Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Vertical curves - geometric design of roads, Vertical Curves: When tw...

Vertical Curves: When two vertical gradients meet, it is necessary to provide a vertical curve. Two types of vertical curves are used: (a) Summit curve, where the point of

Foundation, what are factors that affect bearing capacity of a shallow foot...

what are factors that affect bearing capacity of a shallow footing

Segmentally lined and sprayed concrete linings tunnels, Q. Segmentally line...

Q. Segmentally lined and Sprayed Concrete Linings tunnels? The fundamental difference between segmentally lined tunnels and SCL tunnels is that the sprayed concrete in SCL tunn

Concepts and definitions of thermodynamics, System A system (often cal...

System A system (often called a closed system) is any collectionof matter within a prescribed boundary, but no matter may enter or leave the system.  Note 1. That the bo

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

Wet mix macadam - road pavements, Wet Mix Macadam: For heavily traffi...

Wet Mix Macadam: For heavily trafficked highways, the granular bases are constructed using Wet Mix Macadam (WMM). The WMM is a specification in which well graded aggregate is

Afflux on account of obstruction to flow, Q. Afflux on account of obstructi...

Q. Afflux on account of obstruction to flow? Even if the river constriction on account of approach banks is not excessive and bridge waterway is wider than that causing critica

Geo Technical Project, I have a geo technical Project that I need to be sol...

I have a geo technical Project that I need to be solved correctly and accurately within 15 hours exact, please. Steps and details must be included. Thanks a lot and let me know ASA

Surveying, working from whole to part

working from whole to part

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd