Explain national contingency plan (ncp), Civil Engineering

Assignment Help:

Explain National Contingency Plan (NCP)

- Provides detailed direction on the action to be taken at a hazardous waste site, including emergency actions and a method to rank sites to establish future actions

- NCP describes the steps to be taken for the detailed evaluation of the risks associated with a site, termed a remedial investigation(RI).  The process of selecting an appropriate remedy is termed the feasibility study(FS).

- Specifies the degree of cleanup to be selected in accordance with several criteria.

- There is no predetermined level of remediation that can be required or that must be achieved at a particular site.

- The degree of correction is established on a site-by-site basis.

- Upon completion and approval of the RI/FS, the preparation of the selected remedy is planned out in the remedial design.


Related Discussions:- Explain national contingency plan (ncp)

Concrete cracking, Attached information shows construction details of a wat...

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped

Fixed end moments, For fixed beam(say for example fixed with a point load a...

For fixed beam(say for example fixed with a point load at midspan) how did we end up getting P*L/8...??

The covers of electrical machines are made of what materials, The covers of...

The covers of electrical machines are made of what materials ? Answer: It is made of  soft magnetic materials.

Slabs, difference between flat slab and normal slab

difference between flat slab and normal slab

Concrete pavement, Question In case of concrete pavement, why is requir...

Question In case of concrete pavement, why is requirement of 95% by mass of quartz grains are specified in contract? Answer In universal Specification of Civil Enginee

Estimate prestress losses, Given: beam deminsions: flange width=22" FL...

Given: beam deminsions: flange width=22" FLANGE THICKNESS=7" WEB WIDTH=7" SECTION HEIGHT=40" f'c=5000psi f'ci=3500psi fpu=270ksi Ap=eighteen 1/2" diam strands superim

How are freeway bridges built, After measuring the anticipated traffic for ...

After measuring the anticipated traffic for the bridge, cement/reinforced- with- rebar stanchions are spaced over the freeway to accommodate the bridge. An 'off-ramp' from the free

Determine the ruthann graphical method, A retaining wall with a vertical ba...

A retaining wall with a vertical back 5 m high supports cohesion less backfill of unit weight of 19 kN/m 3 . The upper surface of the backfill rises at an angle of 10° with the hor

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd