Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Explain what are the social and ethical challenges, What are the social and...

What are the social and ethical challenges that Nike has to wrestle with?

Explain industrial products and consumer products, Compare and contrast ind...

Compare and contrast industrial products and consumer products

Production, Production Production is any process or  procedure develope...

Production Production is any process or  procedure developed to transform a set  of input elements  such as men,  materials capital, information and energy into a specified set

Product layout., define the following key terms in product layout; product...

define the following key terms in product layout; product interval time, product duration, assembly line balancing

Explain labour agreements, Outline and explain the three major elements (an...

Outline and explain the three major elements (and their arguments) contained in the controversial question as to whether union security provisions should be negotiated in labour ag

Product layout - connected flow, Product Layout - Connected Flow Where...

Product Layout - Connected Flow Where the demand for a single product is sufficiently high to warrant truly continuous operation (mass production for discrete items such as, c

Simo chart, It is sometimes required to record in minute detail the si...

It is sometimes required to record in minute detail the simultaneous movement of the different parts of the body of an operator during the performance of a single

Technological infrastructure, Identity technological infrastructure that su...

Identity technological infrastructure that supports operations management

Explain the company is expected to maintain growth rate, The Lo Tech Co. ju...

The Lo Tech Co. just issued a dividend of $2.30 per share on its common stock. The company is expected to maintain a constant 7 percent growth rate in its dividends indefinitely.

Explain effort-driven, Answer the followingquestions (use MS Project help i...

Answer the followingquestions (use MS Project help if necessary)- Define effort-driven? Under what circumstances would you turn off effort driven scheduling? Use a real-wo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd