Explain pressure balance method and compressed air method, Civil Engineering

Assignment Help:

Pressure balance method vs. compressed air method in pipe jacking

Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand.  Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools. 

The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit. 

Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.


Related Discussions:- Explain pressure balance method and compressed air method

P.h.e, procedure for designing of sewage scheme

procedure for designing of sewage scheme

Building, What quantity of cement will be needed to lay 2000 blocks of 9 in...

What quantity of cement will be needed to lay 2000 blocks of 9 inches using a mortar ratio of 1:6 with a thickness of 25mm in-between blocks.

Calculate the amount of concrete - construction management, An electrical c...

An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank

Deflection in concrete structures, Tension reinforcement leads to increasin...

Tension reinforcement leads to increasing deflection in concrete structures? In BS8110 a modification factor is applied to span/depth ratio to take into account effect of tens

Majority carriers are hols in, Majority carriers are hols in which type? ...

Majority carriers are hols in which type? Answer: In P-type semiconductors hols are majority carriers .

Mechanics of solids, if we take brass & steel and on applying temperature t...

if we take brass & steel and on applying temperature the brass contracts the steel expands how it is possible

What do by diaphragm wall, Q. What do by Diaphragm wall? For the constr...

Q. What do by Diaphragm wall? For the construction of diaphragm walls adjacent to buildings, former experience showed that excess slurry head above groundwater level had to be

Highway Engg, what are lab and field test carried on soil subgrade

what are lab and field test carried on soil subgrade?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd