Explain how many crates will it need to plan, Operation Management

Assignment Help:

A bottling facility with an effective capacity of 40,000 crates per day operates with an efficiency of 85%. How many crates will it need to plan for bottling on a day that requires 33,300 crates to be shipped? Round to a whole number.


Related Discussions:- Explain how many crates will it need to plan

Why the production manager is asked to reduce the safety, The annual demand...

The annual demand for a product is 15,600 units. The weekly demand is 300 units with a standard deviation of 90 units. The cost to place an order is $31.20, and the time from order

Line balancing, what do you understand by line balancing what happens if ba...

what do you understand by line balancing what happens if balance doesn''t exist?

Describe alabama electric for a claim, Fred Flowers works for Alabama Elect...

Fred Flowers works for Alabama Electric and is a resident of the State of Florida. Following a series of storms in the Northeast, Alabama Electric sent Fred to Virginia as part of

Explain cars tend to break down at the rate of two per hour, During the cam...

During the campus Spring Fling, the bumper car amusement attraction has a problem of cars becoming disabled and in need of repair. Repair personnel can be hired at the rate of $20

Selection of operations in an organisation, Selection of Operations in an O...

Selection of Operations in an Organisation In any organisation there will be very many operations which could be studied; this step of the procedure addresses the question - w

Describe implications for the video game industry, Case Study- Implications...

Case Study- Implications for the Video Game Industry To consider the viability of Nintendo's new strategy, the CEO of Nintendo, has brought you in as a consultant. Your task is

What are the terminal course objectives, Class, looking back over the Termi...

Class, looking back over the Terminal Course Objectives for this course, what are you looking forward to learning more about throughout your education and career?

Explain what should johnson estimate time and parts costs, Johnson Industri...

Johnson Industries received a contract to develop and produce four high intensity long distance receiver/transmitters for cellular telephones. The first took 2000 labour hours, and

Explain capacity planning involving hiring, Capacity planning involving hir...

Capacity planning involving hiring, layoffs, some new tooling, minor equipment purchases, and subcontracting is considered as which one of the following planning horizons?

LOCATION AND LAYOUT, WHAT WOULD BE A GOOD RESEARCH QUESTION ON THIS TOPIC F...

WHAT WOULD BE A GOOD RESEARCH QUESTION ON THIS TOPIC FOR A GROUP PROJECT

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd