An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Cost estimating, I would like to know if anyone can help me with my const e...

I would like to know if anyone can help me with my const estimating project

Structure, what is the cutelment length

what is the cutelment length

Yield, Describe the process of yielding and state the effect work hardening...

Describe the process of yielding and state the effect work hardening has on the yield point of mild steel

Estimating, a 45 cm deep roof beam is provided on 30 cm wall of a room size...

a 45 cm deep roof beam is provided on 30 cm wall of a room size 3.0m*5.0m . calculate the quantity of steel required in beam on percentage basis.

Explain brake and electrical horsepower, Explain Brake and Electrical Horse...

Explain Brake and Electrical Horsepower Brake horsepower (bhp) = whp/pump efficiency Electrical or motor horsepower (ehp) or (mhp) = bhp/motor efficiency Friction of heat

Friction dampers, what is friction damper and there types?

what is friction damper and there types?

Designing of roadbase material, Question In General Specification for C...

Question In General Specification for Civil Engineering Works, designing of roadbase material is based on recipe approach. Give reason. Answer Designing of roadbase

Estimation specification and costing, Estimate the single room of size 3m x...

Estimate the single room of size 3m x 4m x height 3m using individual wall method?

Water absorption test for precast concrete pipes, Purpose of carrying out w...

Purpose of carrying out water absorption test for precast concrete pipes Cement will mix with more water than is essential to ultimately combine during hydration of cement pas

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd