Explain how might this process be improved, Operation Management

Assignment Help:

Abbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby make one large production run per model type. Plastic injection melding machines are used to make these parts and it is time consuming to clean and re-setup the machines between production runs. Each melding machine and operator works one nine-hour shift with a one-hour lunch break and one-half hour for operator breaks.

Consolidated Work Orders Work Order Quantity Setup (Changeover) Time per Work Order (Minutes) Processing Time per Panel (Seconds)

Model XVT-5 Case 11,500

panels 90 2.15

Model UYT-3 Case 6,500 60 1.78

Model KLY-6 Case 8,800 150 3.31

What is the total workload (demand) in hours for this work order mix? How many machines will it take to do this work in one, two, or three days?

How might this process be improved?


Related Discussions:- Explain how might this process be improved

Explain tomorrow''s business environment, Write a job description for a pos...

Write a job description for a position in tomorrow's business environment

Explain specifically about team incentive rewards, Do results from the surv...

Do results from the survey illustrate typical complaints about teams and specifically about team incentive rewards?

Compute the cycle time for the application process, The Central Evaluation ...

The Central Evaluation Unit Task 1: Analyse and evaluate the processing of new applications at the CEUPU: • Create a process map for new applications • Calculate the cycle time for

Explain the major risk factors of the disease, Select one chronic disease s...

Select one chronic disease such as diabetes or heart disease. Assume that you are working for a county public health department with staff nurses and physicians. You want to run a

Explain how many mocha latte coffees would be forecast, 4.31 Coffee Palace'...

4.31 Coffee Palace's manager, Joe Felan, suspects that demand for mocha latte coffees depends on the price being charged. Based on historical observations, Joe has gathered the fol

Explain importance of team preparation, • Prepare a 3 to 5 page paper discu...

• Prepare a 3 to 5 page paper discussing what conclusions you can reach on the importance of team preparation and member selection to the "Define" stage, and eventual success of Si

Calculate the expected value, C and S Metal company produces stainless stee...

C and S Metal company produces stainless steel pots and pans. C and S can pursue either of two distribution plans for the coming year. The firm can either produce pots and pans for

Explain how many customers could be served per hour, Greg Davis, a business...

Greg Davis, a business major at the University of South Carolina (USC), has opened Six Points Saco (SPS), a specialty subs-taco restaurant, at the rim of the USC campus. SPS has gr

Explain authority to make such an agreement, White, Fring, and Pinkman are ...

White, Fring, and Pinkman are partners in the operation of the A1A car wash. Without Fring's knowledge, White and Pinkman sold 10 percent of their interest in the business and its

Explain what is the expected project length, Task time estimates for the mo...

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows- a) 6.0 - b) 7.2 - c) 5.0 a d) 6.0 b,c e)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd