Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Design the high-pass filter, Q. Design the high-pass filter shown in Figure...

Q. Design the high-pass filter shown in Figure (by determining C) to have a half-power frequency of 1 MHz.

Single phase full wave controlled rectifier , Single Phase Full Wave Contro...

Single Phase Full Wave Controlled rectifier The single  phase  half  wave controlled  rectifier  produce only one pulse  of load  current  during  one cycle  of supply voltage

Determine the 50- hz applied voltage, Athree-phase, 440-V, 60-Hz, four-pole...

Athree-phase, 440-V, 60-Hz, four-pole induction motor operates at a slip of 0.025 at full load, with its rotor circuit short-circuited. This motor is to be operated on a 50-Hz supp

Control, Ask The goal of this project is to model a system and to design a ...

Ask The goal of this project is to model a system and to design a controller for the system so that the closed-loop system performs satisfactorily. We want to accurately positio

Calculate the hysteresis loss in joules per cycle, Q. In plotting a hystere...

Q. In plotting a hysteresis loop the following scales are used: 1 cm = 400 At / mand 1 cm=0.3 T. The area of the loop for a certain magnetic material is found to be 6.2 cm 2 . Calc

Dpr preparation, DPR PREPARATION: 1.  Asset Management 2.  System O...

DPR PREPARATION: 1.  Asset Management 2.  System Operations and Despatch 3.  Field Operations 4.  Customer Processes 5.  Corporate Processes The details covered

What do you mean by load factor, Q. What do you mean by Load factor? Th...

Q. What do you mean by Load factor? The two components of electric service are demand and energy. Demand is the maximum level of real power which the electric utility must supp

Hahaha, Ask question #Minimum 10gzhahahaau0 words accepted#

Ask question #Minimum 10gzhahahaau0 words accepted#

What do you mean by assembly procedures in fem, a) What do you mean by asse...

a) What do you mean by assembly procedures in FEM, discuss by taking suitable example of your choice. b) Write the potential energy equation for particular FE analysis of a prob

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd