Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Describe the magnetic effects of current, 1.   Describe the magnetic effe...

1.   Describe the magnetic effects of current? ( to achieve a pass grade, describe the magnetic effect of current) 2.   Complete the diagram to show the direction of mo

Compute the kvar and the power factor of the motor, Q. A three-phase balanc...

Q. A three-phase balanced load draws 100 kW at 0.8 power factor lagging. In order to improve the supply power factor to 0.95 leading, a synchronous motor drawing 50 kWis connected

Measures of regulator quality, Measures of regulator quality: The outp...

Measures of regulator quality: The output voltage can just be held roughly constant; the regulation is fixed by two measurements: 1. Load regulation is the alteration in ou

Calculate the combined resistance of resistors , 1.   Calculate the combi...

1.   Calculate the combined resistance of three resistors connected in series with resistance of 20 ohm, 30 ohm and 40 ohm? (to achieve a pass grade, solve problems with resisto

Calculate the value of the wavelength, In an electron microscope, a beam of...

In an electron microscope, a beam of electrons is produced by a device called an electron gun. In the electron gun, electrons are 'boiled off' from a heated filament (which is the

Squeeze castings, Squeeze Castings: Squeeze casting, also known as ...

Squeeze Castings: Squeeze casting, also known as liquid metal forging, is a combination of casting and forging process . The molten metal is poured into the bottom half

Explain basic working of transport layer, Q. Explain basic working of Trans...

Q. Explain basic working of Transport Layer? It is responsible for establishing a network independent communication path appropriate for the specific terminal equipments (for exa

Pdc, disadvantages of shunt&series clippers

disadvantages of shunt&series clippers

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd