Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

KNIFE EDGE LOADING, How does the knife edge load simulate the existing cond...

How does the knife edge load simulate the existing condition of the bridge structure?

Define the marine growth - underwater inspection of bridges, Define the Mar...

Define the Marine Growth - Underwater inspection of bridges? Bridges on many inland waterways are relatively clean and free of marine growth. However, there is likelihood of ma

#surveying, Finding distances in tacheometric survey

Finding distances in tacheometric survey

Propped cantilever retaining wall, how to combine moments from soil pressur...

how to combine moments from soil pressure and surcharge to get maximum moment

What is main purpose of swabbing, Question After construction of waterm...

Question After construction of watermain, earlier to hydrostatic pressure test , swabbing is approved out. What is main purpose of swabbing ? Answer Pipelines ha

Define the impact damage - underwater inspection of bridge, Define the Impa...

Define the Impact Damage - underwater inspection of bridge? Impact from moving vessels or logs carried during the floods can inflict damage to the structure. The impact or coll

Leveling, how to find the correction on leveling calculation

how to find the correction on leveling calculation

Survey obstacles in both chainage and ranging, Askobstacles I ranging andsu...

Askobstacles I ranging andsurvey question #Minimum 100 words accepted#

Define the usage of data from hydrographs, Define the usage of Data from Hy...

Define the usage of Data from Hydrographs Flow rates and volume quantities over time. Predictions based on the runoff flow rates. The characteristics of the drainage b

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd