Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

What is occur in density flux state- ferromagnetic material, In a ferromagn...

In a ferromagnetic material the state of flux density is as follows when external magnetic field is applied to it. (A) Increased (B) Becomes zero (C) Remains unchang

Show the characteristics of general - purpose capacitors, Q. Show the Chara...

Q. Show the Characteristics of General - Purpose Capacitors? The working voltage for a capacitor is generally specified by themanufacturer, thereby giving the maximum voltage t

Show effects of saliency and saturation, Q. Show Effects of Saliency and Sa...

Q. Show Effects of Saliency and Saturation? Because of saliency, the reactancemeasured at the terminals of a salient-pole synchronousmachine as opposed to a cylindrical-rotor m

Customer indexing scheme, Customer Indexing Scheme: Customer indexing ...

Customer Indexing Scheme: Customer indexing has to be carried out in a way, that makes it probable to associate the customer's geographical and electrical address along with h

process of damping, Describe the process of DAMPING. You explanation shoul...

Describe the process of DAMPING. You explanation should include an example of each of the following:- Over-damping, Under-damping, Zero-damping, Critically da

What is stored program control, Q. What is Stored Program Control ? Sto...

Q. What is Stored Program Control ? Stored Program Control:Modern digital computers use stored programmed concept. Here, a program or a set of instructions to the computer is s

#t voice controlled mobile base, The aim of this project is to design, co...

The aim of this project is to design, construct and build a motorised base driven by two small dc motors. The motor drives are two H-bridges. The switching devices in these bridges

Dc machines, how unbalanced effect in wave winding is considered to be bala...

how unbalanced effect in wave winding is considered to be balanced?

What is meant by blanking, a. Explain the following terms: (6) (i) Persi...

a. Explain the following terms: (6) (i) Persistence of vision (ii) Flicker in motion pictures b. What is meant by blanking? What is the need of blanking pulses? Compare th

Phasor relation between different voltages and currents, Phasor relation be...

Phasor relation between different voltages and currents: In the capacitive circuit of Figure, find 1.      Impedance, 2.      Resultant current, 3.      Power factor,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd