Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

How typical dma controller can be interfaced to 8086/8085, Show how a typic...

Show how a typical DMA controller can be interfaced to an 8086/8085 based maximum mode system. For 8088 in maximum mode: The RQ/GT1 and RQ/GT0 pins are utilized to issue DMA

What are the advantages of using robots, What are the Advantages of using r...

What are the Advantages of using robots -  They are able to work non-stop; they don't need a break -  They are capable of working in conditions hazardous to humans -  Ess

Cmos processes, CMOS processes: The low-performance "lateral" bipolar ...

CMOS processes: The low-performance "lateral" bipolar transistors occasionally employed in CMOS processes are sometimes designed symmetrically, i.e., with no distinction betwe

Transformers., Calculations of sending line voltage

Calculations of sending line voltage

What digits are represented by the signal, A signal stands for 0110 with po...

A signal stands for 0110 with positive logic in which low stands for 0 and high stands for 1. If negative logic (in which low stands for 1 and high stands for 0) is used, what digi

3-phase 180 degree mode vsi , 3-phase 180 0 mode VSI In 1800 mode VSI...

3-phase 180 0 mode VSI In 1800 mode VSI  each thyristor  conduct  for 1800 and two  thyristor  are fired  at 600 interval. For  example  if thyristor  T1  is fired at 00 then

Determine the dielectric constant of slab, Determine the Dielectric constan...

Determine the Dielectric constant of slab: An air capacitor contains two parallel plates 10 cm 2 in area and 0.5 cm apart. While a dielectric slab of area 10 cm2 and thicknes

Analysis of frequency response with pspice and probe, Analysis of Frequency...

Analysis of Frequency Response with PSpice and PROBE PSpice can readily accomplish the circuit analysis as a function of frequency, and PROBE can display Bode plots for magnitu

Distinguish between harmonized and non-harmonized standards, (a) A digital ...

(a) A digital product is being tested for compliance to CISPR 22 Class A requirements. The receiving antenna is placed a distance of 30 m away and is attached to a 50 V receiver w

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd