Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Transistors, how fet transistor works in self bias

how fet transistor works in self bias

Instruction set architecture, assume that the top of the stack in the progr...

assume that the top of the stack in the program is pointed by the register sp.

State diagram for a typical von neumann machine, Question: a) Give the ...

Question: a) Give the instruction cycle state diagram for a typical Von Neumann machine. b) Give two diagrams to differentiate between a Memory and CPU connections. c) Co

Rc phase shift, what is the equation for rc phase shift oscillator?

what is the equation for rc phase shift oscillator?

Methods of material handling, Q. Show the Methods of material handling? ...

Q. Show the Methods of material handling? Methods of material handling during operations and maintenance activities shall be considered for all facilities to ensure that the fi

Find the transfer function of a linear system, Q. The response y(t) of a li...

Q. The response y(t) of a linear system to an excitation x(t) = e -2t u(t) is y(t) = (t + 2)e -t u(t). Find the transfer function.

Traffic light display, Traffic Light Display Design a three color LED sy...

Traffic Light Display Design a three color LED system with the following times for each LED: Duration of Green signal : 16s Duration of Yellow signal : 1s Duration of R

Water.., hot and cold lime soda process

hot and cold lime soda process

Prepaid meters, Prepaid Meters Prepaid metering is a system whereby co...

Prepaid Meters Prepaid metering is a system whereby consumers purchase electricity by a smart card. The amount paid together along with other information is encoded in the sma

Hlt halt instruction , HLT Halt Instruction The microprocessor halts  ...

HLT Halt Instruction The microprocessor halts  the execution  of the  program and enters into  the wait  state  the address  and data bus are placed in the  high  impedance st

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd