Explain pressure balance method and compressed air method, Civil Engineering

Assignment Help:

Pressure balance method vs. compressed air method in pipe jacking

Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand.  Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools. 

The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit. 

Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.


Related Discussions:- Explain pressure balance method and compressed air method

#survey, Ask question #chaining and rangingMinimum 100 words accepted#

Ask question #chaining and rangingMinimum 100 words accepted#

Concrete technology, material for formwork and their specifications

material for formwork and their specifications

What is the station at point b, What is the station at Point B? SO...

What is the station at Point B? SOLUTION 3 Station at Point A = Sta 22+45  Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273'  = Sta 32+73

Stone, Explain briefly physical classifications of stone

Explain briefly physical classifications of stone

What is rail lubrication, Q. What is Rail Lubrication? Rail Lubrication...

Q. What is Rail Lubrication? Rail Lubrication is done on sharp curves where lateral wear is considerable. The function of Rail Lubrication is to lubricate or oil the running fa

Concrete pavement - thickness, Concrete Pavement: Thickness T...

Concrete Pavement: Thickness The thickness of concrete pavements is determined from the stresses induced due to loads and temperature. The thickness adopted is genera

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Constructed wetland design guidelines, Develop a simple urban constructed w...

Develop a simple urban constructed wetland design guidelines and drawings. Your report should include the following: I. Data required for the design II. Types of constructed

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd