Which of the following is normally not addressed in a change control board meeting to approve a scope change?

Answer

Cost of the change

Which functional unit will perform the change

Impact on the schedule

Value-added opportunity for the client


Related Discussions:- Explain control board meeting to approve a scope change

System complexity - boulding taxonomy, System complexity - Boulding taxonom...

System complexity - Boulding taxonomy  To obtain an insight into the nature of the system with which the operations manager is dealing, consider the economist Kenneth Boulding

Health and safety, what are the roles of the health and saety committees

what are the roles of the health and saety committees

Compute the expected average flow time, New Time Videos (NTV) is a new on-l...

New Time Videos (NTV) is a new on-line video rental service. In the field, it is trying to compete by offering its customers access to all of the major new video releases in one bu

Explain what should johnson estimate time and parts costs, Johnson Industri...

Johnson Industries received a contract to develop and produce four high intensity long distance receiver/transmitters for cellular telephones. The first took 2000 labour hours, and

Explain when communicating a change, When communicating a change, which rol...

When communicating a change, which role is more important: reporter of information or sense maker? Why

Demerits of a phased system roll-out for bombardier, 1) In your opinion, ho...

1) In your opinion, how does the visioning phase of the Bombardier ERP project impact the rest of the project? 2) What organizational outcomes did Bombardier expect with a succe

Explain type of organization structure face and why, Under what conditions ...

Under what conditions are customer-centric structures appropriate and what challenges does this type of organization structure face and why?

Explain providing detailed project management methodologies, Portfolio alig...

Portfolio alignment helps an organization achieve its goals by A. Adopting highly similar project to insure against failure B. Including a complement of projects with differe

Strategic service concept and service delivery system, Strategic Service Co...

Strategic Service Concept and Consideration of Service Delivery System Service has been singled out for particular attention. Product differentiation is a relatively visible

Give a specific definition of time study, Give a specific definition of tim...

Give a specific definition of time study. Time study It is defined as a work measurement technique for recording the times and rate of working for the component of a speci

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd