Explain how might this process be improved, Operation Management

Assignment Help:

Abbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby make one large production run per model type. Plastic injection melding machines are used to make these parts and it is time consuming to clean and re-setup the machines between production runs. Each melding machine and operator works one nine-hour shift with a one-hour lunch break and one-half hour for operator breaks.

Consolidated Work Orders Work Order Quantity Setup (Changeover) Time per Work Order (Minutes) Processing Time per Panel (Seconds)

Model XVT-5 Case 11,500

panels 90 2.15

Model UYT-3 Case 6,500 60 1.78

Model KLY-6 Case 8,800 150 3.31

What is the total workload (demand) in hours for this work order mix? How many machines will it take to do this work in one, two, or three days?

How might this process be improved?


Related Discussions:- Explain how might this process be improved

Define quality and definition of quality, 1) Definition of Quality Part 1: ...

1) Definition of Quality Part 1: How do you define Quality? Provide a definition of quality, support your definition, and define the stakeholders who are affected by your quality d

Explain what the best collaboration tools, For firms that have multiple loc...

For firms that have multiple locations that would like their professionals from different teams to be able to collaborate efficiently, how would you determine what the best collabo

Explain quality metrics, A variety of organizational culture characteristic...

A variety of organizational culture characteristics make project success more likely. The characteristics include: A. Sufficient funding B. Feasible schedule C. Respect fo

Efforts to reduce materials waste & procure materials, 1. In the hypothetic...

1. In the hypothetical manufacturing company (figure) what other actions do you think management might take in addition to their efforts to reduce materials waste, procure material

Linear programming, classification of linear programming on the basis of st...

classification of linear programming on the basis of structure

Responsiveness - customers needs for a product, Responsiveness - Customers ...

Responsiveness - Customers Needs for a Product How quickly the operations system reacts to changes in customer demand. This may be considered as customisation but in terms of

Describe a diet is being prepared for the university, A diet is being prepa...

A diet is being prepared for the University of Arizona dorms. The objective is to feed the students at the least cost, but the diet must have between 1,800 and 3,600 calories. No m

Management, explain the evolution of the subject operation management over ...

explain the evolution of the subject operation management over time

Explain steps are critical to sustaining change, Which of Kotter's 8 steps ...

Which of Kotter's 8 steps are critical to sustaining change? (You can list multiple steps.) Why do some change leaders fail to properly address sustaining change?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd