Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Define wastewater treatment processes, Define Wastewater treatment Processe...

Define Wastewater treatment Processes The wastewater treatment processes that we design mimic the processes that occur in the nature (for example processes that occur in a flow

Define recommendations for ptfe, Define Recommendations for PTFE? (a) I...

Define Recommendations for PTFE? (a) It can be either of the two forms given below: (i) Dimpled large sheet It may be circular or rectangular divided maximum into four pa

Landslides induced by rainfall, Landslides induced by rainfall After r...

Landslides induced by rainfall After rainfall, groundwater pressure is built up and this elevates ground water table. Water inside the pores of soil reducesthe effective stres

Calculate the modulus of elasticity of concrete, Calculate the Modulus of e...

Calculate the Modulus of elasticity of concrete A pre-stressed concrete beam, having a cross-section of 150 mm width and 400 mm depth, is used over a span of 8 m. Straight tend

Explain the underwater problems and material defects, Explain the Underwate...

Explain the Underwater Problems and Material Defects? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as

Define fixed instrumentation - sounding or sensing devices, Define Fixed in...

Define Fixed instrumentation - Sounding or Sensing Devices? It is possible to monitor local scour at pier or abutment using fixed instrumentation as an alternative to the sound

Explain frame members effective lengths, Explain Frame Members Effective Le...

Explain Frame Members Effective Lengths a. Effective length is a product of an effective length factor (k) and the actual length of the column. b. k depends on the rel

Ballast and sub-ballast aggregates, I want to check the grammer of report a...

I want to check the grammer of report and edit it in better sentances , reduce the Plagiarism & edit the reference to havaerd style

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd