Explain flash butt welding, Civil Engineering

Assignment Help:

Q. Explain Flash Butt welding?

In this process the ends of two rails are kept at fixed distance apart and a mould (designed to suit the rail section ) is fitted on. The rail ends are then heated to yellow red temperature with a blowlamp. A swiveling type crucible containing iron oxide and aluminum powder to match the metallurgical composition of the rails is then ignited and the molten metal is poured into the mould so that the gap between the rail ends is filled up with over flow on all sides. The mould is then removed and excess metal is chipped off from the railhead while still hot. Later it is filed to railhead profile.

Normally it takes 45 minutes to weld a joint but by quick thermit process it can be done in 15 minutes. The joint can be brought into use immediately after welding.


Related Discussions:- Explain flash butt welding

What do you mean by guide bunds, Q. What do you mean by Guide bunds? Gu...

Q. What do you mean by Guide bunds? Guide bund may be given an elliptical shape separation of flow can be avoided better with such an alignment. Alternatively straight parallel

Home, Ask question #Mindasfimum 100 words accepted#

Ask question #Mindasfimum 100 words accepted#

Loading and unloading cycles for soil nails, In carrying out pull-out tests...

In carrying out pull-out tests for soil nails, it generally requires the unloading and loading of soil nails of several cycles up to 80% of ultimate tensile strength of soil nails.

Define lateral load - actions in pot bearings, Define Lateral Load - Action...

Define Lateral Load - Actions in POT Bearings? Lateral load is transferred from the piston to the POT by contact between the rim of the piston and the wall of the POT. The cont

Neglecting bearing at the tip of the piles, A square pile group of 9 piles ...

A square pile group of 9 piles of 25 cm diameter is arranged with a pile spacing of 1m. The length of the piles is 9 m. Unit cohesion of the clay is 75 kN/m 2 . Neglecting beari

Calculate the amount of waste, Calculate the Amount of Waste A municipa...

Calculate the Amount of Waste A municipal solid waste department plans to separate a portion of the ferrous metal, newsprint and cardboard from its MSW waste stream. The depart

Harbour, typical layout showing dock,quay.jetties,turning circle,pier

typical layout showing dock,quay.jetties,turning circle,pier

Meaning of driving succession of driven piles, Question What is meaning...

Question What is meaning of driving succession of driven piles? Answer In Basement construction, if piles are driven from centre to perimeter, there is a propensity o

Determine the magnitude of application of the active thrust, A retaining wa...

A retaining wall 9 m high retains cohesion less soil, with an angle of internal friction 33°. The surface is level with the top of the wall. The unit weight of the top 3 m of the f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd