Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Zener breakdown, Zener breakdown: Zener Breakdown takes place in very ...

Zener breakdown: Zener Breakdown takes place in very thin junction i.e. when both sides of junction layer is narrow. When a small reverse bias voltage is applied a Very strong

Desirable requirements of a generic photo-detector, Question : a) Stat...

Question : a) State six desirable requirements of a generic photo-detector. b) A gallium arsenide pin photo-diode has an intrinsic layer of width 1 μm. The diode is revers

Evaluate the voltage source, Q. For the capacitor shown in Figure connected...

Q. For the capacitor shown in Figure connected to a voltage source, sketch i(t) and w(t).

Transfer function, derive transfer function of S= 2.25+j4.5

derive transfer function of S= 2.25+j4.5

Find the expressions for the inductor current, Consider the RL circuit of F...

Consider the RL circuit of Figure with R = 2, L = 5H, and v(t) = V = 20 V (a dc voltage source). Find the expressions for the inductor current i L (t) and the inductor voltage v L

Fibre optics, 1. A very narrow laser beam in air is shone into a sphere of ...

1. A very narrow laser beam in air is shone into a sphere of solid glass that has a uniform refractive index n>1 and radius ? . The beam makes an angle a in air with the normal to

Core electron binding energies, Perform a Hartree-Fock geometry optimizatio...

Perform a Hartree-Fock geometry optimization calculation of butadiene using a minimal basis set. Repeat with the 6-311G(d,p) basis set, using the optimized minimal basis set geomet

Determine excitation voltage and power angle, A 500KVA, 6 pole, 500v, 3 pha...

A 500KVA, 6 pole, 500v, 3 phase, wye-connected synchronous generator has a synchronous impedance of 0.1 + j1.5 ohms per phase. If the generator is driven at 1000 r.p.m., what is th

Define instruction cycle, Define instruction cycle and T-state Instruct...

Define instruction cycle and T-state Instruction cycle is defined, as the time needed completing the execution of an instruction. Machine cycle is defined as the time needed co

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd