Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Explain what is the first goal of national unions, What is the first goal o...

What is the first goal of national unions? Elections in units where employees are not currently represented are called? Corporate goal achievement is facilitated or inhibited

Explain disadvantages of functional systems and briefly, In this case study...

In this case study, you will review a case involving a functional system. The Lynx Company uses a functional system for their sales system. It takes the orders from their salesm

Explaining each milestone using the smart criteria, Identify at least eight...

Identify at least eight milestones for WBS and A Gantt chart. Write a one-page paper describing each milestone using the SMART criteria. Discuss how determining these milestones mi

Servqual model - consumption of service products, SERVQUAL Model - Consumpt...

SERVQUAL Model - Consumption of Service Products In later publications PZB, having analysed their data using factor analysis, reduced the original ten dimensions to the follow

Describe the term orginizational culture, Define the term orginizational cu...

Define the term orginizational culture. How might this company information enhance a sales presentation?

Explain project procurement management, When concerned with project procure...

When concerned with project procurement management regarding a project, list the different steps of the supply process and reasons why or why not the project would have been more s

Explain nominal work groups and the delphi techniques, Nominal work groups ...

Nominal work groups and the Delphi Techniques are used as part of which risk management process? Answer Risk identification Risk assessment Risk monitoring and control

Operation strategy for non profit organization, what should be the operatio...

what should be the operation strategy for non profit business?

Explain objectives along with your reasoning for creating, Imagine you are ...

Imagine you are the product manager for a new electric car similar to the Chevrolet Volt. Using all your knowledge of the new product life cycle, speculate on the stages of the lif

Memorandum, location analysis on expanding manufacturing plant

location analysis on expanding manufacturing plant

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd