Estimate Bridge Pier Concrete, Civil Engineering

Assignment Help:
Takeoff the 3 elements for the following bridge pier components:
1. Pier Footing,
2. Pier Column,
3. Pier Cap (Top).
• Misc Items to include Shear Key.
• Misc Items to exclude Rebar.
• Include the following Finishes:
1. Bearing Pad Surfaces (the complete top surface, not just the pads);
2. Concrete Sealing of ALL Exposed surfaces including 600mm below grade.
• Show all work on quantity take off sheets using proper order and numbering system

Related Discussions:- Estimate Bridge Pier Concrete

Hydrometer analysis - soil mechanics and foundations, Hydrometer Analysis -...

Hydrometer Analysis - soil mechanics and foundations Hydrometer Analysis used to obtain the grain size distribution of fine-grained soils (finer sands, silts and clays) smalle

Define facilities that discharge wastewater to a potw, Facilities that disc...

Facilities that discharge wastewater to a publicly owned treatment works? Facilities that discharge wastewater to a POTW (publicly owned treatment works) are known as subject t

#title beam design, how to calculate loads acting on a simple supported bea...

how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#

Soil plug in marine piling system of steel tubular pile, Soil plug in marin...

Soil plug in marine piling system of steel tubular pile with reinforced concrete infill At the time of initial driving process, open-ended steel piles are driven through the s

Design nominal reinforcement to piles, Question Is it true that there i...

Question Is it true that there is no essential to design nominal reinforcement to piles. Answer In BS8110 and BS5400 Pt.4, they need provision of nominal reinforce

Minimum and maximum area of reinforcement, Q. Minimum and maximum area of r...

Q. Minimum and maximum area of reinforcement? Minimum area of reinforcement vs. maximum area of reinforcement Beams can be designed to be larger than required for strength

What is imp rest stores, Q. What is Imp rest Stores? Material obtained ...

Q. What is Imp rest Stores? Material obtained not for specific works but as a standing advance for the purpose of material urgent requirements as and when they arise should wit

Determine the bar sizes and spacing, Referring to problem 1, in order to me...

Referring to problem 1, in order to meet a 1-hour fire code rating the slab thickness must be at least 4.00. Based on the information given in problem 1 and with a slab thickness o

Maintenance of bituminous roads, Maintenance of Bituminous Roads: The...

Maintenance of Bituminous Roads: The common defects noticed in a bituminous road are : potholes cracks rutting corrugations shoving stripping and l

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd