What is cyclomatic complexity?

Cyclomatic complexity is software metric that gives the quantitative measure of logical complexity of the program.

The Cyclomatic complexity explains the number of independent paths in the basis set of the program that gives the upper bound for the number of tests that must be conducted to make sure that all the statements have been implemented at least once.

 


Related Discussions:- Explain cyclomatic complexity

How is the state diagram helpful to an engineer, Problem: a) Assume a w...

Problem: a) Assume a washing machine. List all possible states of the washing machine. Draw a state diagram showing also the events triggering the change of states where poss

Explain quick-fix model, Explain Quick-fix Model Quick-fix Model : Thi...

Explain Quick-fix Model Quick-fix Model : This is the easiest model used for the maintenance of the software. In this model changes at the code level are made as early as poss

Illustrate the symbols of a data flow diagram, Symbols of a data flow diagr...

Symbols of a data flow diagram  1. Data Flow Signifies the connectivity between various processes 2. Process   Performs some processing of input data 3. Ex

Swot analysis, how to threat into opportunities and weaknesses into streng...

how to threat into opportunities and weaknesses into strength

Explain the software scope, Define software scope. The first software p...

Define software scope. The first software project management activity is the determination of software scope. Scope is defined answering the following questions. Context: Wh

Describe various types of cohesion, Describe various types of Cohesion? ...

Describe various types of Cohesion? i. Coincidentally cohesive -The modules in which the set I\of tasks are linked with each other loosely then these modules are called coincid

What are the three activities of risk assessment, What are the three activi...

What are the three activities of risk assessment? Ans: The three activities are analyzing, identifying and giving priorities. Risks are able to be identified by a check list

Srs, Why is SRS document known as black box specification of a system

Why is SRS document known as black box specification of a system

Flow chart, desidn a complete flow chart diagram ,which ask the user to inp...

desidn a complete flow chart diagram ,which ask the user to input the rate of diesel and quantity of diesel consumed.after calculate the total amount of diesel consumed and display

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd