Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

What is the function of ct and p.t, Q. What is the function of CT and P.T a...

Q. What is the function of CT and P.T and where they are used? Ans: The full form of CT is Current transformer and is used for calculating of current. The full form of PT is

Static v- i characteristics - power semiconductor devices , Static V- I Cha...

Static V- I Characteristics A thyristor  works in  three basic  modes a.Reverse  blocking mode b.Forwards  blocking  mode and c.Forward  conducting  mode In revers

What do you mean by signal multipath, Q. What do you mean by Signal multipa...

Q. What do you mean by Signal multipath? Signal multipath occurs with electromagnetic wave propagation via sky wave in the HF range. When the transmitted signal reaches the rec

Multiplexers and flip flops, Decoders and multiplexers are termed, medium s...

Decoders and multiplexers are termed, medium scale integration (MSI) devices; this term implies that the device is complex in construction and usually its operation as well. Below

Determine the remaining voltages and currents, Q. Some element voltages and...

Q. Some element voltages and currents are given in the network configuration of Figure. Determine the remaining voltages and currents. Also calculate the power delivered to each el

Engineering Science, A rifle with a mass of 3,5 kg fires a bullei with a ma...

A rifle with a mass of 3,5 kg fires a bullei with a mass of 120 g with a muzzle velocity of 420 mls. Calculate the following: 1.4.''l The momentum before the rifle was fired ''1.4.

Clipper, merits amd demerits of series and shunt clipper

merits amd demerits of series and shunt clipper

Draw and explain the r-2r ladder dac, Question 01 Convert the following bi...

Question 01 Convert the following binary numbers to its specified number system 111.101 (2) to octal 10111 (2) to decimal 0.1010 (2) to hexadecimal 1011.11 (2)

Closed loop block diagram into Electrical Circuit, I have a closed loop or ...

I have a closed loop or feedback system and i want to convert it into electrical circuit. please give me example about this

Reduce the circuit to a thevenin and a norton equivalent, Q. Reduce the cir...

Q. Reduce the circuit of Figure to a Thévenin and a Norton equivalent circuit with respect to terminals a-b.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd