Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Give the alternate functions for the port pins of port3, Give the alternate...

Give the alternate functions for the port pins of port3? RD - Read data control output. WR - Write data control output. T1 - Timer / Counter1 external input or test pin.

Explain error-rate control and output-rate control, Error-Rate Control, Out...

Error-Rate Control, Output-Rate Control, and Integral-Error (Reset) Control Let us consider a typical second-order servomechanism(containing two energy-storing elements) whose

Input output operations , Input Output Operations Many times microproc...

Input Output Operations Many times microprocessor has to  accept data  from input port and send data to  output  port to  interact with the  real world. Input  port is  tri st

Calculate the impedance, What is the impedance Z between terminals A and B ...

What is the impedance Z between terminals A and B of the networks shown below? Express your answers in polar form. Three voltages represented by v 1 (t)=100cosωt, v 2 (t)=7

Measurement, Why delay circuit used in CRO?

Why delay circuit used in CRO?

Compute the current loss in the lines, Q. Consider a 240-V supply feeding a...

Q. Consider a 240-V supply feeding a resistive load of 10 kW through wires having a total resistance of R = 0.02 . For the same load, let a 120-V supply be used with a total wire

Connection of shunt capacitors - vantage points, Connection of Shunt Capaci...

Connection of Shunt Capacitors - Vantage Points An unloaded distribution line is capacitive in character and a fully loaded line has inherent inductive and resistive features

Fiind the magnitudes of the line-to-line voltages, Q. A single-line diagram...

Q. A single-line diagram of a three-phase transformer bank connected to a load is given in Figure. Find the magnitudes of the line-to-line voltages, line currents, phase voltages,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd