Explain precedence relationships - construction management, Civil Engineering

Assignment Help:

Explain the Precedence Relationships

a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start

b. Finish to Finish - The predecessor activity must finish before the successor activity can finish

c. Start-to-Start - The predecessor activity must start before the successor activity can start

d. Start-to-Finish - the predecessor activity must start before the dependent activity can finish

 

601_Precedence Relationships.png

 


Related Discussions:- Explain precedence relationships - construction management

Disparity between working stress and limit state approach, Question Wha...

Question What is key disparity between working stress approach and limit state approach ? Answer Working stress approach, service loads are used in whole plan and st

Brigdes, infomation about differnt brigdes

infomation about differnt brigdes

Concrete, Determine the quantity of materials required per batch and probab...

Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows

Engineering project control, need help with my assignment. An Asian Pacific...

need help with my assignment. An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Pref

Light and rapid rail transit, Light Rail Transit (LRT) Light Rail Tra...

Light Rail Transit (LRT) Light Rail Transit is also known by the name train. LRT can be run on the surface if road space is available (as in Kolkata) or as elevated, with pil

Explain measured shovel packing, Explain Measured shovel Packing Measu...

Explain Measured shovel Packing Measured shovel Packing essentially consists of accurate measurements of track defects particularly the unevenness and voids caused in the cour

Expansion jiont, some expansion joint(10 mm- 20 mm) on my basement roof.rai...

some expansion joint(10 mm- 20 mm) on my basement roof.rain water leakage in basement i want the solution of expiation joint and water leakes.

Dam, Check for stability in a dam

Check for stability in a dam

How to calculate the diameter of the footing, A circular footing rests on a...

A circular footing rests on a pure clay with qu = 270 kN/m 2 , at a depth of 1.8 m. Verify the diameter of the footing if it has to transmit a load of 720 kN. Suppose the bulk u

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd