Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Dad double add instruction , DAD Double Add Instruction The contents o...

DAD Double Add Instruction The contents of register  R P are added  to the  contents  of HL register pair  and results of addition is stored  in HL register pair. R P   may b

Illustrate the experts model of GPS system, Illustrate the experts model of...

Illustrate the experts model of GPS System A fundamental expert system is made up of the below elements: Setting up an Expert System -  Information is collected

Digital electronics, With the use of clocked JK flip-flops, draw and explai...

With the use of clocked JK flip-flops, draw and explain the working principle of a 3-bit binary ripple counter.

How typical dma controller can be interfaced to 8086/8085, Show how a typic...

Show how a typical DMA controller can be interfaced to an 8086/8085 based maximum mode system. For 8088 in maximum mode: The RQ/GT1 and RQ/GT0 pins are utilized to issue DMA

What is thermal runaway, Q. What is thermal runaway. The problem of sel...

Q. What is thermal runaway. The problem of self heating arises due to dissipation of power at the collector junction. The leakage current ICBO is extremely temperature dependen

Measure phase angle by using an oscilloscope, 1. Introduction : ...

1. Introduction : Theory:  Phase angle is defined as the number of degrees separating two sine waves of the same frequency. The Phase shift is defined as any change t

Ac netwoks, hello look for someone that could do i lab report form me on ac...

hello look for someone that could do i lab report form me on ac network, the report is due tonight at 12:00 so only have 8 hours left wondering if anyone is interested in do it? ca

Give the significance of sim and rim instruction, Give the significance of ...

Give the significance of SIM and RIM instruction available in 8085. Instruction SIM: Set Interrupt Mask. This is a 1 byte instruction and can be used three dissimilar functio

Three phase ac circuit, Three Phase AC Circuit: Alternating circuits t...

Three Phase AC Circuit: Alternating circuits thus far discussed have single phase supply system and it's satisfactory for domestic application as light, fan and heating, etc.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd