Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Why the production manager is asked to reduce the safety, The annual demand...

The annual demand for a product is 15,600 units. The weekly demand is 300 units with a standard deviation of 90 units. The cost to place an order is $31.20, and the time from order

Explain managers tend to make teams too large, With regard to the question ...

With regard to the question of team size (i.e., how big the team should be), all of the following are true, except: a. Most of the time, teams should be fewer than 10 members b. Ma

Define summarize the organization technological solution, 1. Briefly summar...

1. Briefly summarize the organization technological solution. 2. Would you classify this as an enterprise or workgroup solution (review the Case Study Areas of Focus document in

Which kind of portable computer will meet everyones needs, Your organizatio...

Your organization plans to acquire 250 new portable computers. The finance vice president has asked you to lead a project team assigned to define users' computer hardware needs and

What are the three sequential operations, A manufacturing process consists ...

A manufacturing process consists of three sequential operations. At maximum capacity operation A can output 125 units per hour, Operation B can output 120 units per hour, and Opera

Approaches to expanding long term capacity, Approaches to Expanding long te...

Approaches to Expanding long term Capacity There  are two  major  approaches to  expanding  the long  term capacity  viz. All at once and Building  a capacity  increm

Explain what you understand by supply chain management, Question 1: (a)...

Question 1: (a) Explain what you understand by supply chain management. (b) An important decision facing most purchasing managers is whether to source each individual produc

Office management, how can we cover and understand the gaps in our company?...

how can we cover and understand the gaps in our company? and what is the slosh-an

Explain what are the upper and lower control chart limits, The defect rate ...

The defect rate for a product has historically been about 2.4%. What are the upper and lower control chart limits for a p-chart, if you wish to use a sample size of 100 and 3-sigma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd