An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Insurance required to be incorporated in deal, Question Is procurement ...

Question Is procurement of third party insurance required to be incorporated in deal for construction works? Answer Purpose of third party insurance is to guard contra

List the significant engineering classification system, How do you distingu...

How do you distinguish among clay and silt in the field? State the purpose of identification and categorization of soils. List any three significant engineering classification syst

What is the withdrawal force of steel nails, In engineering, the code-allow...

In engineering, the code-allowable withdrawal force is zero, due to the wood expands and contracts over time and the nail pullout force can decrease to zero

Site plan, can I have some help with a site plan. I want it on autocad, I h...

can I have some help with a site plan. I want it on autocad, I have all the dimmension

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

Softening point of bitumen, Hi, i need discussion for softening point of bi...

Hi, i need discussion for softening point of bitumen 7.5 ?C

Depth of boring for multi-storeyed building, Depth of Boring  for Multi-st...

Depth of Boring  for Multi-storeyed Building Peck has recommended that first drill hole is to be made up to depth at which the presence of a thick layer of soft clay with a hig

Bridge, Explain economical span if bridges

Explain economical span if bridges

Dam, how many types of drainage galleries and foundation treatment

how many types of drainage galleries and foundation treatment

Theory of elasticity and plasticity, derivation for strain energy stored in...

derivation for strain energy stored in a body due to torsion

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd