Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Show television waveform, Q. Show television waveform? The television w...

Q. Show television waveform? The television waveform representing one scan is illustrated in Figure. A blanking pulse with a duration of 0.18 of the horizontal - sweep period T

Logically and the contents of register, Logically AND  the contents of Reg...

Logically AND  the contents of Register Contents of  register are logically AND with the accumulator bit wise. The result  of the AND  operation is  stored  in the accumulat

Compute the force, Q. Consider a current element I 1 d ¯ l 1 = 10 dz ¯ az...

Q. Consider a current element I 1 d ¯ l 1 = 10 dz ¯ az kA located at (0,0,1) and another I 2 d ¯ l 2 = 5dx ¯ ax kA located at (0,1,0). Compute d ¯ F 21 and d ¯ F 12 experienc

Explain working of ammeter, Q. Explain working of Ammeter? In order to ...

Q. Explain working of Ammeter? In order to measure the current through a wire or line of a circuit, an ammeter is connected in series with the line. A practical ammeter can usu

Show cmos logic families, Both DTL and TTL are based on the saturating BJT ...

Both DTL and TTL are based on the saturating BJT inverter. The transistor acts as a switch that connects or disconnects the collector and emitter. The switch is closed when suffici

Why monitoring and control done, Why Monitoring and control done? Mo...

Why Monitoring and control done? Monitoring and control using microprocessors/computers is often done for the below reasons: - It is safer (faster response to non-standar

Metering and billing system, Metering and Billing System Previously, y...

Metering and Billing System Previously, you have learnt about various measures for reducing commercial losses of a utility. You have studied in which the metering and billing

Segment assembler directive, What do you understand by SEGMENT assemble...

What do you understand by SEGMENT assembler directive? SEGMENT: This directive explains to the assembler the start of a segment along with name segment-name. The segment

What is thermal runaway, Q. What is thermal runaway. The problem of sel...

Q. What is thermal runaway. The problem of self heating arises due to dissipation of power at the collector junction. The leakage current ICBO is extremely temperature dependen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd