Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Explain what is the coefficient of determination, A large school district i...

A large school district is revaluating its teachers' salaries. They have decided to use regression analysis to predict mean teacher salaries at each elementary school. The research

Responsibilities of operations managers, what are the direct responsibiliti...

what are the direct responsibilities of operations managers?

Explain companies choose not to tie resources to their job, Some companies ...

Some companies choose not to tie resources to their projects. In what ways does this benefit a project? In what ways does this hinder a project?

Competitive priorties, explain basic competitive priorities considered whil...

explain basic competitive priorities considered while formulating operations strategy by a firm?

Explain team meetings can be helpful, Team meetings can be helpful. Interor...

Team meetings can be helpful. Interorganizational conflict is conflict that arises across organizations. What are sources of conflict?

Create an is strategy for an organisation, 1. Create an IS strategy for you...

1. Create an IS strategy for your organisation.  2. Give examples of the Data, Information and Knowledge that are used in your organisation. 3. How would the idea of sustaini

Resource allocation and Contingency planning, What are those topics all abo...

What are those topics all about? Can you give me a summary of that in a clear and understandable explanation. Thank you so much!

Explain elements of a typical scope statemen, Analyze the elements of a typ...

Analyze the elements of a typical scope statement and the significance of each element. As a project leader, determine how you would communicate the scope of a project to the proje

Explain an in-n-out pay strategy, An In-N-Out Pay Strategy: Costa Vida's De...

An In-N-Out Pay Strategy: Costa Vida's Decision to Boost Pay

Why it is vital government to regulate businesses operating, • Explain at l...

• Explain at least two ways in which poor cost management could negatively impact a business. Provide support for your rationale. • Discuss three reasons why it is important for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd