Explain minimize make span in a two machine flow shop, Operation Management

Assignment Help:

Please explain your answer-

Johnson's rule gives the optimal answer for which of the following type of problems?

A) Minimize make span in a two machine flow shop

B) Minimize make span in a two machine job shop

C) Minimize make span in a single machine problem

D) Minimize make span in both two machine flow and job shops


Related Discussions:- Explain minimize make span in a two machine flow shop

Linear programming, Premier coatings Zambia ‘PCZ’ produce both interior and...

Premier coatings Zambia ‘PCZ’ produce both interior and exterior paints from two raw materials, Ml and M2. A market survey indicates that the daily demand for interior paint cannot

Explain the probability that the second item is defective, A production pro...

A production process is known to produce a particular item in such a way that 5% of these are defective. If two items are randomly selected as they come off the production line, wh

Explain how many machines should be purchased, Up, up, and away is a produc...

Up, up, and away is a producer of kites and wind socks. Relevant data on a bottleneck operation in the shop for the upcoming fiscal year are given in the following table: Item Kite

Explain this in relevance to uncertain events, Imagine the difficulties of ...

Imagine the difficulties of an employer whose decision context is choosing a new employee from a set of applicants whom he will interview. What do you think the employer's objectiv

Why knowledge is vital supervisor''s tactical planning, Why should a first-...

Why should a first-line supervisor understand the organization's objectives? Why is this knowledge important to the supervisor's tactical planning?

Explain one example from your professional experience, The process of outso...

The process of outsourcing the creation of a product or a service is a controversial, yet critical strategic decision for many employers. Describe one example from your professiona

Explain purpose of processing a digital crime, PDAs, iPods, iPhones, iPads,...

PDAs, iPods, iPhones, iPads, most cell phones, and other data devices are miniature computer systems designed to be highly mobile. Describe how such devices could alter the typical

Explain the different stages of group development, Question 1: There is...

Question 1: There is no use in considering non-financial issues when motivating people as many consider that money is the prime and only motivating factor. Discuss this st

Compute the standard time for each work, The Arkade Company has decided to ...

The Arkade Company has decided to use a 15 percent allowance factor based on job time. Calculate the standard time for each work element and for the total job. The frequency equals

Explain what is the efficiency process, An assembly line currently has five...

An assembly line currently has five workstations and the time required for each is shown below 1. 42sec 2. 49 sec. 3. 32 sec. 4. 47 sec. 5. 42 sec. What is the efficiency process?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd