An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr

Related Discussions:- Environmental Question

Define factor that is not concerned with schedule control, Schedule control...

Schedule control is concerned with all of the following except: a. Influencing the factors which create schedule changes b. Determining that the schedule has changed c.

Strength of materials, distribution of shear stress in triangular section

distribution of shear stress in triangular section

Project management, planking and strutting for shallow excavation

planking and strutting for shallow excavation

Mechanical, Define varigions principle of moments and write about system of...

Define varigions principle of moments and write about system of forces?

Determine the hydraulic radius for rectangular open channel, Determine the ...

Determine the hydraulic radius R for a rectangular open channel with dimensions of 6 ft wide and 4 ft high (side walls) flowing at a depth of 3 ft. Solution: R = A/P Cross-s

Maintenance of drainage and shoulders, Maintenance of Drainage: Maint...

Maintenance of Drainage: Maintenance of drainage will ensure that the run-off is taken away from the runway efficiently. The side ditches and buried pipes should be cleaned r

Internal force of preloaded fasteners, Q. Internal force of preloaded faste...

Q. Internal force of preloaded fasteners? Force in a bolt in a bolted joint relies on the preloading force applied to it at the time of the tightening operation. For example, w

Soil in road construction, Soil in Road Construction: Road Embankme...

Soil in Road Construction: Road Embankment and Sub-grade Soil is mainly used as the material for constructing a road embankment. The road embankment supports the road

Determine condition of activity in the network flow diagram, Determine the ...

Determine the condition of each activity in the network flow diagram shown below   Ans: a. Activity C can be started only after the completion of activities A and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd