Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Terminal of a battery having 10 cells connected in series, An external resi...

An external resistance of 10 Ω is linked to the terminal of a battery having 10 cells connected in series. Emf for every cells and internal resistance  is 1.5V and 0.2Ω . Find the

Industrial approach of speed control dc series motor, industrial approach o...

industrial approach of speed control of dc series motor

Determine the current by mesh analysis, Q. Determine the current I through ...

Q. Determine the current I through the 10- resistor of the circuit of Figure by employing the node-voltage method. Check by mesh analysis.

Microwave components and devices, explain how microwave intergrated circuit...

explain how microwave intergrated circuits differ from conventional intergrated circuit stating the technologies

Sectoral overview and enabling framework, Sectoral Overview and Enabling Fr...

Sectoral Overview and Enabling Framework Previously, you have studied about several Acts and Policies relevant to the power sector, their aims, main features and implications

Dc circuits, Dc Circuits: In this unit, you have learned about methods...

Dc Circuits: In this unit, you have learned about methods of network analysis which are general in nature such as KCL, KVL, Nodal and Mesh analysis. These general methods may

Difference, Difference between bootstrip sweep circuit and Miller sweep ci...

Difference between bootstrip sweep circuit and Miller sweep circuit

Calculate the monthly electric bill, Calculate the monthly electric bill fo...

Calculate the monthly electric bill for TESTU.  Metering is as follows: B 00,000 kWHr C 00,000   kVARHr D 0,000        kW  peak demand Facilities Charge = $500

Find the induced emf across the coil, Q. A coil is formed by connecting 15 ...

Q. A coil is formed by connecting 15 conducting loops, or turns, in series. Each loop has length l = 2.5 m and width w = 10 cm. The 15-turn coil is rotated at a constant speed of 3

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd