Example of simple exponential smoothing, Mechanical Engineering

Assignment Help:

Example of simple exponential smoothing:

A TV manufacturer utilizes simple exponential smoothing with α = 0.1 to forecast demand. For the first week of March, the forecast was 400 units while actual demand turned out to be 370 units.

1. Forecast the demand for the second week of March.

2. If the actual demand for the second week turned out to be 417 units, forecast the demand for the 3rd week. Continue forecasting for the subsequent four weeks. You can take actual demands for the subsequent weeks as 409, 388, 377, 445, and 410 units.

3. Develop an adjusted exponential forecast for this company. You may assume the initial trend adjustment factor Tt as zero and β = 0.1.

Solution

(a) Ft + 1 = Ft + α (Dt - Ft)

                     = 400 + 0.1 (370 - 400) = 397 units.

 (b)

707_Adjusted Exponential Smoothing.png

(c)        The trend adjustment is accomplished by total of a correction factor

[(( 1 -β )/ β ) Tt +1 )]   to the simple exponential forecast.

As the initial trend adjustment factor (given) Tt = 0, we have

March 1st Week

Tt + 1 = β (Ft + 1 - Ft) + (1 - β) Tt

= 0.1 (397 - 400) + (0.9) (0) = - 0.30

T(t +1) adj = Ft +1 +( 1 -β / β )T t +1

= 397 +( 0.9/0.1)  (- 0.30) = 394.30

The adjusted forecast for the second week of March = 394.30.

March 2nd Week

Tt + 1 = 0.1 (399 - 397) + (0.9) (- 0.30)

= 0.2 - 0.27 = - 0.07

F(t + 1) adj = 399 + 9 (- 0.07) = 398.37

The remaining values may be put in table form, as below.

606_Adjusted Exponential Smoothing1.png

The trend-adjusted forecast for the third week of April is Ft, adj   = 393.54 units whereas simple exponential forecast for the same week is 400 units.

The main reason for broad use of simple and adjusted exponential smoothing is that the forecast may be computerized quickly, requires very little memory space, and data can be updated easily. These methods are specifically useful to firms which have thousands of items in inventory. Since each forecast value contains all past forecast and demand data in the properly exponentially weighted manner, there is no requirement to maintain records of historical data (as in case of arithmetic moving averages). It is an effective and efficient method of forecasting with a built-in means of tracking the average while discounting the erratic random fluctuations.


Related Discussions:- Example of simple exponential smoothing

Prototype sand blast method, During the test run of prototype machine we fo...

During the test run of prototype machine we found out a few issue occurred due to blasting room design problem. The blasting room design is too quartet, this design had cause the b

Find out the effort required to run this machine, Find out the effort requi...

Find out the effort required to run this machine: The efficiency of a machine is 75% while an effort of 20 N is required to lift a load of 160 N. Compute the velocity ratio an

Find out the maximum and minimum bending stress in beam, Q.  A steel bar 10...

Q.  A steel bar 10 cm broad and 8 mm thick is subjected to bending moment. The radius of the neutral surface is 100 cm. Found out the maximum and minimum bending stress in beam.

Equipment for resistance welding-stored energy equipments, EQUIPMENT FOR RE...

EQUIPMENT FOR RESISTANCE WELDING-Stored energy equipments   Energy can be stored and further utilised for welding. One method of storing energy is in capacitors electrostat

Economic order quantity, Economic Order Quantity: Assume an economic o...

Economic Order Quantity: Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stockin

Piping material specifications, Q. Show Piping Material Specifications? ...

Q. Show Piping Material Specifications? Piping Material Specifications include the development and / or review of material specifications, and the review of data sheets, materi

Find speed of dynamo shaft, Find speed of dynamo shaft: Q: W ith the...

Find speed of dynamo shaft: Q: W ith the help of belt an engine running at 200rpm drives line shaft. The Diameter of the pulley on engine is 80cm and the diameter of the pul

Change in gravitational force, prove that the weight of a body at an elevat...

prove that the weight of a body at an elevation of h from sea level is expressd by the equation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd