Estimate the probability - noncritical path , Mathematics

Assignment Help:

An advertising project manager developed the network diagram shown below for a new advertising campagign.  In addition, the manager gathered the time information for each activity, as shown in the below table. 

Estimate the probability that the noncritical path B-F-G will take more than 20 weeks.  Hint:  Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.

Activity                Optimistic           Most likely         Pessimistic         Immediate Predecessor(s)

A                               1                              4                              7                              -

B                                2                              6                              7                              -

C                                3                              3                              6                              B

D                                6                             13                           14                           A

E                               3                              6                              12                           A,C

F                               6                              8                              16                          B

G                               1                              5                              6                           E,F


Related Discussions:- Estimate the probability - noncritical path

The new area is 168 square inches how many inches increase, A 4-inch by 6-i...

A 4-inch by 6-inch photograph is going to be enlarged through increasing each side by the similar amount. The new area is 168 square inches. How many inches is each dimension incre

How many cubic yards of concrete are required, A concrete retaining wall is...

A concrete retaining wall is 120 feet long with ends shaped as given. How many cubic yards of concrete are required to construct the wall? a. 217.8 yd 3 b. 5,880 yd 3

Earning money, Terry earns $680 per week. He is entitled to 4 weeks annual ...

Terry earns $680 per week. He is entitled to 4 weeks annual leave and receives an additional holiday loading of 17.5%. Calculate his total pay for this holiday period.

Find the length of the rectangle, Suppose that the width of a rectangle is ...

Suppose that the width of a rectangle is three feet shorter than length and that the perimeter of the rectangle is 84 feet. a)    Set up an equation for the perimeter involving

Discret math, i have a question about discret math

i have a question about discret math

Binomial theorem, use the expansion of (1-x)^7 to find the value of 1.998^7...

use the expansion of (1-x)^7 to find the value of 1.998^7 correct to five significant figures

Inventory record, a) Complete the inventory record below for an FOQ of 100 ...

a) Complete the inventory record below for an FOQ of 100 units. b) Talk about weaknesses of MRP. List at least 3 and describe each in a sentence or two. Item: A

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd