Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Show quantization error, Quantization Error Sampling followed by quanti...

Quantization Error Sampling followed by quantization is equivalent to quantization followed by sampling. Figure illustrates a message signal f (t) and its quantized version den

find power flow solution for the system, For the 3 bus system shown below ...

For the 3 bus system shown below all values are given in pu on a 100MVA base (a) Use Matlab functions lfgauss and lfnewton to find power flow solution for the system, accurate

Emitter follwer, Ask questertion #Minimum 100 words accepted#

Ask questertion #Minimum 100 words accepted#

Triode mode, Triode Mode When   V GS   > V th   and   V DS...

Triode Mode When   V GS   > V th   and   V DS   GS   - V th ) The transistor is turned on, and a channel has been created that allows current to

Fraction of the total cross section - interaction processes, Determine and ...

Determine and plot for 5 keV to 100 MeV the fraction of the total cross section due to each of the four interaction processes for      (a) hydrogen,      (b) nitrogen,

Power, why do we use commutator?

why do we use commutator?

Help needed in degree project, i have to design a project title "Edge deter...

i have to design a project title "Edge determining techniques for Low quality images in different lighting conditions and we use matlab for images simulation by changing different

Logistical management - gis applications, Logistical management - Gis appli...

Logistical management - Gis applications: Using GIS also allows a radical improvement in daily work management practices - such as planning new installations, scheduling opera

Comparison of analog-modulation systems, Comparison of Analog-Modulation Sy...

Comparison of Analog-Modulation Systems The comparison of analog modulation systems (conventional AM, DSB SC, SSB SC, VSB, FM, and PM) can be based on three practical criteria:

What is extended data output ram, What is extended data output RAM? EDO...

What is extended data output RAM? EDO RAM: A slight modification to the DRAM structure changes the device in an EDO (extended data output) DRAM device. Inside the EDO memory, a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd