Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Calculate the reflection of wedge, The corners of wedge-shaped block are A(...

The corners of wedge-shaped block are A(0,0,2), B(0,0,3), C(0,2,3), D(0,2,2), E(-1,2,2) and F(-1,2,3) and the reflection plane goes the Y-axis at 450 between (-X) & (Z) axis. Calcu

Describe properties of the conducting materials, Describe properties of ...

Describe properties of the conducting materials . Conducting materials are classified by low resistivity materials and high resistivity materials. Low resistivity mater

Show effects of saliency and saturation, Q. Show Effects of Saliency and Sa...

Q. Show Effects of Saliency and Saturation? Because of saliency, the reactancemeasured at the terminals of a salient-pole synchronousmachine as opposed to a cylindrical-rotor m

Explain the nor gates - microprocessor, Explain the NOR GATES - Microproces...

Explain the NOR GATES - Microprocessor The NOR GATE is an OR gate with the output inverted. Consequently the outputs of a NOR gate would have the opposite states as the outputs o

Control system, what is the difference between the continuous time system ...

what is the difference between the continuous time system and discrete time system and their advnatages?

Mobile communication, #qConsider a point-to-point radio link between two hi...

#qConsider a point-to-point radio link between two highly directional antennas in a stationary environment. The antennas have antenna gains of 30 dB, distance attenuation is 150 dB

Working of a sweep frequency generator, Q. With suitable diagram explains t...

Q. With suitable diagram explains the working of a sweep frequency generator. Sol. A sweep frequency generator or sweeper is a special type of signal generator in which the o

PLC and Scada, I needed a PLC and SCADA assignment just the program and it ...

I needed a PLC and SCADA assignment just the program and it has to be done in simatic flexible and step 7 software!

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd