Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

How to prove inadequate for governing the new nation, Why did the Articles ...

Why did the Articles of Confederation prove inadequate for governing the new nation? (Think about: national unity under the Articles; lack of an executive branch; economic issues

Explain why does it appeal to an approach to leadership, Write several para...

Write several paragraphs describing the aspects of a servant leader. Why does it appeal to an approach to leadership? What are some concerns? Why does servant leadership seem appro

Larger quantity purchases, A vendor's gives discounts to entice larger quan...

A vendor's gives discounts to entice larger quantity purchases.  The price breaks are as follows: Order Size    Discount    Unit Price     0 - 40              0%           $30 50

Define which of the following are valid range names in excel, Which of the ...

Which of the following are valid range names in Excel? Total Profit TotalProfit Total_Profit All of these b and c only

Explain the linear program, The linear program MAX 3A+4B St. -1A + 2b ? ...

The linear program MAX 3A+4B St. -1A + 2b ? 8 1A+2B ? 12 2A+1B ? 16 A,B ? 0 1-write this problem in the standard form ? 2-Solve the problem using the graphical solution proced

Internal factors - factor affecting productivity improvement, Internal Fact...

Internal Factors - Factors affecting productivity improvement These are the factors which may be modified by the company and may, in themselves, be sub-divided into two catego

Explain the change management factors, Describe the change management facto...

Describe the change management factors that shape HR-business strategy.

Advantages or disadvantages of diversity in the work place, 1. Discuss the ...

1. Discuss the advantages and disadvantages of diversity in the work place 2. Discuss some of the legal guidelines in place to protect diversity in the workplace 3. Identify

Explain counteract the high costs of obese employees, Answer the following ...

Answer the following questions: 1. What are the pros and cons of an airline implementing a policy that heavier customers need to buy a second seat? Research an airline and provi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd