Environmental Question, Civil Engineering

Assignment Help:
An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Explain gauge conversion, Q. Explain Gauge Conversion? All the advanced...

Q. Explain Gauge Conversion? All the advanced countries of the world have recognized the need for uniformity of gauge. There are a number of problems that have cropped up on th

Return period for design situations, Question While design life will it...

Question While design life will it be same as return period for design situations ? Answer Design life means least duration a structure is accepted to last. Longe

Parallel pipe systems or multipath pipeline problems, Parallel Pipe Systems...

Parallel Pipe Systems or Multipath Pipeline Problems Two or more sections of piping (branches) of different diameters, lengths and/or pipe materials originating and terminating

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Execution compression test for concrete, Question In execution compression...

Question In execution compression test for concrete , have to test cubes .Test cylinders be approved? Answer Essentially, results of compression test carried out by using cu

Main concern regarding design of pavements, Question If In case a road ...

Question If In case a road passes from side to side a reclaimed land and an existing land, what is key main concern regarding design of pavements? Answer For a breathin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd