Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Commutation in dc machines, Currents induced in armature conductors of a d....

Currents induced in armature conductors of a d.c. generator are alternating. To make their flow unidirectional in the external circuit, we need a commutator. Moreover, these curren

Buck boost converter - power supplies , Buck Boost Converter The outpu...

Buck Boost Converter The output  of buck boost  regulator may be  less than  or greater than the  input  voltage. Since  the polarity of output  voltage  is opposite  to that

Guarding Against Loss in Transformers, Guarding Against Loss in Transformer...

Guarding Against Loss in Transformers Distribution transformers are expected to convert up to 95-98% of the input power into usable output power. A distribution transformers i

Define the operation of real mode interrupt, Define the operation of real m...

Define the operation of real mode interrupt. Operation of Real mode interrupt: While the microprocessor completes executing the current instruction, this determines whether a

Discrete time system transfer function, For a discrete time unit step input...

For a discrete time unit step input x(kT), the output  y(kT) of a system is shown below,   Part (a)  Obtain the Z-transform of the output signal y(kT).   Part (b)   F

Explain acceptance cone, Explain Acceptance cone? The fibre air - core ...

Explain Acceptance cone? The fibre air - core interface is display below: In this figure Omax is the maximum angle, inside that the rays undergo total internal reflecti

Types of meter test, Types of Meter Test A meter should pass the subse...

Types of Meter Test A meter should pass the subsequent two types of tests: Type Tests Routine Tests Meters are calibrated such in which the whole

Give the applications of carbon, Give the applications of carbon. Car...

Give the applications of carbon. Carbon : These materials used in the field of electrical engineering are manufactured from graphite and the other forms carbon as coal and so

Frequency-controlled induction-motor drives, Q. Frequency-controlled induct...

Q. Frequency-controlled induction-motor drives ? The converters employed for variable-frequency drives can be classified as: • Voltage-source inverter (which is the only one

State advantages of washing machine, State advantagesof Washing machine ...

State advantagesof Washing machine Main advantages are that these washing machines are fully automatic (wash programs are fully stored) it makes them easy to use, they are chea

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd