Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Surveying, how to defined work from whole to the part

how to defined work from whole to the part

Determine about the long-term deflections, Determine about the long-term de...

Determine about the long-term deflections For long-term deflections, the total long-term deflection due to the prestressing force, dead load and any sustained imposed load may

Explain the createthread function used in the windows nt, Explain the Creat...

Explain the CreateThread Function used in the Windows NT CreateThread(security, size, MyThreadFunction, arg, flag,&tID ) The CreateThread function call is used to start an i

Inspection of girder bridge, Q. As an AEN in charge, what inspection will...

Q. As an AEN in charge, what inspection will you under taken at the time of inspection of Girder Bridge 3 x 60 feet. Please explain the important items to be o

What is stress corrosion, What is Stress Corrosion Stress corrosion ta...

What is Stress Corrosion Stress corrosion takes place in prestressed concrete tendons due to the combined actions of corrosion and static tensile stresses. This type of attack

Timber, charring of timber

charring of timber

#overhanging beams, How to calculate point of contraflexion on an overhangi...

How to calculate point of contraflexion on an overhanging beam with udl

Flow, what is maximum flood level

what is maximum flood level

What is activated sludge process, Q. What is Activated Sludge process? ...

Q. What is Activated Sludge process? The term Activated Sludge is used to indicate the sludge which is obtained by settling sewage in presence of abundant oxygen. The Activated

REQUIREMENT OF GOOD BUILDING STONE, HOW TO MAKE A GOOD BUILDING .? TELL ABO...

HOW TO MAKE A GOOD BUILDING .? TELL ABOUT SOME TIPS OF REQUIREMENT OF GOOD BUILDING STONE? AND SAY ABOUT CEMENT?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd