Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

How do you maintain water pressure, If you have water pressure and wish to ...

If you have water pressure and wish to handle it, do not cause flow in the line, which will decrease pressure because of friction. To keep pressure up, decrease friction by increas

Define coefficient of consolidation, Define and distinguish among coefficie...

Define and distinguish among coefficient of volume compressibility and coefficient of consolidation. Explain clearly one method of computing coefficient of consolidation, given

#manholes, #how are manholes mantained

#how are manholes mantained

Show the properties of elastomer, Q. Show the Properties of Elastomer ? ...

Q. Show the Properties of Elastomer ? Though elastomeric bearings offer a number of advantages as compared to steel bearings, many failures have been reported pertaining to the

Prestressed concrete poles, Prestressed concrete poles In the past deca...

Prestressed concrete poles In the past decades, prestressed  concrete poles have become popular and have replaced the traditional poles made of timber, steel or reinforced  con

Roads in hilly areas, Roads in Hilly Areas: (a)        The alignment s...

Roads in Hilly Areas: (a)        The alignment selected should attain the changes in elevation by adopting the ruling gradient to the maximum length. Limiting and exceptional

Construction management, pert disadvantages of software support, datacolle...

pert disadvantages of software support, datacollection , interpretation of results issues

Gas welding be erected in upright position, Question Explain some reaso...

Question Explain some reasons why should acetylene gas cylinders used for gas welding be erected in upright position? Answer Acetylene gas is usually used for gas wel

Expansion jiont, some expansion joint(10 mm- 20 mm) on my basement roof.rai...

some expansion joint(10 mm- 20 mm) on my basement roof.rain water leakage in basement i want the solution of expiation joint and water leakes.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd