Example of simple exponential smoothing, Mechanical Engineering

Assignment Help:

Example of simple exponential smoothing:

A TV manufacturer utilizes simple exponential smoothing with α = 0.1 to forecast demand. For the first week of March, the forecast was 400 units while actual demand turned out to be 370 units.

1. Forecast the demand for the second week of March.

2. If the actual demand for the second week turned out to be 417 units, forecast the demand for the 3rd week. Continue forecasting for the subsequent four weeks. You can take actual demands for the subsequent weeks as 409, 388, 377, 445, and 410 units.

3. Develop an adjusted exponential forecast for this company. You may assume the initial trend adjustment factor Tt as zero and β = 0.1.

Solution

(a) Ft + 1 = Ft + α (Dt - Ft)

                     = 400 + 0.1 (370 - 400) = 397 units.

 (b)

707_Adjusted Exponential Smoothing.png

(c)        The trend adjustment is accomplished by total of a correction factor

[(( 1 -β )/ β ) Tt +1 )]   to the simple exponential forecast.

As the initial trend adjustment factor (given) Tt = 0, we have

March 1st Week

Tt + 1 = β (Ft + 1 - Ft) + (1 - β) Tt

= 0.1 (397 - 400) + (0.9) (0) = - 0.30

T(t +1) adj = Ft +1 +( 1 -β / β )T t +1

= 397 +( 0.9/0.1)  (- 0.30) = 394.30

The adjusted forecast for the second week of March = 394.30.

March 2nd Week

Tt + 1 = 0.1 (399 - 397) + (0.9) (- 0.30)

= 0.2 - 0.27 = - 0.07

F(t + 1) adj = 399 + 9 (- 0.07) = 398.37

The remaining values may be put in table form, as below.

606_Adjusted Exponential Smoothing1.png

The trend-adjusted forecast for the third week of April is Ft, adj   = 393.54 units whereas simple exponential forecast for the same week is 400 units.

The main reason for broad use of simple and adjusted exponential smoothing is that the forecast may be computerized quickly, requires very little memory space, and data can be updated easily. These methods are specifically useful to firms which have thousands of items in inventory. Since each forecast value contains all past forecast and demand data in the properly exponentially weighted manner, there is no requirement to maintain records of historical data (as in case of arithmetic moving averages). It is an effective and efficient method of forecasting with a built-in means of tracking the average while discounting the erratic random fluctuations.


Related Discussions:- Example of simple exponential smoothing

Ventilation process of plant, Q. Ventilation process of plant? Due to t...

Q. Ventilation process of plant? Due to the possibility of accidental discharges of flammable gas and flashing liquid (e.g. leaks, incorrect valve opening, sampling, etc.); ade

Find out the maximum deflection in beam, Find out the maximum deflection in...

Find out the maximum deflection in beam: A beam of span 8m is loaded with UDL of 10 kN/m over the middle half portion. Discover the maximum deflection. EI is constant. Sol

3d design software, Which software is worth in learning for upcoming techno...

Which software is worth in learning for upcoming technologies in mechanical field?

Define 3-d lathe tool dynamometer, Define 3-D lathe Tool Dynamometer It...

Define 3-D lathe Tool Dynamometer It is possible to measure three dimensional cutting tool component with the help of 3-D lathe tool dynamometer. In spite of that we are gone f

Mechanism, how many links and joint does the automatic tool changer (ATC) m...

how many links and joint does the automatic tool changer (ATC) mechanism has?

Determine the location of the hydraulic jump, A rectangular channel of widt...

A rectangular channel of width 12ft has an upstream slope of 0.02ft/ft and a downstream slope of 0.0005 ft/ft. Both reaches have lengths of 500 ft. The upstream reach has a Manning

Calculate the minimum required cross-sectional area, A lifting shackle in a...

A lifting shackle in a glass-making factory is made from a special high-temperature stainless steel. It is expected that the shackle will experience a tensile load of 5kN and th

Differentiate between dynamometer and brakes, Can you Differentiate between...

Can you Differentiate between : Dynamometer and Brakes. Absorption Dynamometer and Transmission Dynamometer.

Calculate the length of developed blank, Calculate the Length of Developed ...

Calculate the Length of Developed Blank Part shown in Figure is to be produced from flat sheet by bending operation. Calculate the length of the developed blank. Assume k = 0.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd