Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Compute the source current, Q. A 230-V, single-phase, 60-Hz source supplies...

Q. A 230-V, single-phase, 60-Hz source supplies two loads in parallel. One draws 10 kVA at a lagging power factor of 0.80 and the other draws 6 kWat a lagging power factor of 0.90.

Show the procedure twos complement subtraction, Q. Show the procedure twos ...

Q. Show the procedure twos complement subtraction? Two's complement subtraction is the binary addition of the minuend to the 2's complement of the subtrahend (adding a negative

Bonding forces and energy bands in solids, Bonding Forces and Energy Bands ...

Bonding Forces and Energy Bands in Solids Electrons are controlled to sets of discrete energy levels in atoms, with large gaps among them in which no energy state is obta

Find percent error of both meters when measuring a current, Q. Error specif...

Q. Error specifications on a 10-A digital ammeter are given as 0.07% of the reading, 0.05% of full scale, 0.005% of the reading per degree Celsius, and 0.002% of full scale per deg

Digital signal processing, A DT LTI system has the following impulse respon...

A DT LTI system has the following impulse response: h(n)=[cos(pi/+delta(n)] u(n-3)u(n-2) (a) Find the system’s frequency response h(e^jw ). (b) Sketch the magnitude and phase respo

Superposition Theorem, Help using superpositions find voltage across all re...

Help using superpositions find voltage across all resistor

Calculate the output torque, The power transferred across the air gap of a ...

The power transferred across the air gap of a two pole inductionmotor is 24 kW. If the electromag netic power developed is 22 kW, find the slip. Calculate the output torque if the

Analogy between electrical and nonelectric physical systems, Systems such a...

Systems such as those encountered in mechanics, thermodynamics, and hydraulics can be represented by analogous electric networks, from the response of which the system characterist

Binary coded decimal addition, Q. Binary Coded Decimal Addition Now as ...

Q. Binary Coded Decimal Addition Now as in conventional decimal addition, Binary Coded Decimal addition is performed one decimal digit at a time. What happens when the sum g

Use delta-wye transformation for network reduction, 1555_Use delta-wye tran...

1555_Use delta-wye transformation for network reduction.png what is the solution to this particular problem?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd