Example of simple exponential smoothing, Mechanical Engineering

Assignment Help:

Example of simple exponential smoothing:

A TV manufacturer utilizes simple exponential smoothing with α = 0.1 to forecast demand. For the first week of March, the forecast was 400 units while actual demand turned out to be 370 units.

1. Forecast the demand for the second week of March.

2. If the actual demand for the second week turned out to be 417 units, forecast the demand for the 3rd week. Continue forecasting for the subsequent four weeks. You can take actual demands for the subsequent weeks as 409, 388, 377, 445, and 410 units.

3. Develop an adjusted exponential forecast for this company. You may assume the initial trend adjustment factor Tt as zero and β = 0.1.

Solution

(a) Ft + 1 = Ft + α (Dt - Ft)

                     = 400 + 0.1 (370 - 400) = 397 units.

 (b)

707_Adjusted Exponential Smoothing.png

(c)        The trend adjustment is accomplished by total of a correction factor

[(( 1 -β )/ β ) Tt +1 )]   to the simple exponential forecast.

As the initial trend adjustment factor (given) Tt = 0, we have

March 1st Week

Tt + 1 = β (Ft + 1 - Ft) + (1 - β) Tt

= 0.1 (397 - 400) + (0.9) (0) = - 0.30

T(t +1) adj = Ft +1 +( 1 -β / β )T t +1

= 397 +( 0.9/0.1)  (- 0.30) = 394.30

The adjusted forecast for the second week of March = 394.30.

March 2nd Week

Tt + 1 = 0.1 (399 - 397) + (0.9) (- 0.30)

= 0.2 - 0.27 = - 0.07

F(t + 1) adj = 399 + 9 (- 0.07) = 398.37

The remaining values may be put in table form, as below.

606_Adjusted Exponential Smoothing1.png

The trend-adjusted forecast for the third week of April is Ft, adj   = 393.54 units whereas simple exponential forecast for the same week is 400 units.

The main reason for broad use of simple and adjusted exponential smoothing is that the forecast may be computerized quickly, requires very little memory space, and data can be updated easily. These methods are specifically useful to firms which have thousands of items in inventory. Since each forecast value contains all past forecast and demand data in the properly exponentially weighted manner, there is no requirement to maintain records of historical data (as in case of arithmetic moving averages). It is an effective and efficient method of forecasting with a built-in means of tracking the average while discounting the erratic random fluctuations.


Related Discussions:- Example of simple exponential smoothing

Tolerances, difference between geometric and amnufacturing tolerances

difference between geometric and amnufacturing tolerances

Stress plots, Problem:   The following machine component is loaded as s...

Problem:   The following machine component is loaded as shown.  It is fabricated from Al 6061-T6.   Determine the analytical solution to this problem and compare result

Potential deadlock, Suppose an interesting situation represented in followi...

Suppose an interesting situation represented in following figure (b). The Petri net somewhat shows a paradoxical situation. Intuitively we contain in our minds that by raising the

Preliminary stress analysis, Preliminary stress analysis work will start ea...

Preliminary stress analysis work will start early in the detail engineering phase after completion of equipment layout and piping study drawings. The piping required to be analyzed

Reinforced concrete design, You are tasked with the analysis and design of ...

You are tasked with the analysis and design of the gravity and wind framing system for a 6-story office building. A part plan of the building is attached.  The plan dimensions o

Chemestry cycle 1st yr, Explain construction and working of calomel electro...

Explain construction and working of calomel electrode

Show material selection process, Q. Show Material selection process? • ...

Q. Show Material selection process? • Design life shall be based on project design criteria and normally 10 to 15 years' service life specified for well pads, 20-25 years for C

Determine maximum fibre stress - beam, Determine Maximum fibre stress: ...

Determine Maximum fibre stress: A beam of rectangular section of 80 mm to 120 mm carries a uniformly distributed load of 40 kN/m over a span of 2 m an axial compressive force

Development of coated electrodes, DEVELOPMENT OF COATED ELECTRODES C...

DEVELOPMENT OF COATED ELECTRODES Can welding be done by bare wire? Why do we require coating at all? What are the different types of coating? What are the stages in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd