capacitance and shunt

Quality control systems, Give three reasons why a chamfer shouldn't be cons...

Give three reasons why a chamfer shouldn't be considered an "unimportant" dimension. When conducting an audit, what is the first step and what is its purpose? Why will calcul

Time constant at decay of current, Time constant at decay of current In...

Time constant at decay of current In decay of current by an inductor, a method to find values of time constant similar as in rise of current through an inductor. The difference

Explain fundamentals of load flow analysis, Explain Fundamentals of Load Fl...

Explain Fundamentals of Load Flow Analysis The calculation of electrical power system load flow or current flow is a problem which has no direct solution. It is not that a solu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd