Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Human resource, Ask question #Minimum 100 words acceFor this discussion, lo...

Ask question #Minimum 100 words acceFor this discussion, look at a specific country of your choice. Develop two brief introductions, one for a U.S. peer, and one for a peer in anot

Two property rule , The state of a pure substance of given mass is defined ...

The state of a pure substance of given mass is defined by specifying two appropriate properties provided that 1. The system is in equilibrium 2. Gravity, motion, electricity,

Construction of passenger terminal building, Construction of Passenger Term...

Construction of Passenger Terminal Building: There are various concepts in planning and constructing passenger terminal buildings. These are : (a)        The international

Two way slab, how can i design reinforcement for a two way slab

how can i design reinforcement for a two way slab

Explain the mechanism of compaction by paver, Q. Explain the Mechanism of c...

Q. Explain the Mechanism of compaction by paver? Mechanism of compaction by paver, steel-wheeled roller and pneumatic tire rollers Paver, steel-wheeled roller and pneumat

Moment of Inertia of a T Beam, Calculate the moment of inertia and section ...

Calculate the moment of inertia and section modulus (top and bottom of the beam) about the z-axis of the beam cross section of Fig.

ENGlLISH, Ask question #WHAT is presentation skill #

Ask question #WHAT is presentation skill #

Curved prestressed bridge, In a curved prestressed bridge , how ought to t...

In a curved prestressed bridge , how ought to the guided bearings in piers of curved region be oriented with respect to a fixed bearing in abutment?

Explain the swell factor of soil, Explain the Swell Factor of Soil A so...

Explain the Swell Factor of Soil A soil's swell factor represents the fact that the volume of soil placed by nature in the ground is not the same as the volume of the same mass

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd