An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Calculate the equivalent uniform annual cost, A contractor purchased an exc...

A contractor purchased an excavator for $100,000. The life expectancy is 10-years. With the annual interest rate at 7%, the annual cost for the excavator is most nearly: Solutio

Water control for sheet pile walls, Q. Water control for sheet pile walls? ...

Q. Water control for sheet pile walls? Ground water flow into excavations constructed by sheet pile walls must be minimized in order to save the cost of the provision of pumpin

Explain cercla and sara - hazardous waste regulations, Explain CERCLA and S...

Explain CERCLA and SARA - Hazardous Waste Regulations In 1980, the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) was enacted to address tho

Precaution of damp, i need simple ans for this question tell me precaution ...

i need simple ans for this question tell me precaution of dampness

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd