Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Calculate the amount of cubic yards of soil, A proposed building site requi...

A proposed building site requires 135,000-ft 3 of imported fill.  A borrow site is located 5-miles Northeast of the project site where the soil has a shrinkage of 16%.  The amount

Show the functions of sleepers in railway, Q. Show the Functions of sleeper...

Q. Show the Functions of sleepers in railway? Functions of sleepers in railway works are as below:  (i)  The primary function of a sleeper is to grip the rail to gauge and t

Construction health & safety, List different access equipment & their uses ...

List different access equipment & their uses wih pictures

Explain flocculation, Explain Flocculation Most important factor ef...

Explain Flocculation Most important factor effecting particle removal efficiency objective - to bring particles into contact so that they will collide, stick together

Finite Element Analysis- MATLAB problem, I am currently enrolled in a gradu...

I am currently enrolled in a graduate Civil Engineering course in Finite Element Analysis. The final assignment and project both deal with coding in MATLAB and I am having great di

Quality control in flexible pavements, Quality Control in Flexible Pavement...

Quality Control in Flexible Pavements: The quality control needed for Flexible Pavements covers the following tests : (a) Density and Moisture content of sub-grade. (b)

Calculate the fuel consumed, A 160-HP Diesel engine (peak fuel consumption ...

A 160-HP Diesel engine (peak fuel consumption = 0.04-gal/HP-hr) hydraulic excavator operates on a cycle time of 20 seconds during a 50-min/hr.  During the filling of the bucket cyc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd