Explain pressure balance method and compressed air method, Civil Engineering

Assignment Help:

Pressure balance method vs. compressed air method in pipe jacking

Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand.  Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools. 

The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit. 

Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.


Related Discussions:- Explain pressure balance method and compressed air method

Construction measurment, calculating quantity of excavation, formwork, conc...

calculating quantity of excavation, formwork, concrete

Concrete technology, chemical compositions of Rapid Hardening Cement

chemical compositions of Rapid Hardening Cement

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

#surveying & levelling, expressions for calculating corrections for earth c...

expressions for calculating corrections for earth curvature

Dry process of cement, i want a complete flow chart of dry process of cemen...

i want a complete flow chart of dry process of cement

How can rock sockets take up loads, Question How can rock sockets take ...

Question How can rock sockets take up loads? Answer Load transfer mechanism is brief as follows- While a socketed basis is loaded, conflict is provided by together

Determine the allowable pressue, The data profile as shown in Figure is obt...

The data profile as shown in Figure is obtained. A best average of N values gave N 10 = 21, column loads including dead and live loads ranged from 500 kN to 950 kN. Determine the

One-way pre stressing vs two-way pre stressing, Q. One-way pre stressing vs...

Q. One-way pre stressing vs two-way pre stressing? At the time of pre-stressing operation at one end, frictional losses will take place and the prestressing force decreases alo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd