Estimate the probability - noncritical path , Mathematics

Assignment Help:

An advertising project manager developed the network diagram shown below for a new advertising campagign.  In addition, the manager gathered the time information for each activity, as shown in the below table. 

Estimate the probability that the noncritical path B-F-G will take more than 20 weeks.  Hint:  Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.

Activity                Optimistic           Most likely         Pessimistic         Immediate Predecessor(s)

A                               1                              4                              7                              -

B                                2                              6                              7                              -

C                                3                              3                              6                              B

D                                6                             13                           14                           A

E                               3                              6                              12                           A,C

F                               6                              8                              16                          B

G                               1                              5                              6                           E,F


Related Discussions:- Estimate the probability - noncritical path

Use newtons method to find out an approximation, Use Newton's Method to fin...

Use Newton's Method to find out an approximation to the solution to cos x = x which lies in the interval [0,2].  Determine the approximation to six decimal places. Solution

Explain adding and subtracting in scientific notation, Explain Adding and S...

Explain Adding and Subtracting in Scientific Notation? To add or subtract numbers in scientific notation, the numbers must be expressed so that they have the same exponent.

Write down the first few terms of the sequences, Write down the first few t...

Write down the first few terms of each of the subsequent sequences. 1. {n+1 / n 2 } ∞ n=1 2. {(-1)n+1 / 2n} ∞ n=0 3. {bn} ∞ n=1, where bn = nth digit of ? So

what are the coordinates of the vertex , Use the graph of y = x2 - 6x  to ...

Use the graph of y = x2 - 6x  to answer the following: a)         Without solving the equation (or factoring), determine the solutions to the equation  x 2 - 6x = 0  usi

Finding the equation of a line, Finding the Equation of a line, Given a Slo...

Finding the Equation of a line, Given a Slope and a Point ? Find the equation of a line with slope m = 2, which passes through the point (-1, -3). Solution: Use the po

ConnectEd, How do I increase and decrease tax and sales

How do I increase and decrease tax and sales

Progressions, * 2^(1/2)*4^(1/8)*8^(1/16)*16^(1/32) =

* 2^(1/2)*4^(1/8)*8^(1/16)*16^(1/32) =

Small samples-estimation of population mean , Estimation of population mean...

Estimation of population mean If the sample size is small (n In this case Population mean µ = x¯ ±  tS x¯  x¯ = Sample mean S x¯ =  s/√n S = standard deviation

4 accounting majors, 4 accounting majors, 2 economics majors and 3 marketin...

4 accounting majors, 2 economics majors and 3 marketing majors have an interview for5 different positions with a large company. Find the number of dfferent ways that 5 of these c

Volume of grains in the silo , The volume of grains in a silo at a particul...

The volume of grains in a silo at a particular time (measured in hours) is given by V (t) = 4t(3-t) m 3 . Find the rate of change of the volume of grains in the silo from first pri

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd