An advertising project manager developed the network diagram shown below for a new advertising campagign. In addition, the manager gathered the time information for each activity, as shown in the below table.
Estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.
Activity Optimistic Most likely Pessimistic Immediate Predecessor(s)
A 1 4 7 -
B 2 6 7 -
C 3 3 6 B
D 6 13 14 A
E 3 6 12 A,C
F 6 8 16 B
G 1 5 6 E,F
Suppose a regular polygon , which is an N-sided with equal side lengths S and similar angles at each corner. There is an inscribed circle to the polygon that has center C and ba
Derivatives of Trig Functions In this section we will see derivatives of functions other than polynomials or roots of polynomials. We'll begin this process off through taking
EXPLAIN HOW MARKOV PROCESS IS APPLIED IN BRAND SWITCHING?
7=1/w-4(1/11
Verify Liouville''''s formula for y "-y" - y'''' + y = 0 in (0, 1) ?
#question.
I want have material of the above topic
4 8/16+1/
explain the formular for finding trigonometry
geometry fbw = 128 saf= 104 what is rfd
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd