Explain delays in the project mean that the center, Operation Management

Assignment Help:

Your in charge of a project at the local community center. The center needs to remodel one of the room in time for the start of a new program. Delays in the project mean that the center must rent other space at nearby church at additional cost. Time and cost data for you project are contained in the table: Your interest is minimizing the cost for the project to the community center. a) Using the normal timr for each activity, what is the ealiest date you can complete the project? b) Suppose the variable overhead costs are $ 50 per day for your project. Also, suppose that the center must pay $ 40 per day for temporary room on day 15 or beyond. Find the minimum-cost project schedule.

Activity NormL(T) Normal Cost ($) Crash T(days) Crash Cost($) Immediate Predecessors

Start 0 0 0 0
A 10 50 8 150 Start
B 4 40 2 200 Start
C 7 70 6 160 B
D 2 20 1 50 A,C
E 3 30 3 30 A,C
F 8 80 5 290 B
G 5 50 4 180 D
H 6 60 3 180 E,F
Finish 0 0 0 0 G,H


Related Discussions:- Explain delays in the project mean that the center

Explain what is your assessment of the health of the project, On day 51, a ...

On day 51, a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the he

Explain responsibility of improving automobile loans, A loan manager for Ba...

A loan manager for Bank of Cascades has the responsibility of improving automobile loans. To assist her in this matter, she has compiled data on 428 cars and trucks. This data are

Describe what information should be shared with partners, The EGAD Bottling...

The EGAD Bottling Company has decided to introduce a new line of premium bottled water that will include several "designer" flavours. Marketing manager Georgiana Mercer is predicti

Illustrate the examples of the inventory control systems, Illustrate the ex...

Illustrate the examples of the inventory control systems? Examples of inventory control systems Reorder level systems: When the current stock level decreased below a

Characteristics of continuous or flow production, Characteristics of Contin...

Characteristics of Continuous or Flow Production Flow of Material: The flow of materials is continuous and there is little or no queuing at any stage of processing. Mac

Explain implementation of a transnational strategy, What do you see as the ...

What do you see as the main organizational problems that are likely to be associated with implementation of a transnational strategy? Explain

Explain project selection, "Project Selection" •For the purpose of completi...

"Project Selection" •For the purpose of completing the requirements of this course, select an actual business or personal project that assumes duration of 15 months and a functiona

Explain compensated for the loss in purchasing power, Fourteen years ago, t...

Fourteen years ago, the U.S. Aluminium Corporation borrowed $9.9 million. Since then, cumulative inflation has been 98 percent (a compound rate of approximately 5 percent per year)

Compute the expected monetary value, Superior Products Inc. is considering ...

Superior Products Inc. is considering two potential equipment alternatives for production of their best selling product line. Option 1 involves proven equipment: Fixed cost investm

Organizational change which starbucks implemented in 2008, I need a two par...

I need a two paragraph (one page) paper on the organizational change that Starbucks implemented in 2008

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd