Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

What do you understand by orthographic projection, What do you understand b...

What do you understand by orthographic projection ? Illustrate with the help of Matrix representation.

Digital control system, a digital computer controlled rolling mill regulato...

a digital computer controlled rolling mill regulator system..

Sphl load stack pointer with hl instruction, SPHL Load Stack  pointer with...

SPHL Load Stack  pointer with HL Instruction This instruction  copies  the contents of HL register  pair  the stack pointer register. The instruction format is             S

What is the use of modem control unit in 8251, What is the use of modem con...

What is the use of modem control unit in 8251? The modem control unit handles the modem handshake signals to coordinate the communication among the modem and the USART.

Determine the efficiency when the transformer, A 3-kVA, 220:110-V, 60-Hz, s...

A 3-kVA, 220:110-V, 60-Hz, single-phase transformer yields these test data: • Open-circuit test: 200 V, 1.4 A, 50 W • Short-circuit test: 4.5 V, 13.64 A, 30 W Determine th

Diatomic molecules in three dimensions, Consider the open rotation of a dia...

Consider the open rotation of a diatomic molecule consisting of two atoms of mass and respectively divided by a distance presume that the molecule is rigid with center of mass fixe

Non inverting summing amplifier, Q. In the non inverting summing amplifier ...

Q. In the non inverting summing amplifier of Figure, let R d = 1k and M = 6. Find R f so that v =

Transformers, A 440v 4-pole dc generator takes an armature current of 50A w...

A 440v 4-pole dc generator takes an armature current of 50A when rotating at 626 rpm. the armature circuit resistance is 0.25 ohms. determine the generated emf?

Find the directive gain, Q. Aconical horn has a side viewas shown in Figure...

Q. Aconical horn has a side viewas shown in Figure  The maximum value ofthe directive gain is given by GD ∼ = 5.13(D/λ) 2 , where D =√3.33λL1 and L1 = L/(1-d/D),in which d is the i

Write the volt-ampere relations for the coupled inductors, Q. For the coupl...

Q. For the coupled inductors shown in Figure, neglecting the coil resistances, write the volt-ampere relations.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd