Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Chain survey, what are the obstacles in chain survey in brief

what are the obstacles in chain survey in brief

Roads in deserts, Roads in Deserts: Problems Encountered The ...

Roads in Deserts: Problems Encountered The western portion of Rajasthan is part of the Thar desert, where strong winds below the fine desert sand particles leading to

About distomat, what is distomat? functipns &properties

what is distomat? functipns &properties

What will be the increase in horizontal thrust, A 9 metre high retaining wa...

A 9 metre high retaining wall retains a soil with the following properties: φ = 36°; γ = 18 kN/m 3 . What will be the enhance in horizontal thrust if the soil slopes up from the

State the loss of prestress, State the Loss of prestress Loss of prestr...

State the Loss of prestress Loss of prestress due to elastic shortening definitely occurs in pre-tensioned concrete members. But in post-tensioned members it does not occur if

Disparities between regular precast and pipe jacking, Question What are...

Question What are main disparities in design between regular precast concrete pipes and pipes used for pipe jacking ? Answer For pipes used for pipe jacking, they h

Tests on bricks, Tests on Bricks The following laboratory tests can be...

Tests on Bricks The following laboratory tests can be conducted on the bricks to find their suitability: 1.    Crushing strength 2.    Absorption 3.    Shape and size

Geotechnical Design, I need this to be done perfectly . It is a civil engin...

I need this to be done perfectly . It is a civil engineering assignment. Please let me know if you can solve this perfectly within no more than 40 hours. Thanks.

What is multiple-cell box girder, Q. What is Multiple-cell box girder? ...

Q. What is Multiple-cell box girder? Multiple-cell box girder: cells connected by top flanges vs. cells connected both by top and bottom flanges When the depth of a box gi

Explain the primary treatment for wastewater, Explain the Primary Treatment...

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd