Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Explain about warren truss, Q. Explain about Warren Truss? A truss is a...

Q. Explain about Warren Truss? A truss is a simple structure whose members are subject to axial compression and tension only and however not bending moment. The most common tru

Comparison of pre and post-tensioning, Comparison of pre and post-tensionin...

Comparison of pre and post-tensioning A comparison between pre-tensioned and post-tensioned concrete members can be made on the basis of the following considerations. (a) T

Diffrence between concrete road and bituminous road, Q. Diffrence between C...

Q. Diffrence between Concrete road and bituminous road? Concrete road belongs to rigid pavement and they don't deflect under traffic loads. Quite the reverse, bituminous pavem

Show the differences between GGBS and PFA, Q. Show the Differences Between ...

Q. Show the Differences Between GGBS and PFA? The use of GGBS as substitute of cement improves smaller reliance on PFA. Particularly GGBS is supposed to be more compatible with

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Calculation of deformation, Calculation of deformation For calculation ...

Calculation of deformation For calculation of deformation at some stage before the total creep is reached,  it may be assumed that about half the total creep takes place  in  f

Design of steel lug angles with channel sections.., while designing the lug...

while designing the lug angles with the channel section what does "the force not acccounted for by the direct connection of member" mean?

Doors and windows, what are the actuall windows and door dimensions e.g AN ...

what are the actuall windows and door dimensions e.g AN ND4

Granite tiles for construction material, Q. Granite Tiles for construction ...

Q. Granite Tiles for construction material? At every important station for public urinals granite may be used as wall cladding drain and foot rest material. The water sinks at

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd