Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Survey, how can I use reciprocal type of leveng method to level a ground, a...

how can I use reciprocal type of leveng method to level a ground, and a procedure

What is the sludge volume index, What is the Sludge Volume Index? Two 1...

What is the Sludge Volume Index? Two 1 L samples of mixed liquor are taken from a lagoon. After settling for 30 min in a graduated cylinder, 250 mL of solids have settled out i

Wastewater, Why is there a concern for dissolved organics and color in the ...

Why is there a concern for dissolved organics and color in the water supply and in water treatment plant?

Cavities under structures., This is the title for my thesis for masters in ...

This is the title for my thesis for masters in structural engineering. Is it possible to make for me the literature review? I already have my references.

Som, Maximum thermal stress in circular tapering section is

Maximum thermal stress in circular tapering section is

Geotechnical engineering, Explain coulomb''s wedge theory-definition and de...

Explain coulomb''s wedge theory-definition and derivation

Determine load carried by each cylinder, Determine load carried by each cyl...

Determine load carried by each cylinder: A hollow steel cylinder of cross-sectional area 2000 mm 2 concentrically surrounds a solid aluminium cylinder of cross-sectional area

Unsealed contraction joints in concrete pavement, Unsealed contraction join...

Unsealed contraction joints in concrete pavement For unreinforced concrete pavement, contraction joint is an approximately 3mm wide groove with a depth of about one-third to o

Hydrographic data for design of bridge, Q.What Hydrographic data required f...

Q.What Hydrographic data required for Design of bridge? (i) Design discharge for bridge waterway and foundation with corresponding high flood levels. Frequency curve for annual

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd