Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Discuss the foreign exchange market equilibrium, Q. To answer the following...

Q. To answer the following question, please refer to the figure below. Concentrating only at the upper right quadrant, discuss the foreign exchange market equilibrium. Answer:

Find the voltage regulation and efficiency of the line, Q. A60-Hz, three-ph...

Q. A60-Hz, three-phase transmission line has a total per-phase series impedance of 35+j140 .Ifit delivers 40 MW at 220 kV and 0.9 power factor lagging, find: (a) The voltage, c

Machine, function of a commutator in a DC motor

function of a commutator in a DC motor

Determine ripple factor of half wave rectifier, Illustrate VI Characteristi...

Illustrate VI Characteristics of PN junction diode (10) Illustrate Half Wave Rectifier. Disadvantage of Half Wave Rectifier. Determine ripple factor of Half Wave Rectifier.

Show process of power transmission and distribution, Q. Show Process of Pow...

Q. Show Process of Power transmission and distribution? The structure of a power system can be divided into generation (G), transmission, (T), and distribution (D) facilities,

Polarisation, describe the working and construction diagram of nicholas pri...

describe the working and construction diagram of nicholas prism

the battery and capacitor combination for power backup, Why do wenot see t...

Why do wenot see the battery and capacitor combination for power backup? Ans) There are "super capacitors" that are used for power backup - they are well-organized for short-te

Data rates in pstns, Data rates in PSTNs: A voice channel in a PSTN is ...

Data rates in PSTNs: A voice channel in a PSTN is band limited with a nominal bandwidth of 3.1 kHz. A first-cut estimate of this can be attained from Nyquist's theorem that app

Show balanced three-phase loads, Q. Show Balanced three-phase loads? Th...

Q. Show Balanced three-phase loads? Three-phase loads can be connected in either wye (also known as star or Y) or delta (otherwise known as mesh or ). If the load impedances i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd