Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Explain the erosion and sedimentation, Explain the Erosion and Sedimentatio...

Explain the Erosion and Sedimentation Erosion: Removal of soil or other channel material caused by the rapid movement of water over the channel surface. The removed material

Explain the statements about the critical path method, 1. Determine a netwo...

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships.  2.  Precedence diagr

Determine the allowable bearing pressure of the sand, Two load tests were c...

Two load tests were conducted at a site-one with a 0.5 m square test plate and the other with a 1.0 m square test plate. For a settlement of 25 mm, the loads were found to be 60 kN

Brick pavement, Brick Pavement: In regions where stone aggregates are...

Brick Pavement: In regions where stone aggregates are not available within economical leads, bricks provide a cheaper alternative. Flat-brick or brick-on-edge pavements provi

Bituminous courses, Bituminous Courses Types of Bituminous Courses ...

Bituminous Courses Types of Bituminous Courses The following are the various bituminous course commonly used : (a) Prime Coat (b) Tack Coat (c) Surface Dress

Explain in detail about textural classification, Explain in detail about  ...

Explain in detail about  Textural classification. Sketch neatly the Casagrande's plasticity chart indicating several aspects. How would you use it in classifying the fine graine

Street originate in the plumbing term street ell, How did street originate ...

How did street originate in the plumbing term street ell? Ans) A "street ell" may have gotten its name due to it describes a 90° fitting particularly useful in tight, street dit

Distomat, Feactures and uses of distomat

Feactures and uses of distomat

Determine the concept of resultant force at a section, Resultant force at a...

Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd