Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

True or false, an increase in consumer income will affect the supply of any...

an increase in consumer income will affect the supply of any given product

Levelling, important terms used in levelling

important terms used in levelling

Explain box jig, Explain Box jig? a) The box jig is so named because of...

Explain Box jig? a) The box jig is so named because of its box shaped construction, closed from most of the sides. b) It is normally designed for those components having awk

Find the cumulative distribution function, Find the Cumulative Distribution...

Find the Cumulative Distribution Function: Find the cdf of Y = Z 2 where Z - N (0,l) Solution: F(y)= P(Y ≤ y) = p(z 2 ≤y) = P(-√y≤ √z≤√y) = ?(√y)- ?(-√y) = ?(√y)

door shutters, what is the difference between paneled and glazed shutte

what is the difference between paneled and glazed shutter

Turbines, How do we get electricity even when the gates of a dam were close...

How do we get electricity even when the gates of a dam were closed?

Water absorption test for precast concrete pipes, Question What is the ...

Question What is the major purpose of carrying out water absorption test for precast concrete pipes? Answer Cement will mix with additional water than is compulsory t

Determine the thermal stress in the bar, Determine the thermal stress in th...

Determine the thermal stress in the bar: A stepped bar made of aluminum is held between two supports. The bar is 900 mm in length at 38ºC, 600 mm of which is having a diameter

How to design marginal embankments, Q. How to design Marginal Embankments? ...

Q. How to design Marginal Embankments? Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below

Assigning central pier and abutment as fixed piers, What are beneficial poi...

What are beneficial points of assigning central pier and abutment as fixed piers ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd