Explain project activity including personal time, Operation Management

Assignment Help:

A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal time. Assuming that an allowance for personal time is 9.5%, the total estimated cost of the project activity including personal time is approximately: (Points : 1)
$6,300
$6,899
$6,990
$7,300


Related Discussions:- Explain project activity including personal time

Describe how advancing technologies in the security, Explain how advancing ...

Explain how advancing technologies in the security field are changing how end users are identified. In your response, identify potential security gaps that may be caused by these n

Explain work study as a management tool, Explain work study as a management...

Explain work study as a management tool. Work Study as a Management Tool: Work study checks the work done in an organization and this aims at finding the best and most effici

How can controlling asist a manager to become more efficient, How can contr...

How can controlling help a manager to become more efficient?

Explain how the components of the hawthorne study, Describe how the compone...

Describe how the components of the Hawthorne study are incorporated in current human resource functions? What was the main idea behind this study?

Explain the consumers have a high debt-to-income ratio, In the U.S., consum...

In the U.S., consumer expenditures on homes and other large purchases tend to slow down during a recession because a. of steady supply of loanable funds in the economy dur

Explain what does it mean to exploit a system constraint, 1) If an operatio...

1) If an operation uses a pull system and lean manufacturing techniques do they need to use forecasts? How about production schedules and shop floor control systems? Explain why/wh

Explain project management in the form of a cpm, Discuss an example of a wo...

Discuss an example of a work-related project that is able to be broken down into structure, tasks, subtasks, and work packages, and why project management in the form of a CPM/PERT

Explain primarily used to help design products, Which of the following is p...

Which of the following is primarily used to help design products that will connect product attributes with customer desires?

Explain bottleneck operation by adding a new machine, A small firm intends ...

A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two alternatives, A and B, have been identified, and the associated costs and reven

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd