Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Square wave generator ( 10 MHz to 20MHz), I need a simple design of above ...

I need a simple design of above mentioned , this oscillator will be used in a wireless power transmission

2365 - 305 task a, List four sources of information which are essential to ...

List four sources of information which are essential to the designer of this electrical installation.

Explain about folded network, Q. Explain about Folded network? Folded ...

Q. Explain about Folded network? Folded network: When all the outlets/inlets are connected to the subscriber lines, logical connection appears as displayed in figure. In this

Matlab antenna diversity, please I need help in matlab to program complex e...

please I need help in matlab to program complex expression in antenna diversity please

Conductometry experiment, why conductance is not zero at end pont? reply as...

why conductance is not zero at end pont? reply as soon as possible.

What is an opcode, What is an Opcode? The part of the instruction that ...

What is an Opcode? The part of the instruction that specifies the operation to be performed is known as the operation code or opcode

Show the bode plot, Question: (a) Show the Bode Plot, showing the relev...

Question: (a) Show the Bode Plot, showing the relevant corner frequencies and slopes, for the unity feedback system whose open loop transfer function is given by: (b) T

RC phase shift oscillator, For the RC phase-shift oscillator if c=1pF and R...

For the RC phase-shift oscillator if c=1pF and R=10K determine the value of Rf

Obtain the complete solution for the voltage, Consider the circuit of Figur...

Consider the circuit of Figure and obtain the complete solution for the voltage v C (t) across the 5-F capacitor and the voltage vx(t) across the 5- resistor.

Explain about communication systems, Q. Explain about Communication Systems...

Q. Explain about Communication Systems? Even though most modern communication systems have only been invented and developed during the eighteenth and nineteenth centuries, it i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd