An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Explain rebound hammer - underwater non-destructive testing, Explain Reboun...

Explain Rebound Hammer - Underwater non-destructive testing? The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condit

Design of steel structure, in compression member [strut] why no deduction o...

in compression member [strut] why no deduction of area of rivet hole?

Mosaic and p v c tiles, Q. Mosaic and P V C Tiles? The water sink at wa...

Q. Mosaic and P V C Tiles? The water sink at water points may be provided with mosaic lining at other than important station. Mosaic tiles also may be provided in flooring of

Cost estimating, I would like to know if anyone can help me with my const e...

I would like to know if anyone can help me with my const estimating project

Loss of prestress due to creep of concrete, Loss of prestress due to creep ...

Loss of prestress due to creep of concrete Creep of concrete means time dependent deformation of concrete. Its effect depends upon the interval of  time for which the member is

Analysis of the two stage construction, A County is planning to build a new...

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widen

What is moisture-dry density, Describe why soils are compacted in the field...

Describe why soils are compacted in the field. How is the degree of compaction ensured in the field (i.e., control of field compaction)? Distinguish among 'compaction' and 'consoli

Maximum shear stress , the propane gas tank has an inner diameter of 1500mm...

the propane gas tank has an inner diameter of 1500mm and wall thickness of 15mm. If the wall is pressurized to 2MPa, determine the absolute maximum shear stress in the wall of tank

Explain box jig, Explain Box jig? a) The box jig is so named because of...

Explain Box jig? a) The box jig is so named because of its box shaped construction, closed from most of the sides. b) It is normally designed for those components having awk

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd