Explain build the pilot project and then make a decision, Operation Management

Assignment Help:

Dan Reid, chief engineer at New Hampshire Chemical, Inc., has to decide whether to build a new state-of-art processing facility. If the new facility works, the company y could realize a profit of $200,000. If it fails, New Hampshire Chemical could lose $150,000. At this time, Reid estimates a 60% chance that the new process will fail. The other option is to build a pilot plant and then decide whether to build a complete facility. The pilot plant would cost $10,000 to build. Reid estimates a fifty-fifty chance that the pilot plant will work. If the pilot plant works, there is a 90% probability that the complete plant, if it is built, will also work. If the pilot plant does not work, there is only a 20% chance that the complete project (if it is constructed) will work. Reid faces a dilemma. Should he build the plant? Should he build the pilot project and then make a decision? Help Reid by analyzing this problem.


Related Discussions:- Explain build the pilot project and then make a decision

Explain bruce wayne routinely participates in activities, Bruce Wayne routi...

Bruce Wayne routinely participates in activities such as skydiving, rock climbing and bungy jumping. His employer told him to stop the activities or they would cancel his health in

Compute the operating characteristics of interest, An urn contains nine whi...

An urn contains nine white balls and 11 black balls. A ball is drawn and replaced. If the ball is white your opponent pays you 25 cents. If it is black you pay him 25 cents. You ha

Explain the term total quality management, Explain the term Total Quality M...

Explain the term Total Quality Management (TQM). Total Quality Management (TQM): It is a system approach to quality in all spheres of the organisation. TQM implies meeting th

Explain the overall strategy, Put yourself in the position of an entreprene...

Put yourself in the position of an entrepreneur who is developing a new product to introduce into the market. Briefly describe the product. Then develop the segmentation, targeting

Products produced by project, 1. Identify products which you would expect t...

1. Identify products which you would expect to be produced by each of the following configurations: project, job shop, and batch and continuous. Answer: Many possible answers:

Explain manufacturing and service processes using queuing, Briefly compare ...

Briefly compare and contrast the manufacturing and service processes using queuing and assembly lines as your items to compare and contrast

Explain implied warranties of merchantability, The UCC includes both implie...

The UCC includes both implied warranties of merchantability, warranties of fitness, and product liability. Some of these warranties protect the customer from defective products and

Drawbacks and challenges designing this job for efficiency, Consider the jo...

Consider the job of a customer service representative who fields telephone calls from customers of a retailer that sells online and through catalogs. What measures can an employer

#facility manger, to find a medium that works across 4 other facility sites...

to find a medium that works across 4 other facility sites on how to properly and effectively maintain facility design, to all model after eachother

Mass Production and Continuous Flow Manufacturing, Mass Production and Cont...

Mass Production and Continuous Flow Manufacturing  Continuous systems lie at the other extreme, where demand for a single product is sufficiently high to warrant the installa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd