Explain about unit pipe racks, Mechanical Engineering

Assignment Help:

Q. Explain about Unit pipe racks?

Unit pipe racks are the main arteries carrying the pipes and cables into the units, and as such should be centrally located. They are usually elevated, and are of sufficient height to allow vehicle access beneath. The width of rack will be determined by the number of lines and cable trays with an allowance for future requirements.

Piping should enter/leave from above or below the rack level. Piping should not flat turn on or off the rack closing out space for installation of future lines. Lines requiring expansion loops should be located close to pipe rack columns and should be grouped together to enable use of common supports. Space between levels must be sufficient to allow the largest lines to leave or enter the rack.

Electrical and instrument cable trays are normally run in or off the side of the pipe racks. The Piping Designer shall liaise with these disciplines to allocate these areas. Cable trays systems shall be kept away from hot lines. When there are large numbers of cable trays, they should be installed at the highest levels of the rack and process pipes should not be crossing or running above them.


Related Discussions:- Explain about unit pipe racks

Mechanical material requisition, The Mechanical Engineer/Specialist shall p...

The Mechanical Engineer/Specialist shall prepare Material Requisitions for all required mechanical material and equipment. The format for all requisitions shall be in accordance w

Wedge problems, How to solve wedge problems..can anyone just explain the me...

How to solve wedge problems..can anyone just explain the method..

Classify the various types of manometers, (a) What are fluids? How are they...

(a) What are fluids? How are they classified? (b) Classify the several kinds of manometers. (c) Define the following (d) Define metacenter (1) Steady flow (2) Unsteady

Materials requirements planning, Materials requirements planning: Mate...

Materials requirements planning: Materials requirements planning (MRP) is a set of process for converting forecasted demand for a manufactured product into a requirement sched

About Transfer Function block, How can i change the normal function block p...

How can i change the normal function block parameter[1 1]=>(s+1) to (s-1)?

Determine tension in horizontal rope , Determine tension in horizontal rope...

Determine tension in horizontal rope: Q:  A 500N cylinder, 1 m in diameter is loaded between cross pieces AE and BD that make an angle of 60º with each other and are pinn

Optimization, consider the following LPP max z=9x1+8x2+5x3 subject to 2x1+3...

consider the following LPP max z=9x1+8x2+5x3 subject to 2x1+3x2+x3 5x1+4x2+3x3 x1,x2,x3>_0 (a)solve using simlex method (b)hence using the sesitivity analysis

Explain the working of radial drilling machine, Normal 0 false ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd