Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Concrete, what are the appropriate methods of concreting

what are the appropriate methods of concreting

Calcculate the material costs, A capital improvement project requires the i...

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts space

Acid test - tests on stones, Acid Test: This test is usually carried...

Acid Test: This test is usually carried out on sand stones to examine the presence of calcium carbonate that weakens the weather resisting quality. In this particular  test,

Trigo, A pole which leans 11o from the vertical toward the sun casts a shad...

A pole which leans 11o from the vertical toward the sun casts a shadow 12m long when the angle of elevation of the sun is 40o. Find the length of the pole

Calculation of deformation, Calculation of deformation For calculation ...

Calculation of deformation For calculation of deformation at some stage before the total creep is reached,  it may be assumed that about half the total creep takes place  in  f

Mosaic and p v c tiles, Q. Mosaic and P V C Tiles? The water sink at wa...

Q. Mosaic and P V C Tiles? The water sink at water points may be provided with mosaic lining at other than important station. Mosaic tiles also may be provided in flooring of

Grouted or penetration macadam, Grouted or Penetration Macadam: This ...

Grouted or Penetration Macadam: This is a specification where the binder is sprayed on a compacted layer of stone aggregates and is allowed to penetrate and bind the aggregat

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

Human values, give the two aspects of honesty& explain

give the two aspects of honesty& explain

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd