Q. Explain about Unit pipe racks?
Unit pipe racks are the main arteries carrying the pipes and cables into the units, and as such should be centrally located. They are usually elevated, and are of sufficient height to allow vehicle access beneath. The width of rack will be determined by the number of lines and cable trays with an allowance for future requirements.
Piping should enter/leave from above or below the rack level. Piping should not flat turn on or off the rack closing out space for installation of future lines. Lines requiring expansion loops should be located close to pipe rack columns and should be grouped together to enable use of common supports. Space between levels must be sufficient to allow the largest lines to leave or enter the rack.
Electrical and instrument cable trays are normally run in or off the side of the pipe racks. The Piping Designer shall liaise with these disciplines to allocate these areas. Cable trays systems shall be kept away from hot lines. When there are large numbers of cable trays, they should be installed at the highest levels of the rack and process pipes should not be crossing or running above them.
The salary calculation method for employees of a company is as follows: (1) If the number of working hours exceeds 120 hours, an additional 15% will be issued for the excess part;
(a) Show that two statements of Second Law of thermodynamics are similar to each other. (b) A house that was heated by electric resistance heater consumed 1200 KWh of electric e
What is elements with increasing dimensions?
Q. What do you understand by Carburization? Carburization is initiated by the adsorption of carbon in contact with the surface of the metal and may progress by diffusion along
Q. Show drain systems used in plant? Process/power plants usually have a variety of different drain systems to collect the different types of liquid effluent. One of these is u
Cam: This is an integral part of camshaft. A cam is designed in such a way as to open or close the valves at the correct timing and keep them open for the necessary duration.
what is the two purposes of surveying
Specifi c Heat: The specific Heat of a solid or liquid can be usually defined as heat required for raising unit mass through one degree temperature rise. That is, dQ = m
Ask okokopkpk#Minimum 100 words accepted#
1. Write a short note (not more than half A4 page) on your understanding on St. Venant's Principal for your engineering design analysis. 2. Estimate the " Stress Concentration
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd