Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Kerb overflow weirs – horizontal bars vs. vertical bars, Q. Kerb overflow w...

Q. Kerb overflow weirs – horizontal bars vs. vertical bars? Overflow weirs must be provided for steep roads (longitudinal gradient>5%), flat roads (longitudinal gradient Ess

Specification of wood work for door, Q. Specification of Wood work for Door...

Q. Specification of Wood work for Door? 1. General - Timber for door, window and ventilators frames shall be as specified. Timber shall be sawn in the direction of the grains.

Simulink software, Using Matlab/ Simulink software to model the overall bui...

Using Matlab/ Simulink software to model the overall building fabric heat transmit characteristics, in order to estimate the maximum rate of heat loss (kW) from the building under

Derive, Derived condition of economic span of bridge

Derived condition of economic span of bridge

Aggregate crushing test, Aggregate Crushing Test: In which the layer o...

Aggregate Crushing Test: In which the layer of aggregates in a cylindrical measure is subjected to a compressive load of 40 T, and the per cent fines generated are determined,

Surveying, WCB from included angle

WCB from included angle

Explain the traffic safety - transportation, Explain the Traffic Safety - T...

Explain the Traffic Safety - Transportation Crash rates are normally considered better indicators of risk than crash frequencies.  a. Crash rates for intersections are norma

Determine the flow rate if the pump is turned at 100 rpm, One pump lifts st...

One pump lifts storm water from a storage tunnel wet well a constant vertical distance of 150 ft. The equivalent length Le of the 14 in diameter piping is 1,000 ft. Pressure drop d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd