Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Batch operations - operations function, Batch Operations - Operations Funct...

Batch Operations - Operations Function Batch systems form an intermediate category, and are the most common. Here, many different products are produced at regular or irregular

Explain what is activity-based costing, 1. What is activity-based costing? ...

1. What is activity-based costing? 2. What are three of the five purposes of a performance measurement system? 3. What are three of the five benefits listed that the right informat

Manager case, In the table given below the Distribution Manager is expected...

In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what woul

Explain regulatory organizations, "Regulatory Organizations" Please respond...

"Regulatory Organizations" Please respond to the following: • Evaluate the effectiveness of JCAHO%u2019s recommendations for emergency preparedness. Discuss which recommendation

Define what would the average inventory be for this lot size, A chemical fi...

A chemical firm produces sodium bisulfate in 100-pound bags. Demand for this product is 20 tons per day. The capacity for producing the product is 50 tons per day. Setup costs $100

Explicitly explain the role you will take as chair, 1. When a group wants t...

1. When a group wants to achieve a consensus or unanimous decision, the responsibility of the chair is to be constantly attentive to the group process. Identify which of the pointe

Explain the best leader you ever had and why, 1. Describe in your own words...

1. Describe in your own words the best leader you ever had and why? Be specific in your answers as to the impact this leader had in your workplace. 2. Describe in your own words

Describe communication skills, From the scenarios, we see that Chris and Er...

From the scenarios, we see that Chris and Erica have different communication styles that could potentially have a negative impact on the business. Suggest at least two strategies t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd