Unit pipe racks are the main arteries carrying the pipes and cables into the units, and as such should be centrally located. They are usually elevated, and are of sufficient height to allow vehicle access beneath. The width of rack will be determined by the number of lines and cable trays with an allowance for future requirements.

Piping should enter/leave from above or below the rack level. Piping should not flat turn on or off the rack closing out space for installation of future lines. Lines requiring expansion loops should be located close to pipe rack columns and should be grouped together to enable use of common supports. Space between levels must be sufficient to allow the largest lines to leave or enter the rack.

Electrical and instrument cable trays are normally run in or off the side of the pipe racks. The Piping Designer shall liaise with these disciplines to allocate these areas. Cable trays systems shall be kept away from hot lines. When there are large numbers of cable trays, they should be installed at the highest levels of the rack and process pipes should not be crossing or running above them.


Related Discussions:- Explain about unit pipe racks

Thermodynamics.., what is critical pressure, triple point, degree of super ...

what is critical pressure, triple point, degree of super heat...

Diffrence between external diameter and internal diameter, Diffrence betwee...

Diffrence between external diameter and internal diameter: A compound tube is built by shrinking one tube on another, the ultimate dimension being, 80 mm internal diameter, 16

Parallelograular law of forces and triangular of forces, two forces are act...

two forces are acting at a point''o'',determine magnitude and direction by using parallelogram law of forces and triangular law of forces

Extrusion, Difference between hot extrusion and cold extrusion

Difference between hot extrusion and cold extrusion

Piping stress analysis, The Mechanical Engineer/Specialist shall be respons...

The Mechanical Engineer/Specialist shall be responsible for coordinating project issues related to stress analysis, as they relate to his/her equipment, with the Stress Engineer/Sp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd