An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

Measure the ultimate settlement due to pumping, A clay stratum of 18 metres...

A clay stratum of 18 metres thickness was found above a sand stratum when a boring was made. The clay was consolidated under the present overburden pressure. The hydrostatic pressu

Engineer''s role on Transportation Problems In the Society, #question.Techn...

#question.Techniques of Operations Research - Transportation Problem, Transportation Models Transportation Problems Transportation plays an important role in our econ

Street originate in the plumbing term street ell, How did street originate ...

How did street originate in the plumbing term street ell? Ans) A "street ell" may have gotten its name due to it describes a 90° fitting particularly useful in tight, street dit

State highways, State Highways: These are trunk or arterial roads of a...

State Highways: These are trunk or arterial roads of a state connecting the National Highways of adjacent states and linking the district headquarters and important cities wit

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Operation researcg, Discuss Scope and necessity of O.R in industry ?

Discuss Scope and necessity of O.R in industry ?

#title., desirable properties in green concrete

desirable properties in green concrete

Measure the cohesion of internal friction of the soil, A cylindrical specim...

A cylindrical specimen of a saturated soil fails under an axial stress 150 kN/m 2 in an unconfined compression test. The failure plane makes an angle of 52° with the horizontal.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd