Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Cleaning and greasing of steel sliding bearings, Cleaning and greasing of s...

Cleaning and greasing of steel sliding bearings : Following equipments are required for greasing of steel sliding bearings: 1. Jacks (50 ton capacity) - 2 nos. 2. Hard wo

What is over vibration of fresh concrete, Q. What is Over vibration of fres...

Q. What is Over vibration of fresh concrete? For proper compaction of concrete by immersion vibrators, vibrating part of the vibrators must be completely inserted into the conc

Behaviour of elastomeric bearings, Q. Behaviour of elastomeric bearings ? ...

Q. Behaviour of elastomeric bearings ? In order to carry out successful design and installation of elastomeric bearings, it is necessary to understand the behaviour of elastome

State the term - constant eccentricity, State the term - constant eccentric...

State the term - constant eccentricity A pre-stressed concrete beam has a width of 300 mm and an overall depth of 450 mm. The permissible stresses in tension and compression du

Determine the grade rod reading at station, A section view of a proposed ro...

A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft

Prestressed concrete poles, Prestressed concrete poles In the past deca...

Prestressed concrete poles In the past decades, prestressed  concrete poles have become popular and have replaced the traditional poles made of timber, steel or reinforced  con

Bending moment , The internal forces in any cross-section of a symmetric me...

The internal forces in any cross-section of a symmetric member in pure bending are equivalent toa couple M The moment of the couple is referred to as the bending moment in the s

Explain cercla and sara - hazardous waste regulations, Explain CERCLA and S...

Explain CERCLA and SARA - Hazardous Waste Regulations In 1980, the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) was enacted to address tho

Cutbacks and emulsions, Cutbacks And Emulsions: Cutbacks A cu...

Cutbacks And Emulsions: Cutbacks A cutback is a bitumen whose viscosity has been reduced by adding a diluent such as naphtha or kerosene. The use of cut-back is not f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd