Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Pressure balance method vs. compressed air method in pipe jacking
Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand. Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools.
The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit.
Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.
Q. Purpose of setting minimum amount of longitudinal steel areas for columns? In some design codes it specifies that area of longitudinal steel reinforcement must be not less
procedure
Define Fixed instrumentation - Sounding or Sensing Devices? It is possible to monitor local scour at pier or abutment using fixed instrumentation as an alternative to the sound
Interface between base plates and footings Surface of footings is generally quite rough so that some levelling has to be carried out for base plates. Interface between base pl
Design a 10 unit rapid sand filter system for a flow of 6.3 MGD with a filtration rate of 2 gpm/sq ft. and an L: W ratio of 1.3. Design flow (Q) = 6.3 MGD = 6.3x106 gpd =
Question In designing of service reservoirs , straight reinforcement in walls of reservoirs is placed at external layer. Give some specific and main reasons? Answer
Q. Explain Remote sensing technique? Remote sensing is a science or an art of obtaining the information about an object, area or a phenomenon through analysis of data acquired
"We have one other pressing challenge that you could review for us," Alistair Wu says. "As you know, the Shanghai plant was our first facility in China, but we also have two other
Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note
why use wmm upon gsb can be laid dbm directly upon gsb
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd