Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Which is stronger solid steel rod or hollow steel pipe, On a per pound basi...

On a per pound basis, steel pipe is stronger in bending and is less likely to buckle in axial compression.

State the maximum amount of resistance in a pole, State the maximum amount ...

State the maximum amount of resistance in a pole The maximum amount of resistance in a pole is generally required at the base and, so, the maximum cross sectional area is requi

Estimate the net present worth - construction management, Three alternative...

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection wi

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

Verify the total active thrust on the wall per lineal metre, A smooth backe...

A smooth backed vertical wall is 6.3 m high and retains a soil with a bulk unit weight of 18 kN/m 3 and φ = 18°. The top of the soil is level with the top of the wall and is horiz

Define overloading - deterioration in steel, Define Overloading - Deteriora...

Define Overloading - Deterioration in Steel? Steel structural elements are sensitive to impact damage from moving vessels and other types of accidental overloading. Impact or c

Explain Rapid Mixing Tank and Flocculation Basin , Explain Rapid Mixing Tan...

Explain Rapid Mixing Tank For the chemical reactions to occur, the chemicals must be mixed with water for both coagulation and softening we need mixing of chemical wi

Stone, Explain briefly physical classifications of stone

Explain briefly physical classifications of stone

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd