Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Tools for power supply, Tools for Power Supply The several universal t...

Tools for Power Supply The several universal tools those could be applied in the power-sector for the improvement of organizational efficiency and effectiveness. These tools v

What are the hardware elements in the embedded systems, What are the hardwa...

What are the hardware elements in the embedded systems? Hardware Elements in the Embedded Systems are as follows: (i) Power Source (ii) Clock Oscillator Circuit and Clock

Find out the low-frequency voltage gain, Design a differential amplifier wi...

Design a differential amplifier with active current mirror load in Cadence using TSMC 0.35 micron process. The power supply voltage is 3.3V. A 10µA current reference is available

What would the cutoff frequency, Q. The cutoff frequency of a dominant mode...

Q. The cutoff frequency of a dominant mode in an air-?lled rectangular waveguide is 3 GHz. What would the cutoff frequency be if the same wave - guide were ?lled with a lossless di

Determine potential difference across resistor, Determine Potential Differe...

Determine Potential Difference: Compute the current through each element of the given network and also determine potential difference across 15 Ω resistor. Figure

Calculate the starting torque, A squirrel-cage inductionmotor operates at a...

A squirrel-cage inductionmotor operates at a slip of 0.05 at full load. The rotor current at starting is five times the rotor current at full load. Neglecting stator resistance and

Amper circuital lw, the plot of amper circuital law by using matlap?

the plot of amper circuital law by using matlap?

What do you mean by addressing and numbering, Q. What do you mean by addres...

Q. What do you mean by addressing and numbering? Numbering and Addressing: In data and telephone networks, end equipment are more often single units than multiple devices uni

Engineer, Transmission Through a LiNb0 3 Plate Examine the transmission of...

Transmission Through a LiNb0 3 Plate Examine the transmission of an unpolarized He-Ne laser beam (?o= 633 nm) normally incident on a LiNb0 3 plate (ne = 2.29, no = 2.20) of thickn

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd