Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Produce electrical power using solar cell - electrical power, 1. Suppose th...

1. Suppose the California government sets aside a square patch of land that is 10 kilometers on each side and plans to use this land to generate electrical power with wind turbines

Signal., explain about signal

explain about signal

Lt metering or low tension metering, LT Metering or Low Tension Metering ...

LT Metering or Low Tension Metering The subsequent types of meters are generally used for LT consumers: Whole Current Meters i)   Single phase meters ii)   3-phase

Analyse the characteristics of a dc machine, Theoretical calculations T...

Theoretical calculations The characteristics of the d.c. machine you will be investigating are given on the last page of this part. Use 200V DC supply for both armature and fie

Calculate the frequencies at which there is an alias, A pure sine wave alon...

A pure sine wave along with a frequency of 100Hz is sampled at 150Hz. At which point one of the subsequent frequencies would you expect an alias? A) 75Hz B) 100Hz C) 150Hz

Develop and execute a pspice program, Develop and execute a PSpice program ...

Develop and execute a PSpice program to solve for the current I 2 in Figure.

Demand meters, Demand Meters Demand meters measure volt-amperes (in kV...

Demand Meters Demand meters measure volt-amperes (in kVA), that merge both reactive (reflected) and actual (consumed) power. In its easiest form, a demand meter has a gauge wh

What do you mean by digital systems, Q. What do you mean by digital systems...

Q. What do you mean by digital systems? Electronics information is generally placed into two categories as digital and analog. The Digital information is represented in discret

Calculate the analog output voltag, For the 3-bit 2 n -R D/A converter of ...

For the 3-bit 2 n -R D/A converter of Figure, calculate the analog output voltage when the input is (a) 100, and (b) 010. Solution a. For the binary input 100, switches con

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd