Explain gap survey and adjustment of gap, Civil Engineering

Assignment Help:

Q. Explain Gap Survey and adjustment of Gap?

Gap survey and rectification of gaps is to be carried out, in stretches where track develops excessive creep jammed joints, sun kinks, buckling, wide gaps, battered and hogged joints, fractures at joints and bending of bolts etc. In SWR the gap survey and adjustment should normally be done before the end of February once a year (i.e., before onset of Summer).

The gap survey shall be conducted on a clear and sunny day in the cool hours of the day.

The length over which gap survey is to be done should, wherever possible, be divided into suitable sub-sections, each bounded by fixed points such as level crossings, points and crossings etc. The survey should be completed during as short a time as possible, by employing adequate number of parties so that the rail temperature is not likely to vary appreciably.

The joint gaps shall be measured by taper gauge in mm. and the readings entered in the pro forma.


Related Discussions:- Explain gap survey and adjustment of gap

Emulsion - road materials, Emulsion: An emulsion is a bituminous bind...

Emulsion: An emulsion is a bituminous binder which is in a fluid form at atmospheric temperatures above O o C and requires no heating at all. Bitumen cab be converted to an e

Define the degree of saturation and soil moisture content, Establish the r...

Establish the relationship among degree of saturation, soil moisture content, definite gravity of soil particles, and void ratio. The volume of an undisturbed clay sample having

Delay of bituminous laying on top of sub-base, Question In case if ther...

Question In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base? Answer When there is a d

Describe the consolidation settlement, Q. Describe the Consolidation Settle...

Q. Describe the Consolidation Settlement? The resulting settlements which are time-dependent and are termed consolidation settlements. After the consolidation settlements take

Distomat, applications of distomat in briefly

applications of distomat in briefly

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd