Explain synchronisation and parallel operation, Electrical Engineering

Assignment Help:

Explain Synchronisation and Parallel Operation

Generation, transmission and distribution of electric power have to be conducted in an efficient and reliable way at a reasonable cost with the least amount of interruptions. Consequently, in a large power system many synchronous generators are connected in parallel to a common line known as an infinite bus of fixed voltage and frequency, and pre-determined phase sequence. A number of safety requirements need to be satisfied prior to connecting a generator to the infinite bus (this is called a synchronising procedure):

2448_Explain Synchronisation and Parallel Operation.png

(1) The operating frequency,

(2) The line voltage and

(3) The phase sequence must all be the same as those for an infinite bus.

To meet an increased load demand, let us, for instance, bring a second generator into service as shown in Figure. The necessary synchronisation procedure consists of the following major steps. The speed of the incoming generator is adjusted to obtain the frequency of the induced voltage equal to that of the infinite bus. Now that the frequency match is achieved the field current can be raised to a level at which the induced voltage of the second generator is identical to the bus voltage. In order to verify the phase sequence, three lamps are connected asymmetrically as illustrated in the figure. When the phase sequence is correct, the lamp LI will be dark, while the other two lamps will glow brightly. If the phase sequence is not proper, all the lamps will glow or become dark simultaneously. When all the above conditions are met, the second generator can be safely connected to the infinite bus by closing the appropriate circuit breaker.

In addition to the lamps to check the conditions for synchronism, an electronic device (often computer controlled) called a synchroscope is also used to perform a precise switching when the above criteria are fulfilled. It provides the information on the incoming generator as to whether it is running at a lower or higher speed. At a proper speed and a correct phase sequence, the synchroscope indicates zero when the synchronising switch must be closed to connect the second generator on line. At this moment, it is neither receiving nor delivering any power. This is referred to as the floating stage of the generator. If we now increase the field current, the second generator will produce reactive power and help improve voltage regulation. Else, if an attempt is made to increase the rotor speed, the torque developed will increase and the second generator will begin to supply active power to the load.


Related Discussions:- Explain synchronisation and parallel operation

Equipment parameter data, Equipment parameter data: The schematic diag...

Equipment parameter data: The schematic diagrams for existing substations have to be prepared along with information of power transformer rating and numbers, impedance values,

Spread time - power semiconductor devices , Spread Time (t s ) During  ...

Spread Time (t s ) During  spread time anode  voltage  falls from 10% I a  to the  on state  voltage  drop  and anode  current  rises  from 90% I a   to final  value  of anode

Cause of sparking at the brushes of a dc motor, Q. Cause of sparking at the...

Q. Cause of sparking at the brushes of a DC Motor? Ans: Sparking at the brushes can be occur due to poor quality of carbon brushes, loose connection, poor armature of carbon

List the different types of flags, List the different types of flags affect...

List the different types of flags affected by the arithmetic and logic operations. Carry flag, Auxiliary carry flag , Parity flag, Sign flag, Zero flag

Discuss the approximate effect on the characteristic, Consider a three-phas...

Consider a three-phase induction motor with a normal torque-speed characteristic. Neglecting the effects of stator resistance and leakage reactance, discuss the approximate effect

For carry flag - conditional jumps , For carry Flag JC (  jump on  Ca...

For carry Flag JC (  jump on  Carry ) and JNC (Jump  on No carry ) Instructions : JC transfer the  execution of the  program to the  specified memory  address if  carry

Unconditional return, Unconditional Return RET Instruction: This  instr...

Unconditional Return RET Instruction: This  instruction is used to transfer the program sequence  from subroutine to the calling  program unconditionally. The instruction forma

Derive the equations of the self bias circuit, Q. Derive the equations of t...

Q. Derive the equations of the self bias circuit? A circuit which is used to establish a stable operating point is the self biasing configuration. The circuit is shown in Fig

Eeprom, advantages and disadvantages

advantages and disadvantages

Determine the number of poles of this ac motor, Q. A three-phase ac motor, ...

Q. A three-phase ac motor, used to drive a draft fan, is connected to a 60-Hz voltage supply. At noload, the speed is 1188 r/min; at full load, the speed drops to 1128 r/min. (a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd