Q. Explain about Unit pipe racks?

Unit pipe racks are the main arteries carrying the pipes and cables into the units, and as such should be centrally located. They are usually elevated, and are of sufficient height to allow vehicle access beneath. The width of rack will be determined by the number of lines and cable trays with an allowance for future requirements.

Piping should enter/leave from above or below the rack level. Piping should not flat turn on or off the rack closing out space for installation of future lines. Lines requiring expansion loops should be located close to pipe rack columns and should be grouped together to enable use of common supports. Space between levels must be sufficient to allow the largest lines to leave or enter the rack.

Electrical and instrument cable trays are normally run in or off the side of the pipe racks. The Piping Designer shall liaise with these disciplines to allocate these areas. Cable trays systems shall be kept away from hot lines. When there are large numbers of cable trays, they should be installed at the highest levels of the rack and process pipes should not be crossing or running above them.


Related Discussions:- Explain about unit pipe racks

Illustrate the electromagnetic clutch, Illustrate the Centrifugal Clutch in...

Illustrate the Centrifugal Clutch in Detail with neat sketch ? Illustrate the Electromagnetic Clutch in Detail with neat sketch ? Illustrate the Diaphragm spring Clutch in

Estimate the cutting time, Estimate the Cutting Time A surface 115 mm ...

Estimate the Cutting Time A surface 115 mm wide and 250 mm long is to be rough milled with a depth of cut of 6 mm by a 16-tooth cemented carbide face mill 150 mm in diameter.

Process selection and sequencing, Process Selection and Sequencing In th...

Process Selection and Sequencing In this, some factors, which have an influence in all processes, are discussed. The factors include size, shape complexity, tolerances and produ

Welding, function of helium shielding gas

function of helium shielding gas

Derive the equation for the pressure difference, The differential manometer...

The differential manometer (shown below) is used to measure the pressure difference between two vessels. Derive the equation for the pressure difference (pA - pB) in terms of the l

Show modular structures layout, Q. Show Modular Structures layout? Outs...

Q. Show Modular Structures layout? Outside dimensions and weight of truckable modules shall not exceed limits specified, Modular Structures in GS-904-0103. Minimum head clearan

Construction of lacashire boiler, Construction of Lacashire boiler: C...

Construction of Lacashire boiler: CONSTRUCTION : Consists of boiler shell which contains water and steam. Diameter can vary from 1.75 to 2.75 m and length can be 7.25 - 9 m

Importance of stresses in shaft, Importance of stresses in shaft: Wha...

Importance of stresses in shaft: What is  importance of stresses in shaft ? Sol.: In shaft the following significant stresses occur. 1. A maximum shear stress occurs on

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd