Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

FET operation, ON output plot of a JFET n-channel transistor if ID is close...

ON output plot of a JFET n-channel transistor if ID is close to IDSS does the value of VGS close to VP?

Revision of basics, Revision  of Basics Although  it is  assumed in th...

Revision  of Basics Although  it is  assumed in this book  that the  reader has  enough  knowledge of  various number systems ( binary, octal and hexadecimal and their relation

Nand gate - introduction to microprocessors , NAND Gate NAND   means NO...

NAND Gate NAND   means NOT AND  it complements  the output  of an AND  gate. The symbol  of NAND  by a NOT  gate.  Generally Not  operation  is represented by a bubble as shown

Evaluate supply and the supply power factor, Q. Two balanced, three-phase, ...

Q. Two balanced, three-phase, wye-connected loads are in parallel across a balanced three-phase supply. Load 1 draws a current of 20 A at 0.8 power factor leading, and load 2 draws

Mov instruction, MOV Instruction Op code  format  of MOV  instruction i...

MOV Instruction Op code  format  of MOV  instruction is as follows : Replace the  codes of destination register and source  register with code of  required  register from.

Minimize f in a pos form and obtain a possible realization, Q. The truth ta...

Q. The truth table for F(A,B,C) = Mi (0, 1, 6, 7) is as follows: (a) Express F in a canonical product-of-sums form. (b) Minimize F in a POS form and obtain a possible re

Calculate reactive power to be delivered by the capacitor, A single-phase s...

A single-phase source delivers 100 kW to a load operating at 0.8 lagging power factor. In order to improve the system's efficiency, power factor improvement (correction) is achieve

Gis for distribution network management, Gis for Distribution Network Manag...

Gis for Distribution Network Management: You are well aware of the problems facing the distribution utilities to meet the day-to-day requirements of the power consumers, like

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd