Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Discuss the function of instruction queue in 8086, Discuss the function of ...

Discuss the function of instruction queue in 8086? In 8086, a 6-byte instruction queue is presented at the Bus Interface Unit (BIU). It is used to pre fetch and store at the ma

Define voltage source multiplying dac, Define Voltage Source Multiplying DA...

Define Voltage Source Multiplying DAC? Voltage source multiplying DACs use a reference voltage which is switched in or out by the digital data.  The converter is so-named becau

Explain the working of rectifier circuits, Q. Explain the working of Rectif...

Q. Explain the working of Rectifier Circuits? A simple half-wave rectifier using an ideal diode is shown in Figure(a). The sinusoidal source voltage v S is shown in Figure (b)

Determine the efficiency of the transformer, 1.    A 230/1000V 50 Hz, singl...

1.    A 230/1000V 50 Hz, single phase transformer has the following test data: Open circuit test (L.V.) Primary voltage = 230V Primary current = 1.30 A Input power

Sketch the d.c. equivalent circuit of the amplifier, Question: Figure s...

Question: Figure shows the basic circuit of the BJT Common Emitter Amplifier. (a) What is the function of RB, RC, Ci, Co and CE ? (b) (i) Sketch the d.c. equivalent circu

Derive the expression for steady state error, Derive the mathematical expre...

Derive the mathematical expression for steady state error of first order system with unit ramp signal. Discuss the following - proportional cum integral control - proporti

Types of multiplexing techniques, (a) List three types of Multiplexing tech...

(a) List three types of Multiplexing techniques. (b) Give two advantages of "Multiplexing". (c) Given the total duration for the signal is 8 ns. What is the bit rate for

When input is a triangular wave, Q. When input is a triangular wave. W...

Q. When input is a triangular wave. When the input fed to differentiating circuit is a triangular wave, the output will be a rectangular wave. During the period OA of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd