Explain equation for change interval, Civil Engineering

Assignment Help:

Explain equation for Change Interval

y = t + v / 2a + 64.4G

Where:  y = length of yellow interval (sec)

    t = driver perception/reaction time (1.0 sec generally used)

    v = velocity of approaching vehicle (fps)

    a = deceleration rate (10 fps2 generally used) 

    G = grade of approach (percent/100)   

                         If G is positive percent or upgrade, use '+' symbol 

                         If G is negative percent or downhill, use '-' symbol


Related Discussions:- Explain equation for change interval

What are some facts about concrete, Actually, drying is not directly linked...

Actually, drying is not directly linked to hardness in concrete. After concrete is poured, putting it in a wet environment by spraying it constantly with water will hasten its hard

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

.Chemestry, How desalination of water can be acheived by reverse osmosis an...

How desalination of water can be acheived by reverse osmosis and electrodialysis process?

Uses of bricks, Uses of Bricks In the following civil works Bricks are ...

Uses of Bricks In the following civil works Bricks are used: a. in building blocks. b. For lining of ovens, chimneys and furnaces. c. As aggregates in providing water

Self compacting concrete, what will be the w/c ration and cement/fly ash ra...

what will be the w/c ration and cement/fly ash ration for the particular mix design

Determine the probable period of time, A clay stratum is 4.5 m thick and re...

A clay stratum is 4.5 m thick and rests on a rock surface. The coefficient of consolidation of a sample of this clay was found to be 4.5 × 10-8 m 2 /s in the laboratory. Verify pro

Mixed ground with soils and boulders, Ground settlement occurs when pipe-ja...

Ground settlement occurs when pipe-jacking machine enters mixed ground with soils and boulders? The rate of cutting through soils is faster than cutting through boulders for pi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd