Explain rebound hammer - underwater non-destructive testing, Civil Engineering

Assignment Help:

Explain Rebound Hammer - Underwater non-destructive testing?

The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condition assessment of concrete. The system contains an underwater rebound hammer, an umbilical cable, and a topside data acquisition unit that is abbreviated as DAU. The rebound hammer is mounted in a waterproof housing which contains an electrical pick up to sense the position of the rebound mechanism. The umbilical cable connects the underwater rebound hammer to the DAU that contains the signal conditioning electronics and data acquisition system.


Related Discussions:- Explain rebound hammer - underwater non-destructive testing

Describe the boussinesq theory, A raft of size 4 m-square carries a load of...

A raft of size 4 m-square carries a load of 200 kN/m 2 . Verify the vertical stress increment at a point 4 m below the centre of the loaded area using Boussinesq's theory. Compare

Determine the active thrust on the wall by culmann method, A retaining wall...

A retaining wall with its face inclined at 75° with horizontal is 10 m high and retains soil inclined at a uniform surcharge angle of 10°. If the angle of internal friction of the

Determine the limit states of serviceability, Limit States of Serviceabilit...

Limit States of Serviceability These are those limit states which point out to the inability of a structure or a structural component in functioning properly as per the intende

Explain the kinematic viscosity, Explain the Kinematic Viscosity Ratio ...

Explain the Kinematic Viscosity Ratio of a fluid's Viscosity to the same fluid's Density.  Greek symbol: ν nu    ν = μ/ρ = Absolute Viscosity/Mass Density    Units: ft

What is a projection line, Projection line is the way, in which the earth i...

Projection line is the way, in which the earth is made known on a flat piece of paper.

Maintenance of gravel roads, Maintenance of Gravel Roads: The mainten...

Maintenance of Gravel Roads: The maintenance consists of : filling up of potholes/depressions with fresh gravel and compacting after light sprinkling with water. g

Strength of materials, An I-section beam 350*200mm2 has a web thickness of ...

An I-section beam 350*200mm2 has a web thickness of 12.5mm & a flange thickness of 25mm. It carries a shearing force of 200KN at a section. Sketch the shear stress distribution acr

Diving operation - preparation for underwater inspection, Define Diving Ope...

Define Diving Operation - Preparation for underwater inspection? Use of experienced divers trained and screened by a reputed commercial diving school is critical for successful

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd