Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Effect of pile installation method, Effect of pile installation method to l...

Effect of pile installation method to load carrying capacity of piles The construction of piles by driving method causes an increase in density of surrounding soils. Therefore

Arches and lintels, classification of arches based on their shape are?

classification of arches based on their shape are?

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

The material that have lowest resistivity is , The material that have lowes...

The material that have lowest resistivity is Answer: Silver is the material

Reliability of settlement computations, Inspite of the problems of sample d...

Inspite of the problems of sample disturbance, if 1) e or E vs log p curve is interpreted, reasonably with some corrections for sample disturbance, 2) if the sample disturbance

Cumulative error, diffrence between cumilative compensative error

diffrence between cumilative compensative error

Explain the design discharge for bridge waterway, Q. Explain the Design dis...

Q. Explain the Design discharge for bridge waterway? Design discharge for bridge waterway should be a flood of 50 year frequency. For very large bridges damage to which is like

Prime coat - road pavements, Prime Coat: A prime coat is the applicat...

Prime Coat: A prime coat is the application of a low viscosity binder, usually a bituminous emulsion, to a gravel, WBM or WMM surface, to enable the binder to fill up the voi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd