Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

EEI., explain about heat time curve and cool time curve

explain about heat time curve and cool time curve

Slip-power controlled wound-rotor induction-motor drives, Q. Slip-power con...

Q. Slip-power controlled wound-rotor induction-motor drives? Slip power is that portion of the air-gap power that is not converted into mechanical power. The methods involving

Clippers, what is shunt clipper?

what is shunt clipper?

Find the rate of information transmission, Q. Find the rate of information ...

Q. Find the rate of information transmission? If the time occupied in transmitting each binary digit is 1 µs, find the rate of information transmission if 1 baud is equal to 1

Determine the voltage gain , (a) A second order Sallen and Key Low Pass Act...

(a) A second order Sallen and Key Low Pass Active Filter has these component values R 1 =R 2 =15 kΩ, C 1 =C 2 =1 nF and the feedback resistors are R 3 =3.9 kΩ and R 4 =2.3 kΩ

Variable capacitors, how can I simulate air variable capacitors in cst simu...

how can I simulate air variable capacitors in cst simulator?

Control, The goal of this project is to model a system and to design a cont...

The goal of this project is to model a system and to design a controller for the system so that the closed-loop system performs satisfactorily.

Explain block diagram of the system, Q. Explain Block diagram of the system...

Q. Explain Block diagram of the system? The block diagram is a pictorial representation of the equations of the system. Each block represents a mathematical operation, and the

Compute the theoretical and practical frequency, Q. An RG-139/U rectangular...

Q. An RG-139/U rectangular waveguide is given to have dimensions a = 0.8636 mm and b = 0.4318 mm. Compute the theoretical and practical frequency ranges of operation for the guide.

Determine the percentage reduction in the applied voltage, A large inductio...

A large induction motor is usually started by applying a reduced voltage across themotor; such a voltage may be obtained from an autotrans- former. A motor is to be started on 50%

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd