An advertising project manager developed the network diagram shown below for a new advertising campagign. In addition, the manager gathered the time information for each activity, as shown in the below table.
Estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.
Activity Optimistic Most likely Pessimistic Immediate Predecessor(s)
A 1 4 7 -
B 2 6 7 -
C 3 3 6 B
D 6 13 14 A
E 3 6 12 A,C
F 6 8 16 B
G 1 5 6 E,F
what is break even point and how can it helps managers to make decisions?
Two circles C(O, r) and C 1 (O 1 , r 1 ) touch each other at P, externally or internally. Construction: join OP and O 1 P . Proof : we know that if two circles touch each
how do you solve quadratic equations by factoring?
Find the greatest number of 6 digits exactly divisible by 24, 15 and 36. (Ans:999720) Ans: LCM of 24, 15, 36 LCM = 3 × 2 × 2 × 2 × 3 × 5 = 360 Now, the greatest six digit
4x+3y+7=0 and 3x+4y+8=0 find the regression coefficient between bxy and byx.
3^2=8
give some examples of fractions that are already reduce
difference between PERT and CPM
-8 plus (-17)
how do u add them together?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd