Johnson's rule gives the optimal answer for which of the following type of problems?

A) Minimize make span in a two machine flow shop

B) Minimize make span in a two machine job shop

C) Minimize make span in a single machine problem

D) Minimize make span in both two machine flow and job shops


Related Discussions:- Explain minimize make span in a two machine flow shop

Describe what are the benefits of working for someone else, What are the be...

What are the benefits of working for someone else? What are the advantages of being part of a company or agency that is established? Explain. Reference/Cited

Define what is the probability that the battery will perform, An undergradu...

An undergraduate business student has purchased a laptop computer for use during exams. This laptop is perfectly reliable except for two parts: its microchip, which has a failure r

How do the stop process enter into the planning process, How does the stop ...

How does the stop process enter into the planning process?

Explain sales manager and credit manager learn to appreciate, 1. Can you de...

1. Can you devise strategies for the two viewpoints in a firm to live together harmoniously? 2. How can both the sales manager and credit manager learn to appreciate each other'

Explain what is the annual ordering cost, If annual demand is 24,000 units,...

If annual demand is 24,000 units, orders are placed every 0.5 months, and the cost to place an order is $50, what is the annual ordering cost?

Explain inventory tracking systems, Bill of Materials are kept current with...

Bill of Materials are kept current with changes using: a) Inventory Tracking Systems b) Engineering Change Order Systems c) Master Scheduling Systems d) Capacity Planni

Describe what is the expected value of perfect information, Director of leg...

Director of legal services of ABC Company must decide whether to hire another full-time lawyer or to hire part-time lawyers. Anticipated costs for the two options under three possi

Explain line balancing, Explain Line Balancing. Line Balancing: It m...

Explain Line Balancing. Line Balancing: It means balancing the line between the product lines or assembly lines. This aims at grouping facilities and workers in an efficient

Evaluate the performance of a bank holding company, The purpose of the proj...

The purpose of the project is to evaluate the performance of a bank holding company of your choice. 1. Choose a bank holding company. You can choose from Top 50 BHCs or find a b

Break Even Sales, K Ltd a multi product company, furnishes you the followin...

K Ltd a multi product company, furnishes you the following data relating to the year 2000. First half sales Second half sales Sales Rs.45000 Rs.50000 Total cost Rs.40000 Rs.43000

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd