Estimate the probability - noncritical path , Mathematics

Assignment Help:

An advertising project manager developed the network diagram shown below for a new advertising campagign.  In addition, the manager gathered the time information for each activity, as shown in the below table. 

Estimate the probability that the noncritical path B-F-G will take more than 20 weeks.  Hint:  Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.

Activity                Optimistic           Most likely         Pessimistic         Immediate Predecessor(s)

A                               1                              4                              7                              -

B                                2                              6                              7                              -

C                                3                              3                              6                              B

D                                6                             13                           14                           A

E                               3                              6                              12                           A,C

F                               6                              8                              16                          B

G                               1                              5                              6                           E,F


Related Discussions:- Estimate the probability - noncritical path

Shoppers'' stop, How should shoppers''stop develop its demand forecasts?

How should shoppers''stop develop its demand forecasts?

?, x/15=50/20

x/15=50/20

Terminology of polynomial, Terminology of polynomial Next we need to ge...

Terminology of polynomial Next we need to get some terminology out of the way. Monomial polynomial A monomial is a polynomial which consists of exactly one term.

Linear programming , A paper mill produces two grades of paper viz., X and ...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Find the discount factors -linear interpolation, Find the discount factors ...

Find the discount factors -Linear interpolation: All rates should be calculated to 3 decimal places in % (e.g. 1.234%), the discount factors to 5 decimal places (e.g. 0.98765

Statistics, marks frequency 0-9 8 10-19 10 20-29 ...

marks frequency 0-9 8 10-19 10 20-29 14 30-39 28 40-49 46 50-59 25 60-69 17 70-79 9 80-89 2 90-99 1 (

Word problems, The sum of two numbers is 19, their difference is 5. find th...

The sum of two numbers is 19, their difference is 5. find the numbers

Prove that prims algorithm produces a minimum spanning tree, Prove that Pri...

Prove that Prim's algorithm produces a minimum spanning tree of a connected weighted graph. Ans: Suppose G be a connected, weighted graph. At each iteration of Prim's algorithm

Construct a tangent to a circle of radius, 1.  Draw a pair of tangents to a...

1.  Draw a pair of tangents to a circle of radius 2cm that are inclined to each other at an angle of 900. 2.  Construct a tangent to a circle of radius 2cm from a point on the c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd