Estimate total dissolved solids, alkalinity and hardness, Civil Engineering

Assignment Help:

Estimate total dissolved solids, Alkalinity and Hardness

A sample of water from Brazos River at Brenham was collected and analyzed for water quality characteristics and the data is presented in the table below (regular font).  Estimate (i) total dissolved solids. (ii) Alkalinity (iii) hardness (TH, CH and NCH)

  (Data is shown in Columns 1 and 2 other columns are part of solution)

1836_Estimate total dissolved solids, Alkalinity and Hardness.png

(i) Note that the sum of cations and anions should be roughly equal (in eq/m3) for a satisfactory analysis.

Total dissolved solids (TDS) = sum of all the ions in column 2 = 685.52 g/m3

(ii) Alkalinity is caused by the presence of mainly CO3-2 and HCO3 - ions (For all practical purposes the contribution of hydroxyl (OH-) and Hydrogen (H+) ions to alkalinity is negligible for natural waters)

Alkalinity (eq/m3) = CO32- + HCO3- = 4.79 + 0.2 = 4.99 eq/m3

(also remember that 1 eq/m3 = 50 mg/l as CaCO3)

(iii) Total Hardness, TH (add all the cations with a charge of 2 or more)

TH = Ca+2 + Mg+2 =

3.9 + 2.62 = 6.52 eq/m3 (or 326 mg/l as CaCO3)

Carbonate Hardness (CH) = bicarbonate + carbonate (However, CH cannot be more than TH)

= 4.79 +0.2 = 4.99 eq/m3 (250 mg/l as CaCO3)

Non-Carbonate Hardness (NCH) = TH - CH = 6.52-4.99 = 1.53 eq/3 (To obtain values in mg/L as CaCO3 multiply eq/m3 with 50 or use the column with mg/L as CaCO3).


Related Discussions:- Estimate total dissolved solids, alkalinity and hardness

Calculate the initial height of the stockpile, On a 5-acre level terrain bu...

On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft sub-g

Major considerations in selecting marine plants, Question What are majo...

Question What are major considerations in selecting marine plants and land plants for fitting of band drains? Answer For fitting of band drains by marine plants,

Designing of watermain, Question In designing of watermain , regular p...

Question In designing of watermain , regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than 600mm. Give some speci

Epoxy-coated bars vs galvanized bars, Bonding performance to concrete: Epox...

Bonding performance to concrete: Epoxy-coated bars vs. galvanized bars  Based on the findings of CEB Bulletin 211 the bonding of galvanized bars to concrete is lower in early

Design of the aeration basin based on solids retention time, Design of the ...

Design of the Aeration Basin Based on Solids Retention Time - sewer construction: You are provided the following information about a municipal wastewater treatment plant. That

Brickwork, write buckling and dislodging of brick slip?

write buckling and dislodging of brick slip?

Engineering economics, Ask quA contractor has both a 3-cy and a 5-cy shovel...

Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 worki

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd