Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Explain what are competencies, What are "competencies?" Explain, and provid...

What are "competencies?" Explain, and provide two or three examples.

Explain the concept of the quality of assurance system, Q. Explain the conc...

Q. Explain the concept of the quality of assurance system? Quality assurance is a systematic and planned action to give adequate confidence which a product or item conforms to

Explain what is the critical path, The following represents a project that ...

The following represents a project that should be scheduled using CPM: Time (DAYS) Activity Immediate Predecessors a m b A - 1 3 5 B - 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F

Explain how many machines should be purchased, Up, up, and away is a produc...

Up, up, and away is a producer of kites and wind socks. Relevant data on a bottleneck operation in the shop for the upcoming fiscal year are given in the following table: Item Kite

Normal distribution of frequency in the histogram, Normal Distribution of F...

Normal Distribution of Frequency in the Histogram The frequency distribution in the histogram was obtained from 200 measurements segregated into seven classes, each class havi

What needed to accurately predict capacity, 1) A process oriented layout wi...

1) A process oriented layout will minimize the total time spent on setting up machines? 2) By increasing the capacity of an operation you improve its efficiency. 3) Standard

Depict a sequence diagram, Hertford Post Office Situation: Hertford has a t...

Hertford Post Office Situation: Hertford has a typical small town post office that sells stamps, rents post office boxes, and delivers mail to postal customers. a. Identify possibl

Features of production and operation management, Features of Production and...

Features of Production and Operation Management 1. Production management is the process of making decisions. 2. Decisions are made regarding transformation of inputs outputs. 3

Explain los angeles court syestem, I need Los Angeles Court Syestem. I need...

I need Los Angeles Court Syestem. I need orginal thought no plagerism or won't award points. Assignment Complete the following, placing it in a single Word document. You h

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd