An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Maintenance of gravel roads, Maintenance of Gravel Roads: The mainten...

Maintenance of Gravel Roads: The maintenance consists of : filling up of potholes/depressions with fresh gravel and compacting after light sprinkling with water. g

Avoidance of designing acute angle of concrete pavement, Q. Avoidance of de...

Q. Avoidance of designing acute angle of concrete pavement The stress persuaded in acute angle corners of concrete pavement is far much higher than right-angle corners of the

Compaction, describe how quality control is maintained in a rolled fill dam...

describe how quality control is maintained in a rolled fill dam

Explain rebound hammer - underwater non-destructive testing, Explain Reboun...

Explain Rebound Hammer - Underwater non-destructive testing? The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condit

Storm water, what are the roles of civil engineers in storm water managemen...

what are the roles of civil engineers in storm water management

Simply supported steel frame help, I need some help sizing a rectangular pl...

I need some help sizing a rectangular plate that will distribute my load to the simply supported beams below.

Describe principles of river protection works, Q. Describe Principles of ri...

Q. Describe Principles of river protection works? Determination of design discharge for a bridge is sometimes required to be based on flood marks left during unprecedented abno

Key functions of changed components of paint, Question What are key fun...

Question What are key functions of changed components of paint? Answer For regular paint application, there are largely three key components of paint, namely primer, u

Scheme of some smaller piles with same load capacity, Question Which wi...

Question Which will be a better choice, a large diameter piles or a scheme of some smaller piles with same load capacity ? Answer Choice of a large diameter pile suff

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd