Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Roof truss, The angle between the members at the joint is 30°. Design the ...

The angle between the members at the joint is 30°. Design the members at the joint. Design also the connection of the members at the joint. The length of the principal rafter betw

Determine the equivalent of free float, The free float is equal to: a. L...

The free float is equal to: a. Latest allowable event occurrence time + Early finish time b. Earliest event occurrence time + early finish time c. Latest allowable event o

State the method of pre- tensioning, State the method of Pre- Tensioning ...

State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr

Calculates the energy required, Write a program called, A1Q1, that reads a ...

Write a program called, A1Q1, that reads a single letter.   It will then display the corresponding ASCII code of the letter and prints the next character and the character which is

Necessity of air voids in bituminous pavement, Q. Necessity of air voids in...

Q. Necessity of air voids in bituminous pavement? If the presence of air voids is too high, it results in an increase of permeability of bituminous pavement. This enables the f

What is switch and expansion joint, Q. What is Switch and Expansion Joint? ...

Q. What is Switch and Expansion Joint? Switch Expansion, Joint (SEJ) is an expansion joint installed at each end of LWR/CWR to permit expansion/contraction of the adjoining bre

Erosion ocntrol, java program to design a SD-3 sediment pond per Georgia er...

java program to design a SD-3 sediment pond per Georgia erosion control manual

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd