Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Explain the different coupling schemes used in amplifiers, Q. Explain the d...

Q. Explain the different coupling schemes used in amplifiers? When amplifiers are cascaded, it is necessary to use a coupling network between the output of one amplifier and th

Integrator circuit, Q. Addition and integration can be combined by the summ...

Q. Addition and integration can be combined by the summing integrator circuit shown in Figure. With the given component values and input waveforms, sketch v o when S is opened at

Evaluate the quiescent point of the circuit, Question: a). For the circ...

Question: a). For the circuit shown in figure state which operation is performed and draw the output waveform if measured between points A and B. The input signal is given in f

Determine the parameters of the equivalent circuit, No-load and blocked-rot...

No-load and blocked-rotor tests are conducted on a three-phase,wye-connected inductionmotor with the following results. The line-to-line voltage, line current, and total input powe

Electronic monitor and alarm system for an oil separator, This assignment i...

This assignment is to develop a User Requirements Specification for an electronic monitor and alarm system for an Oil Separator in Surface Water Drainage Systems. These separato

Dc motor, why we rotate the armature of dc motor in anticlockwise direction...

why we rotate the armature of dc motor in anticlockwise direction

Gis database, GIS database:  In a nutshell, we could say that the GIS ...

GIS database:  In a nutshell, we could say that the GIS technology integrates general database operations (data query and statistical analysis), along with the unique a

Compute the effective armature, For a 45-kVA, three-phase, wye-connected, 2...

For a 45-kVA, three-phase, wye-connected, 220- V synchronous machine at rated armature current, the short-circuit load loss (total for three phases) is 1.80 kWat a temperature of 2

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd