Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Pressure balance method vs. compressed air method in pipe jacking
Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand. Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools.
The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit.
Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.
Q. Do you mean by Accelerated Aging? Accelerated ageing tests are conducted at elevated temperature of 100 o C to know the variation in hardness, UTS and elongation at break.
what is the permissible limit of sand
what is the waste utilisation?
Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir
Define Contaminants - underwater inspection of bridge? There are various substances that may be inadvertently incorporated into the concrete matrix (e.g. glass, coal, gypsum),
calculate height of instrument?
Determine the latitude and departure of each side of the closed traverse ABCDA. Total the latitudes and departures. TIP: For Closed Traverse, Sum of Latitudes is Z
Question In checking quality of weld, what are pros and cons of a variety of non-destructive weld inspection methods as in ultrasonic test, radiographic inspection and magnetic
Blocked process list is not maintioned in priority order why
About Doors,windows&vendilators
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd