Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Determine the meaning of relaxation of steel, Determine the meaning of Rela...

Determine the meaning of Relaxation of Steel If the strain in steel is kept constant, it is seen that stresses in it reduce with time. It is called as relaxation of steel. Ten

What is the main reason being for the phenomenon, Sometimes side of concret...

Sometimes side of concrete bridges is observed to turn black in colour . What is the main reason being for the phenomenon ?

Determine the allowable bearing pressure of the sand, Two load tests were c...

Two load tests were conducted at a site-one with a 0.5 m square test plate and the other with a 1.0 m square test plate. For a settlement of 25 mm, the loads were found to be 60 kN

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Fluid Mechanics, I am taking a fluid mechanics class that is related to was...

I am taking a fluid mechanics class that is related to wastewater treatment. I need help with my homework

Good surface regularity for sub-base in concrete pavement, Q. Good surface ...

Q. Good surface regularity for sub-base in concrete pavement? Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reas

Grouting in segmental linings in tunnels, Q. Grouting in segmental linings ...

Q. Grouting in segmental linings in tunnels? Grouting is typically carried out under pressure in segmental linings at the time of tunnel construction due to the below reasons:

Define ways of providing the anti slip device - by stops, Define Ways of pr...

Define Ways of providing the anti slip device - By stops? In this method stopper plates or angles are welded to the underside of the girder and embedded in the bed block. It sh

Hydraulics, A tank with vertical sides contain 3m of water in the bottom, o...

A tank with vertical sides contain 3m of water in the bottom, overlain by 4m of oil with no intermixing. Draw pressure diagram due to the oil and water on one of the tank sides and

What do you understand by percolation of water, Q. What do you understand b...

Q. What do you understand by Percolation of water? Percolation of water into the ground or embankment takes place, causing rise in water table and / or saturation of the body.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd