Explain pressure balance method and compressed air method, Civil Engineering

Assignment Help:

Pressure balance method vs. compressed air method in pipe jacking

Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand.  Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools. 

The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit. 

Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.


Related Discussions:- Explain pressure balance method and compressed air method

Calculate time taken for consolidation in actual layer, A clay layer 5 m th...

A clay layer 5 m thick has double drainage. It was consolidated under a load of 127.5 kN/m2. The load is enhanced to 197.5 kN/m 2 . The coefficient of volume compressibility is 5.7

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Calculate the amount of waste, Calculate the Amount of Waste A municipa...

Calculate the Amount of Waste A municipal solid waste department plans to separate a portion of the ferrous metal, newsprint and cardboard from its MSW waste stream. The depart

Define analytical methods approved under the clean water act, Define Analyt...

Define Analytical Methods Approved Under the Clean Water Act? Analytical Methods Approved Under the Clean Water Act CWA Section 304(h) needs EPA to publish test procedures (ana

Mollusca, what is the taxonomy of phylum molluska

what is the taxonomy of phylum molluska

Explain the design of graded filter, Q. Explain the design of graded filter...

Q. Explain the design of graded filter? Use of graded filter has been traditionally used below the revetment and protection works. The material used in the granular / graded fi

Overhanging beams, Do we take the whole length (including the over hanging ...

Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd