Example of Production Rate
The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.
Solution
Given Number of machines n = 6
Number of shifts per week S = 10
Number of hours per shift H = 8
Production rate Rp = 17
Production capacity = n x S x H x Rp
∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk
Need someone to help in doing a connecting rod for an engine by using abaqus software version12 or 6.11?
A powered metal-working crank press (a generic press is shown at the end) has been designed to be capable of punching blanks from mild steel sheet up to 3 mm thick. 1. the ultim
Modulus of Rupture: What is the Modulus of Rupture? Sol.: The maximum fictitious shear stress which can be calculated by torsion formula by using the experimentally fou
cause effect remedies
Data given for gear problem T P = 30 TG = 80 φ = 20o m = 12 mm Addendum = 10 mm then determine the length of path of contact, length of Arc of contact and contact Ratio.
Q. Erosion-Corrosion In Sand Slurry Line? All sands are collected in the Inlet Slug Catcher and routed to the Desand Tank for separation. Sand Slurry lines are subject to erosi
Bore - Thermodynamics: The inner diameter of engine cylinder is called as bore. It can be measured by a vernier calliper or bore gauge. As engine cylinder wears out with the p
Equilibrium of body on the rough inclined plane: If the inclination is less than angle of friction, the body remains in equilibrium without any external force. If body is to b
Use of Auger extension for extended screed An improved extended auger arrangement and an improved asphalt paver with a tractor unit and a screed assembly including a main scree
Q. Safety from Corrosive Chemicals? Safety showers and eyewash stations shall be provided in areas where corrosive chemicals are stored and handled. They should be located so t
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd