Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Thyristor terminology , Thyristor  Terminology The followings  terms ...

Thyristor  Terminology The followings  terms are used in SCR  specifications: Latching current : The  latching  current is  the value of on stat e current  required  to mai

Edc, transistor biasing stabilization problems

transistor biasing stabilization problems

Draw the timing diagram for the first input pulses, Given the block diagram...

Given the block diagram of a synchronous counter shown in Figure (a), draw the timing diagram for the first input pulses, with Q 1 , Q 2 , and Q 3 initially at 0.

What happen when negative bias applied to the gate of fet, Q. What happens ...

Q. What happens when a negative bias is applied to the gate of a FET? The result of applying a negative bias to the gate is to reach the saturation level at a lower level of V

Find the rotor current, A 2200-V, 1000-hp, three-phase, 60-Hz, 16-pole, wye...

A 2200-V, 1000-hp, three-phase, 60-Hz, 16-pole, wye-connected, wound-rotor induction motor is connected to a 2200-V, three-phase, 60-Hz bus that is supplied by synchronous generato

State value of current flowing in the winding, The winding of an electromag...

The winding of an electromagnet has an inductance of 3H and a resistance of 15?. When it is connected to a 120 V d.c. supply, Determine: (a)  the steady state value of current f

3-phase 120 degree mode vsi , 3-phase  120 0 Mode VSI In 1200 mode ...

3-phase  120 0 Mode VSI In 1200 mode VSI each thyristor  conducts for 1200. At a  time only  thyristor  one form  upper  group  and another  form group will conduct.  Only th

A circuit having of a resistor connected in series, A circuit having of a r...

A circuit having of a resistor connected in series with a 0.5µF capacitor and has a time constant of 12 ms. Verify: (a)  The value of the resistor (b)  The capacitor voltage

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd