Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Define the cavitation - underwater inspection of bridge, Define the Cavitat...

Define the Cavitation - underwater inspection of bridge? Cavitation damage is caused by repeated impact forces caused by collapse of vapour bubbles in rapidly flowing water. Th

Influence of pressure in the soil, Q. Influence of Pressure in the Soil? ...

Q. Influence of Pressure in the Soil? Figure shows the stress state beneath a footing. The steady state situation prior to footing as well as qualitative variation of pressure

Why we use air valves, Q. Why we use Air Valves? Air Valves - Air valve...

Q. Why we use Air Valves? Air Valves - Air valves of proper size and pressure rating at summits. Air valves ensure the safety of the pipe line against collapse when at points o

Effect of prestress in an reinforced cantilever beam, Effect of prestress i...

Effect of prestress in an reinforced cantilever beam The effect of prestress in an ordinary reinforced cantilever beam and a prestressed concrete (PSC) beam. When no load is pr

Wet mix Macadam, Test required before laying or after laying.

Test required before laying or after laying.

Integration of the strain settlement, All soils subjected to stress undergo...

All soils subjected to stress undergo strain. This will be taking place within the soil skeleton. This strain is caused by rolling, slipping, sliding and crushing at the particle c

Lime, what is stone lime shall lime and kankar lime

what is stone lime shall lime and kankar lime

Explain the term - strength cement, Explain the term - strength cement ...

Explain the term - strength cement It should be appreciated that the tensioning arrangement shall have to be kept in place until tendons are cut. This shall depend on how quick

Find the youngs modulus of the rod, Find the Youngs modulus of the rod: ...

Find the Youngs modulus of the rod: A composite rod is made by joining a copper rod end to end with a second rod of different material but of same cross-section. At 25oC, the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd