Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Exponentially weighted moving average, 1. The Excel file contains daily clo...

1. The Excel file contains daily closes for the S&P/TSX composite index from January 2, 2008 to December 31, 2010. Assuming that December 31, 2010 is the current day. A) Using the

Compute the received carrier frequency, Consider a transmitter S which radi...

Consider a transmitter S which radiates a sinusoidal carrier frequency of 1850 MHz. For a vehicle moving at 26.82 m/s, compute the received carrier frequency if the vehicle is movi

Change management in power distribution, Change Management in Power Distrib...

Change Management in Power Distribution: Organisational change might be described as an organisation-wide effort to augment the effectiveness of an organisation through str

Power diode - power semiconductor devices , Power Diode A power diode i...

Power Diode A power diode is a two terminal, anode a and cathode K and  two layer P  and  N  junction devices. A PN  junction normally  formed  by allowing  diffusion and epita

Customer satisfaction - issues of power supply, Customer Satisfaction - Iss...

Customer Satisfaction - Issues of Power Supply Customer satisfaction measurement is a systematic process for collecting customer data (e.g. surveys, audits and etc.), analyzin

Matlab ? uniform quantization, simulate a uniform quantizer that takes as a...

simulate a uniform quantizer that takes as an input a vector of numbers and returns as an output the quantized vector. 1-Generate a random input vector of 10000 samples randomly in

Gis technology, GIS technology: GIS could be used to derive diverse in...

GIS technology: GIS could be used to derive diverse information for efficient technical and commercial management of a power distribution utility, e.g., capacity analysis, inv

Dc machines, compound generator drawback

compound generator drawback

Bad workmanship, Bad Workmanship Bad workmanship contributes important...

Bad Workmanship Bad workmanship contributes importantly towards increasing distribution losses. Efforts should, thus, be made to have the best probable workmanship. In this co

Simplified operation on transistor, Simplified operation: Figu...

Simplified operation: Figure: Simple circuit to show the labels of a bipolar transistor. The essential value of a transistor comes from its capability to make use

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd