Explain project activity including personal time, Operation Management

Assignment Help:

A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal time. Assuming that an allowance for personal time is 9.5%, the total estimated cost of the project activity including personal time is approximately: (Points : 1)
$6,300
$6,899
$6,990
$7,300


Related Discussions:- Explain project activity including personal time

Compute the future value of 2000 in, Calculate the future value of 2,000 in...

Calculate the future value of 2,000 in 1. 5 years at an interest rate of 6% per year 2. 10 years at an interest rate of 6% per year 3. 5 years at an interest rate of 7% pe

Explain what is modern management theory, What is modern management theory ...

What is modern management theory because are we not just working from the Scientific Management Theories of the 40s and 50? so what is more modern?

Explain ongoing risk exists in any project, Ongoing risk exists in any proj...

Ongoing risk exists in any project. Once a project starts, risk increases. How should one monitor and mitigate risk in a rapidly changing project?

Explain how effective are actions by project managers, Provide two examples...

Provide two examples of current leaders and describe how they demonstrate their leadership characteristics. What separates these characteristics from management techniques? How eff

Explain how does the market demand curve change, How does the market demand...

How does the market demand curve change (as a function of marketing expenditure) during recession? a. Shifts downward b. Remains unaffected c. Becomes ver

Explain overwhelming moral dilemmas, Should ethical concerns be part of lif...

Should ethical concerns be part of life's everyday experience, or is it only necessary when we are faced with overwhelming moral dilemmas? Please state why you have come to this co

Explain critical path consists of only five activities, You are working on ...

You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical pat

Explain a linear trend equation, Value: 15.00 points Problem 3-2 National S...

Value: 15.00 points Problem 3-2 National Scan, Inc., sells radio frequency inventory tags. Monthly sales for a seven-month period were as follows: Month Sales (000) Units Feb. 17 M

Explain crisis leadership style, How is crisis leadership different from le...

How is crisis leadership different from leading under normal circumstance? If leaders wanted to fine-tune crisis leadership style, how would you suggest they practice without creat

Explain the challenges of global virtue teams, Describe the challenges of g...

Describe the challenges of global virtue teams and what types of training and tools management can proactive put in place to ensure cultural differences are taken into account.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd