Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Find the magnetic-field force exerted on the moving bar, Consider the arran...

Consider the arrangement shown in Figure. A conductor bar of length l is free to move along a pair of conducting rails. The bar is driven by an external force at a constant velocit

Measure and set frequency by using an oscilloscope, 1. Introduction : ...

1. Introduction : Theory: Frequency is the number of occurrences of a repeating event per unit time. It can also be defined as the number of repetitions (cycles) of a w

Factors affecting high commercial losses, Factors Affecting High Commercial...

Factors Affecting High Commercial Losses Commercial losses in our country occur mainly because of the following reasons: Incorrect assessment of the energy consum

Motor., if load is removed so which motor will run fast? series or shunt?

if load is removed so which motor will run fast? series or shunt?

Blanking circuit, Blanking circuit: The saw tooth sweep voltage applied to...

Blanking circuit: The saw tooth sweep voltage applied to the X places moves beam across the CRT tube in a straight horizontal line from left to right during the sweep or trace tim

How to calculate back pitch, Q.   A 6 - pole, DC armature with 36 slots and...

Q.   A 6 - pole, DC armature with 36 slots and 2 coil - slides/slot is to be wave wound (double layer). Calculate the back pitch, front - pitch and commentator pitch. How many dumm

Explain the different coupling schemes used in amplifiers, Q. Explain the d...

Q. Explain the different coupling schemes used in amplifiers? When amplifiers are cascaded, it is necessary to use a coupling network between the output of one amplifier and th

Sing flag - microprocessors architecture , Sing Flag If D7  ( bit left ...

Sing Flag If D7  ( bit left  most bit)  of accumulator  (which  some  exceptions) is 1 as a result  of any  arithmetical  or logical operations sign flag  is set ( bit  corresp

Power analyser, Explain frequency selective wave analyser with bandwidth

Explain frequency selective wave analyser with bandwidth

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd