Evaluate the length of guide bund, Civil Engineering

Assignment Help:

Q. Evaluate the Length of guide bund?

For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream length 0.25 to 0.40 times the bridge length. Length necessary for keeping worst possible embayment behind the guide bund sufficiently away from the approach bank is also required to be ascertained by fitting of sharpest loop as indicated in Figure 5.2 in Chapter 5. If field data of acute bends in river when cut offs occurred is not available, It may be assumed that radius of such a bend can be equal to 0.4 times the radius of average bends if maximum river discharge is up to 5660 m3/s and equal to 0.5 times the radius of average bends if the maximum discharge is more than 5660 m3/s. In case of braided rivers, the length determined on basis of both the considerations of axial flow through bridge and keeping away the worst loop may be found to be insufficient for protection of long approaches. Additional protection works like spurs, revetments etc. may then become necessary.

1833_Evaluate the Length of guide bund.png


Related Discussions:- Evaluate the length of guide bund

Concreting, #question why cracks develops on the surface of concrete on the...

#question why cracks develops on the surface of concrete on the next day of casting?

Reduced levelling, what is the theary of reduced levelling

what is the theary of reduced levelling

Land Surveying, What is the difference between accuracy and precision.

What is the difference between accuracy and precision.

Characteristic strength of concrete, In addition to its own weight, the bea...

In addition to its own weight, the beam in Figure is to carry a uniformly distributed live load of 12 kN/m. Figure 1 also shows the cross-sectional details of the beam. Design a

Standard mixes of concrete, In some nations such as Britain, specification ...

In some nations such as Britain, specification for concrete doesn'tusually require cube tests for standard mixes of concrete. Quality control of standard mixes in Britain is achiev

Purposes of subdivision of tunnelling faces, Purposes of subdivision of tun...

Purposes of subdivision of tunnelling faces in Sprayed Concrete Linings (SCL) method In using sprayed concrete lining methods for lining a large tunnel in soft ground, tunnelli

Explain the operating point - pumping system, Explain the Operating Point -...

Explain the Operating Point - Pumping System Intersection of the characteristic curve and the system curve. This is the head and flow rate data for the pump "operation". The op

Explain the unconfined compression strength of the clay, A square group of ...

A square group of 9 piles was driven into soft clay extending to a large depth. The diameter and length of the piles were 30 cm and 9 m respectively. If the unconfined compression

Machanics, differentiate between moment & couple

differentiate between moment & couple

Determine the water content of the sand sample, In order to determine the w...

In order to determine the water content of a wet sand, a sample weighing 4 N was put in a pyknometer. Water  was then poured to fill it and the weight of the pyknometer and its con

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd