Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Determine the required tapping on the transformer, An induction motor has a...

An induction motor has a starting current that is 6 times the full-load current and a per-unit full- load slip of 0.04. The machine is to be provided with an autotransformer starte

Explain priority interrupts of 8085, Explain priority interrupts of 8085. ...

Explain priority interrupts of 8085. The 8085 microprocessor has five interrupt inputs. They are TRAP, RST .5, RST 6.5, RST 5.5, and INTR. These interrupts have a fixed prio

What is the difference between near call and far call, What is the differen...

What is the difference between near call and far call? The PROC directive specifies the start of a procedure, should also be followed along with a NEAR or FAR. A NEAR procedure

Electrical, do you have a place where I can draw the equation out ?

do you have a place where I can draw the equation out ?

Explain acceptance cone, Explain Acceptance cone? The fibre air - core ...

Explain Acceptance cone? The fibre air - core interface is display below: In this figure Omax is the maximum angle, inside that the rays undergo total internal reflecti

Fabrication and testing laboratory, You will manufacture composite beams us...

You will manufacture composite beams using an epoxy matrix (West Systems 105 epoxy resin + West Systems 206 slow hardener) and one of the following reinforcements:  1.  Unidirec

Weighted-resistor converter, Q. WEIGHTED-RESISTOR CONVERTER? Figure sho...

Q. WEIGHTED-RESISTOR CONVERTER? Figure shows a 4-bit weighted-resistor D/A converter which includes a reference voltage source, a set of four electronically controlled switches

What do you mean by counters, Q. What do you mean by Counters? The shif...

Q. What do you mean by Counters? The shift register can be used as a counter because the data are shifted for each clock pulse. A counter is a register that goes through a pred

Diod, explain the application of the Si,zener,and LED diodes

explain the application of the Si,zener,and LED diodes

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd