Solve the following problems and show all steps and calculations clearly:

1. A water treatment plant uses a dual media filter. The two media used are:
a) Anthracite coal with effective diameter of 1.1 mm, porosity of 0.6, and shape factor of 0.5.
b) Sand with effective diameter of 0.5 mm, porosity of 0.45, and shape factor of 0.7.

The entire filter depth is 0.8 m with 0.5 and 0.3 meters of anthracite coal and sand respectively. Calculate the total head loss in the clean filter if the loading rate is 200 m3/m2.day and the operational temperature is 100C.

2. A conventional surface water plant with coagulation, flocculation, sedimentation, and filtration produces a filtered water with a turbidity less than 0.3 NTU, pH 7 and temperature 10oC on a day when the peak hourly flow is 3.0 MGD. After filtration, the water is chlorinated in a baffled reservoir. For the peak hourly flow rate, t10 is 90 minutes. What is the required disinfection for the removal of Giardia cysts of the filtered water if free chlorine is used? The raw water microorganism concentration is <1/100 L.

Note: According to regulations, the free residual chlorine in the water entering the distribution system cannot be less than 0.2 mg/L for more than 4 hours and a residual in the distribution system must be detectable in at least 95% of the samples tested each month.

3. The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free chlorine residual is applied at the well field and is 0.5 mg/L entering the distribution system, what is the log inactivation of viruses?

4. As part of their proposed new research treatment plant, City of St. James is planning to use five banks of rapid sand filter after their sedimentation tanks. Each bank of sand filters has six filters operated in parallel. Each filter bed has a surface area of 3m X 2m. The design flow rate is 0.044 m3/second. If the design loading rate to the filter is 150 m3 /day. m2, calculate the following:

a) What total filter surface area should be provided and how many banks of filters need to be operational?
b) What is the loading rate when one filter is out of service?

Note: Experiments conducted with rapid sand filters at nearby water treatment plants have demonstrated that satisfactory water quality can be obtained with rates as high as 235 m3 /day. m2.


5. A groundwater contains the following constituents to be treated by the lime-soda process to the minimum hardness possible has the following characteristics:

CO2 = 62.0 mg/L HCO3- = 250.0 mg/L as CaCO3
Ca2+ = 80.00 mg/L Cl- = 35 mg/L
Mg2+ = 36.6 mg/L SO42- = 96.0 mg/L
Na+ = 23.0 mg/L
The facility is to treat 50 x 106 L/day of water from this source using lime-soda ash to reduce the hardness.
a) Determine the total hardness, carbonate hardness, and non-carbonate hardness in mg/L as CaCO3.
b) Determine the lime and soda-ash dosages for softening (units of kg/day). Assume that the lime is 90 percent CaO by weight and the soda ash is pure sodium carbonate.


6. A water treatment plant is processing 19,000 m3/day of water. A settling basin for Type- 2 suspension will remove 100 percent of all particles which has a settling velocity of 0.75 m/hour. The basin has an average depth of 3.5 meters and the weir overflow rate is 8m3/m.hour. Determine:
a) Dimensions of each basin;
b) Detention time,
c) Weir length for each basin.

Assume there are 3 basins with a rectangular unit in which the length is 3 times the width.


7. Why is there a concern for dissolved organics and color in the water supply and in water treatment plant?




Related Discussions:- Environmental engineering.

Calculate distance between top and bottom chord of the truss, A W12x58 memb...

A W12x58 member, which comprises a vertical member in a truss span, is subjected to a factored axial compressive force of 163 kips.  The W12x58 section is oriented such that the st

Determine the allowable pressue, The data profile as shown in Figure is obt...

The data profile as shown in Figure is obtained. A best average of N values gave N 10 = 21, column loads including dead and live loads ranged from 500 kN to 950 kN. Determine the

Construction of passenger terminal building, Construction of Passenger Term...

Construction of Passenger Terminal Building: There are various concepts in planning and constructing passenger terminal buildings. These are : (a)        The international

Derive, Derived condition of economic span of bridge

Derived condition of economic span of bridge

Concrete, what is the allwoable combined aggregates Fineness Modulus

what is the allwoable combined aggregates Fineness Modulus

Why does pipe jacking machine usually get stuck, Q. Why does pipe jacking m...

Q. Why does pipe jacking machine usually get stuck when the ground condition change from soil to very hard rock? When pipejacking machine moves from anarea of soil to very hard

Bedding of precast concrete paving units, Q. Sand layer vs. cement sand use...

Q. Sand layer vs. cement sand used as bedding of precast concrete paving units Cement sand is a mixture of sand and cement and it behaves as a cohesive mass once mixed. Usuall

What is thermodynamics?, Thermodynamics is concerned with the conversion of...

Thermodynamics is concerned with the conversion ofheat into mechanical energy or vice versa.  Heat usually generated through combustion of fossil fuelor nuclear reaction. Exa

Cover depths of jacking pipes, Question While pipe jacking or microt...

Question While pipe jacking or microtunneling , it is usually accepted that cover depths of jacking pipes cannot be also shallow as in less than 2D where D is the diameter o

Three key types of reinforcement used in pre stressing, Question-What are t...

Question-What are three key types of r einforcement used in pre stressing ?   Answer- (i) Spalling reinforcement - Spalling stresses are established behind loaded

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd