Explain pressure balance method and compressed air method, Civil Engineering

Assignment Help:

Pressure balance method vs. compressed air method in pipe jacking

Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand.  Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools. 

The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit. 

Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.


Related Discussions:- Explain pressure balance method and compressed air method

Total maximum surface deflection of the pavement system, A stationary 40 kN...

A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming li

Helical reinforcement designed instead of regular links, Question For colum...

Question For column reinforcements, why is helical reinforcement sometimes designed instead of regular links with reasons? Answer The utilization of links for column designi

Strength of materials, #questionwhat is the shear force and bending moment....

#questionwhat is the shear force and bending moment..

What is the meaning of elastic shortening of concrete, What is the meaning ...

What is the meaning of Elastic Shortening of Concrete At the transfer stage, compressive prestressing force is transferred to the concrete. Due to this compressive force, concr

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

Is cbr test is an arbitrary test, CBR Test is an arbitrary test', justify. ...

CBR Test is an arbitrary test', justify. Explain the procedure for conducting the CBR test in the field. Surcharge loads are used in the CBR test; Describe their significa

Cross section diagram of urban road, cross section diagram of urban roan in...

cross section diagram of urban roan in embankment,in cut,in eight lane,in conjusted area,divided hihgway

Find the size of the foundation required, A steam turbine with base 6 m × 3...

A steam turbine with base 6 m × 3.6 m weighs 10,000 kN. It is to be placed on a clay soil with c = 135 kN/m 2 . Find the size of the foundation needed if the factor of safety is to

WATER SUPPLY, THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN ...

THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN DEMAND FOR THE WATER RETICULATION OR DISTRIBUTION PERIOD.

Linear programming, what are the advantages of linear programming?

what are the advantages of linear programming?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd