Explain about the Critical Path.

Critical Path:

Calculation of Earliest and Latest Values of the events of the given network is as below:

Event

EOT

LOT

1

0

0

2

6

6

3

5

6

4

9

9

5

16

16

The critical path now is 1→2→4→5.


Related Discussions:- Explain about the critical path

Explain the components of the specific business environment, Question: ...

Question: (a) Frederick Taylor observed that workers worked below their optimum level (soldiering). He thus devised systematic methods based on a set of principles. These princ

How is the breakeven point computed, How is the breakeven point computed? ...

How is the breakeven point computed? The Break Even Point (BEP) can be computed by using the given relation as follows:                                BEP = F / 1-V/P

Recruitment, what are the challenges constrain that are found in recruitmen...

what are the challenges constrain that are found in recruitment

Discuss the exceptions to the law of demand, Question 1 Discuss the except...

Question 1 Discuss the exceptions to the law of demand Question 2 Explain Elasticity of Supply with the help of a diagram and factors affecting elasticity of supply

What are the uses of control chart, What are the uses of control chart? ...

What are the uses of control chart? Control chart: It is a daily graphical presentation of the collected information. Therefore information pertains to the measured or ot

Business level strategy in firm, 1. Discuss the concept of strategy and di...

1. Discuss the concept of strategy and discuss differences between corporate level strategy and business level strategy in firm? 2. "Good corporate governance in firm leads t

Discuss ways to prevent inter-cultural misinterpretations, QUESTION No...

QUESTION Non-verbal behaviour is prone to being wrongly interpreted in intercultural encounters (Guirdham, 1999). Therefore, using a level of assertiveness which is appropriat

Benefits of holding inventories, There are three main purposes or motive...

There are three main purposes or motives of holing inventories: a. The transaction Motive : Which facilitates continuous production and timely execution of sales orders

Value chain analysis , I want to make a report on Value chain analysis for ...

I want to make a report on Value chain analysis for Recycle used cloth business

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd