Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

How must organisations have the flexibility to demand occur, How must organ...

How must organisations have the flexibility to demand occur? Forecasting demand can be complicated and unreliable into an uncertain environment. Therefore a balance requires to

Explain the basic idea underlying the contingency view, Explain the basic i...

Explain the basic idea underlying the contingency view. How would you go about identifying key contingencies facing an organization?

Explain dispute arises the hotel management, A famous New York City hotel, ...

A famous New York City hotel, Hotel Lux, is noted for its food as well as its luxury accommodations. Hotel Lux contracts with a famous chef, Chef Perlee, to become its head chef at

Service profit chain - operation strategy, Service Profit Chain - Operation...

Service Profit Chain - Operation Strategy Prior to their work on the service-profit chain, Heskett and colleagues produced what they considered as the linkages between the emp

Explain which option is more economical, A company is the logistics vendor ...

A company is the logistics vendor for B Company. B has daily shipments of a power-steering pump from its Ohio plant to an auto assembly line in Alabama. The value of the standard s

Hard change initiatives - linking strategic, Hard Change Initiatives - Link...

Hard Change Initiatives - Linking Strategic 1. Total quality management (TQM)/ISO 9000  2. Enterprise resource planning (ERP)/material requirements planning; manufacturing

Explain what are the separate problems, One day a teller of a bank was robb...

One day a teller of a bank was robbed. When the robber ran the teller ran after him. Well over taking the robber, the teller was shot in the leg. The teller was given an award for

Compute a simple exponential smoothing forecast, The actual demand of the p...

The actual demand of the patients at Omaha Emergency Medical clinic for the first six weeks of the year are as follows: week Actual # of patients 1 65 2 62 3 70 4 48 5 63 6

Explain direct effects and indirect effects of goals, What is the differenc...

What is the difference between direct effects and indirect effects of Goals on choice of strategy?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd