Explain pressure balance method and compressed air method, Civil Engineering

Assignment Help:

Pressure balance method vs. compressed air method in pipe jacking

Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand.  Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools. 

The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit. 

Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.


Related Discussions:- Explain pressure balance method and compressed air method

Road location in dune areas, Road Location in Dune Areas: The followi...

Road Location in Dune Areas: The following principle should be observed in locating a road in dune areas : (a) Align a road where sand is covered by vegetation. (b) Sel

How to calculate the vertical stress, A rectangular foundation, 2 m × 4 m, ...

A rectangular foundation, 2 m × 4 m, transmits a uniform pressure of 450 kN/m 2 to the underlying soil. Verify the vertical stress at a depth of 1 metre below the foundation at a

Calculate the elastic stretch of the steel wire rope, A 70-ft long, ¾" diam...

A 70-ft long, ¾" diameter, 6 x 7 FC wire rope is resisting a tension force of 12-kips.  The elastic stretch of the steel wire rope given the following properties is most nearly: E

Determine stability of the upstream slope of an earth dam, Stability of the...

Stability of the upstream slope of an earth dam Give the step by step procedure for examining the stability of the upstream slope of an earth dam by the Swedish method of slice

Terminology of earthquake, TERMINOLOGY 1. Focus: The point on the fau...

TERMINOLOGY 1. Focus: The point on the fault where slip begins is the focus. It is also called as hypocentre 2. Epicentre: The point vertically above the focus on the su

Total maximum surface deflection of the pavement system, A stationary 40 kN...

A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming li

Necessity of reinforcement in precast concrete manhole units, Necessity of ...

Necessity of reinforcement in precast concrete manhole units Precast concrete manholes are generally constructed by placing the bases of manholes firstly. Walls of precast man

Define the abrasion - underwater inspection of bridge, Define the Abrasion ...

Define the Abrasion - underwater inspection of bridge? Abrasion damage is caused by continuous action of external forces on the surface of the concrete element. Erosive action

Mensuration, My team has to construct a swimming pool at the back of the ho...

My team has to construct a swimming pool at the back of the house. It’s interior dimensions are 10M x 3M and 1M at the shallow end and 2.5M at the deep end. The walls and the bas

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd