Explain project activity including personal time, Operation Management

Assignment Help:

A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal time. Assuming that an allowance for personal time is 9.5%, the total estimated cost of the project activity including personal time is approximately: (Points : 1)
$6,300
$6,899
$6,990
$7,300


Related Discussions:- Explain project activity including personal time

Maintenance, discuss the pross and cons of hiring multi-craft maintenance p...

discuss the pross and cons of hiring multi-craft maintenance personnel

Explain characteristic shared by frame relay and atm, which of the followin...

which of the following is a characteristic shared by frame relay and ATM? a. the use of virtual circuits b. the use of fixed-sized packets known as cells c. the use of ded

Describe ethical to reduce the number of employees, 1. Based on GM's ...

1. Based on GM's current condition, do you think it is ethical to reduce the number of employees? Why or why not?

Comparison of market based and resource-based approach, Comparison of Marke...

Comparison of Market Based and Resource-Based Approach to Operations Strategy Since Porter's assertions, there has been a recognition that traditional strategic management has

Explain goals should be articulated by teams, Clearly-defined goals are the...

Clearly-defined goals are the essence of great teamwork. Which of the following statements is most true about how goals should be articulated by teams

Calculate first''s rop with legal firms in san francisco, First printing ha...

First printing has contracts with legal firms in San Francisco to copy their court documents. Daily demand is almost constant at 12,500 pages of documents. The lead time for paper

Explain the four steps of the feedback control model, Identify and briefly ...

Identify and briefly describe the four steps of the feedback control model

Compute the breakeven volume, The following table shows the critical factor...

The following table shows the critical factors in a company's decision on choosing a new piece of equipment. Calculate the breakeven volume and utilization for each option and then

Explain three process steps performed by three machines, Consider the follo...

Consider the following batch-flow process consisting of three process steps performed by three machines: STEP 1 Processing Time: 0.25 Min/Part Processing Time: 0.20 Min/Part Pro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd