Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

#title.long span truss design, what are the step by step process of designi...

what are the step by step process of designing steel long span trusses?

Write short note on skv process of thermit welding, Q. Write short note on...

Q. Write short note on SKV  process of thermit welding? This term is used for welding by Alumino thermic process with short preheat time. The time required for preheat with pet

Calculate carbon intensity, how to calculate the carbon intensity (gC/MJ) f...

how to calculate the carbon intensity (gC/MJ) for gasoline ( C7H16 ) , we have the Energy Density = 32.2 MJ/L Fluid Density = 0.727 g/mL

Geodesy, what is the difference between geodesy and plane survey

what is the difference between geodesy and plane survey

Define underwater inspection of steel or cast iron structure, Define Underw...

Define Underwater Inspection of steel or cast iron structures? Underwater Inspection of steel/cast iron structures may be carried out as under: i. Start the inspection at sp

Cutting edge in well foundation, Q. Cutting edge in well foundation? Th...

Q. Cutting edge in well foundation? The function of cutting edge on well foundation is basically to cut through the earth which being sunk. The angle of well curb pushes the ea

Determine concentration of total solids and volatile solids, The following ...

The following test results were obtained for a 100 ml wastewater sample taken at the inlet to wastewater treatment plant.  The tests were performed using the standard methods. Dete

Explain the variable conditions of river flow - bridges, Explain the Variab...

Explain the Variable Conditions of River Flow and Health State? The variable conditions of river flow and health state of structure demands constant supervision.  Although scou

Surveying, rectangular grid method for representing contours

rectangular grid method for representing contours

Determine the final stresses in the bolt, Determine the final stresses in t...

Determine the final stresses in the bolt: A steel bolt of diameter 12 mm and length 175 mm is used to clamp a brass sleeve of length 150 mm to a rigid base plate as in Figure.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd