Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Building technology 1, what are the defects in timber due to natural forces...

what are the defects in timber due to natural forces?

Explain the components of a rebound hammer, Explain the Components of a reb...

Explain the Components of a rebound Hammer? Several components of a rebound hammer are displayed in below Figure. 1. Concrete surface; 2. Impact spring; 3. Rider on gui

Bending stress distribution diagram, i want to know how bending stress dist...

i want to know how bending stress distribution in c section

Dam, types of dam

types of dam

Landslides induced by rainfall, Landslides induced by rainfall After r...

Landslides induced by rainfall After rainfall, groundwater pressure is built up and this elevates ground water table. Water inside the pores of soil reducesthe effective stres

Motion in one dimension, An F-16 lands on aircraft carrier and its velocity...

An F-16 lands on aircraft carrier and its velocity is 63 m/sn. If its decceleration is assumed to be constant and it must stop in 2.0 sec. a) What is final position of plane if i

Measurement of surface runoff and infiltration, Surface runoff travelling o...

Surface runoff travelling over ground surface to reach receiving water involves the following events: i) Rainfall intensity exceeds soil's infiltration rate; ii) Excess water

Designing of access ramps for drainage channels, Question Designing of ...

Question Designing of access ramps for drainage channels, why must direction of access ramps is sloping down on the way to downstream ? Answer In designing of access

Of obstacles to both chaining and ranging.., #questof obstacles to both cha...

#questof obstacles to both chaining and ranging. ion..

Explain about the hydrogen embrittlement, Explain about the Hydrogen Embrit...

Explain about the Hydrogen Embrittlement As a result of the action of acids on high-tensile steels, liberation of hydrogen takes place. It penetrates into the steel surface an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd