Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

MBA, Q3. What do you understand by “line balancing”? What happens if balanc...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Define relationship between job satisfaction and performance, When Scott Tw...

When Scott Tweedy picked up a magazine article on how to manage health care workers, he was pleased to some advice. Scott was concerned about poor or mediocre performance on

Process design in operations managment, when asked to critically discuss ma...

when asked to critically discuss main factors that influence process design within a familiar organisation, does this mean a breakdown of the company''s design process or an analys

Explain partitioning a population into hierarchical group, Partitioning a p...

Partitioning a population into hierarchical groups or levels and selecting a sample from each group or level is known as which of the following? Simple random sampling Stra

Explain current managerial ranks or be sought from outside, Should the plan...

Should the plant manager come from inside the current managerial ranks or be sought from outside?

Explain the bargaining unit as technical workers, Jack is a 2nd level manag...

Jack is a 2nd level manager at Johnson Controls. His department includes 2 supervisors, 5 night shift security guards, 5 technical workers, 10 janitorial staff, and 25 manufacturin

Describe assaults a waitress at a nearby restaurant, A company hires a file...

A company hires a file clerk but does not inquire into his criminal history. In fact, he has had several convictions for driving while intoxicated. On a lunch break, he gets drunk

Frameworks for developing performance measures, Frameworks for Developing P...

Frameworks for Developing Performance Measures  There are a number of approaches which will be described here in broad terms:  The Kaplan and Norton balanced scorecard

Production Planning & Control, All of the following are time phasing requir...

All of the following are time phasing requirement of an MRP logic except Options Gross requirement will occur at the middle of a period On hand inventory will be measured

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd