Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Field effect transistors, basic configuration of field effect transistors i...

basic configuration of field effect transistors in mplifiers

Determine the current in the circuit and the voltage, Q. Two identical junc...

Q. Two identical junction diodes whose volt-ampere relation is given by Equation in which IS = 0.1 µA, VT = 25 mV, and η = 2, are connected as shown in Figure. Determine the curren

Explain explanatory notes on a/d conversion, Explain explanatory notes on A...

Explain explanatory notes on A/D conversion. The digital inventory is working a revolution into the field of microcontrollers, technology and microprocessors are used more effi

Determine the peak frequency deviation, If an FM signal is given by s FM (t...

If an FM signal is given by s FM (t) = 100 cos [2πf c t +100 m(τ ) dτ ] and m(t) is given in figure, sketch the instantaneous frequency as a function of time and determine the pea

Explain the third group of 32 ascii character, Explain the Third Group of 3...

Explain the Third Group of 32 ASCII Character? The third group of 32 ASCII characters is set aside for the upper case alphabetic characters. The ASCII codes for the characters

Evaluate complex power in power system, Q. Evaluate complex power in power ...

Q. Evaluate complex power in power system? The complex power ¯S in a single-phase systemis the complex sum of the real (P) and reactive (Q) power, expressed as follows:

Key performance indicators in business, Key Performance Indicators in Busin...

Key Performance Indicators in Business Significance of Key Performance Indicators (KPIs) in the business of power especially within a change environment due to partial deregul

Explain in detail the operation of 8255 in mode 1, Explain in detail the op...

Explain in detail the operation of 8255 in mode1 taking suitable example. In mode1, Ports A and B are programmed as input or output ports and Port C is used for handshaking.

RC phase shift oscillator, For the RC phase-shift oscillator if c=1pF and R...

For the RC phase-shift oscillator if c=1pF and R=10K determine the value of Rf

What insulators have in large size, Insulators have (A) A full valence...

Insulators have (A) A full valence band. (B) An empty conduction band. (C) A large energy gap. (D)All the above. Ans: Insulators have a large energy gap.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd