Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Grade of cement, Grade of Cement: In India, the following grades of c...

Grade of Cement: In India, the following grades of cement are used for roads : Ordinary Portland Cement (OPC) Grade 33 Grade 43 Grade 53 Portland Pozz

Explain civil fe hydraulics and hydrologic systems, Explain Civil Fe Hydrau...

Explain Civil Fe Hydraulics and Hydrologic Systems When spills occur at grade on soils in areas where unconfined aquifers are present, remediation procedures to remove the poll

Highway and traffic, am currently doing my masters degree in highway,pleas...

am currently doing my masters degree in highway,please suggest for me topics i will research on

Surveying, A pre- engineering base line was run down a very steep hill.rath...

A pre- engineering base line was run down a very steep hill.rather than measure horizontaily down hill with steel tape: surveyor measured the vertical angle with the theodolite and

Continuous beam reaction by equilibrium equation, Solve problem of continu...

Solve problem of continuous beam with equilibrium equation

Explain the tertiary treatment for wastewater, Explain the Tertiary Treatme...

Explain the Tertiary Treatment for Wastewater Tertiary Treatment: in cases where secondary treatment is not adequate (particularly if the discharges are into a sensitive water

Railway bridge, how to measure the waterways of railway bridges

how to measure the waterways of railway bridges

Determine the active thrust on the wall by culmann method, A retaining wall...

A retaining wall with its face inclined at 75° with horizontal is 10 m high and retains soil inclined at a uniform surcharge angle of 10°. If the angle of internal friction of the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd