Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Draw a block diagramfor a 2-to-4 decoder, Q. Draw a block diagramfor a 2-to...

Q. Draw a block diagramfor a 2-to-4 decoder. Obtain the truth table, and develop a logic diagram.

Applications of operational amplifiers, Q. Applications of operational ampl...

Q. Applications of operational amplifiers? An op amp along with a few external components (resistors and capacitors) is capable of performing many different operations-hence th

What is the per-unit slip at full load, Q. A three-phase, 60-Hz induction m...

Q. A three-phase, 60-Hz induction motor runs at almost 1800 r/min at no load, and at 1710 r/min at full load. (a) How many poles does the motor have? (b) What is the per-unit

Adi add immediate instruction , ADI Add Immediate  Instruction The  b...

ADI Add Immediate  Instruction The  bit  data specified in the instruction  is  directly  added with  contents of accumulator and result  of operation is stored  in the  accum

Which stack is used in 8086, FIFO (First in First Out) stack is used in 808...

FIFO (First in First Out) stack is used in 8086.In this type of Stack the first stored information is retrieved first.

Lki load register pair immediate instruction , LKI  Load Register pair  ...

LKI  Load Register pair  Immediate  Instruction This instruction is used to copy or  load  16 bit  data specified  in the  instruction  directly into  the register pair. The i

Reflection and retraction in cables and their calculations, How do I calcul...

How do I calculate the line-cable and cable-line values of reflection and refraction coordinates?

Find the first-null bandwidth, An audiomessage is band-limited to 15 kHz, s...

An audiomessage is band-limited to 15 kHz, sampled at twice the Nyquist rate, and encoded by a 12-bit natural binary code that corresponds to Lb = 212 = 4096 levels, all of which s

Compute the efficiency of the transformer, Q. These data were obtained from...

Q. These data were obtained from tests carried out on a 10-kVA, 2300:230-V, 60-Hz distribution transformer: • Open-circuit test, with low-voltage winding excited: applied voltag

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd