Explain predictive validity, Software Engineering

Assignment Help:

Q. Explain Predictive validity?

Predictive validity: It is the potential of the model to predict future failure behaviour from present and past failure behaviour. This capability is important only when failure behaviour is changing. There are two universal ways of viewing predictive validity based on the two equivalent approaches to characterizing failure random process namely

1. The number of failure approach as well as

2. The failure time approach.

We can visually ensure the predictive validity by plotting the relative error against the normalised test time.


Related Discussions:- Explain predictive validity

What does data modelling means, What does data modelling means? Data mo...

What does data modelling means? Data modelling is the first step in the analysis modelling. In data modelling the data objects are checked independently of processing. The data

What is the use of a data flow diagram, What is the use of a data flow diag...

What is the use of a data flow diagram? A data flow diagram is used to represent the functional view of an application domain. It represents all the significant business proces

Explain equivalent size measure software metrics, Q. Explain Equivalent siz...

Q. Explain Equivalent size measure software metrics? Equivalent size measure:- Models makes no distinction between a new software and the portion being reused. The equivalent

What is branch coverage testing, A test method satisfying coverage criteria...

A test method satisfying coverage criteria that needs each decision point at every possible branch to be implemented at least once.

Define about the erroneous data - Test data, Define about the erroneous dat...

Define about the erroneous data - Test data Abnormal/erroneous data  -  This is data outside the limits of validity/acceptability and must cause an error message to be g

Explain the software scope, Define software scope. The first software p...

Define software scope. The first software project management activity is the determination of software scope. Scope is defined answering the following questions. Context: Wh

What is the full form of eva, What is EVA? Earned Value Analysis is a ...

What is EVA? Earned Value Analysis is a technique of performing quantitative analysis of the software project. It gives a common value scale for each task of software projec

Explain data collection, Data collection A metrics programme should be ...

Data collection A metrics programme should be based on a set of product and process data. Data should be collected immediately (not in retrospect) and, if possible, automati

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd