Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Fraction of the total cross section - interaction processes, Determine and ...

Determine and plot for 5 keV to 100 MeV the fraction of the total cross section due to each of the four interaction processes for      (a) hydrogen,      (b) nitrogen,

Explain working of digital-to-analog converters, Q. Explain working of Digi...

Q. Explain working of Digital-to-Analog Converters? Digital-to-Analog (D/A) Converters For the results of digital computations to be used in the analog world, it becomes n

What is polyphase induction machine performance, Q. What is Polyphase Induc...

Q. What is Polyphase Induction Machine Performance? Some of the important steady-state performance characteristics of a polyphase induction motor include the variation of curre

Determine the total energy ?owing into the component, Q. The voltage at ter...

Q. The voltage at terminal a relative to terminal b of an electric component is v(t) = 20 cos 120πt V. A current i(t) =-4 sin 120πt A ?ows into terminal a. From time t 1 to t 2 ,

Magnetic Circuits:, A circular ring of magnetic material has a mean length ...

A circular ring of magnetic material has a mean length of 1m and a cross sectional area of .001m^2.A sawcut of 5mm width is made in the ring . calculate the magnetizing current req

Explain industry standard architecture bus, Explain the term Industry Stand...

Explain the term Industry Standard Architecture Bus. The Industry Standard Architecture, bus has been approximately since the very start of the IBM-compatible personal computer

Which interrupt has the highest priority, TRAP has the maximum priority ...

TRAP has the maximum priority There are 2 types of interrupts external and internal. NMI has highest priority between all external interrupts,TRAP has highest priority between

V-i characteristics - power semiconductor devices, V- I Characteristics ...

V- I Characteristics When the peak  value of  applied  voltage is less than the break over   voltage  of triac  and no signal  is applied to the triac  it will block  both  pos

What are the major systems of a telecommunication network, Q. What do you u...

Q. What do you understand by major systems of a telecommunication network? Explain in detail the subscriber loop systems. Ans: Major systems of any telecommunication netw

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd