An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Calculate the deposited amount - construction management, An engineer depos...

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-mo

Calculate the amount put into saving account, Calculate the Amount put into...

Calculate the Amount put into Saving Account If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is m

Concrete surround for drainage pipes, Concrete surround is generally adopte...

Concrete surround is generally adopted for rigid drainage pipes to resist high traffic loads (for instance under shallow covers) and to allow for using pipes with lower strength. F

Cement, manufacture of cement by dry process

manufacture of cement by dry process

Structures, What is the economic span of a bridge

What is the economic span of a bridge

Cantilever support reactions, A cantilever has two couples: 1st(clockwise, ...

A cantilever has two couples: 1st(clockwise, 15kNm) placed at (1/3)L from support and 2nd (anti-clockwise, 10kNm) at (2/3)L from the support. What should be the reaction at the sup

Offset survey, what is offset survey and how it is done

what is offset survey and how it is done

BUILDING CONSTRUCTION, GIVE IN DETAIL THE TREATMENT OF TOP SURFACE OF EARTH...

GIVE IN DETAIL THE TREATMENT OF TOP SURFACE OF EARTH FILLING..

Hydrometer analysis - soil mechanics and foundations, Hydrometer Analysis -...

Hydrometer Analysis - soil mechanics and foundations Hydrometer Analysis used to obtain the grain size distribution of fine-grained soils (finer sands, silts and clays) smalle

Slope protection, what is the type of slope protection that use rocks and p...

what is the type of slope protection that use rocks and put cements between those rocks??the concept is same as brick layer

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd