Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Define contaminants - underwater inspection of bridge, Define Contaminants ...

Define Contaminants - underwater inspection of bridge? There are various substances that may be inadvertently incorporated into the concrete matrix (e.g. glass, coal, gypsum),

Calculate equivalent uniform annual cost for the excavator, Calculate Equiv...

Calculate Equivalent Uniform Annual Cost for the Excavator An earthwork contractor is considering the purchase of a new excavator.  Based on 10% interest, the equivalent unifor

Common defects - bituminous roads, Common defects - bituminous roads: ...

Common defects - bituminous roads: Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt. If an overlay is to be laid on a cracke

Verify the intensity of vertical stress at a point, Verify the intensity of...

Verify the intensity of vertical stress at a point A line load of 100 kN/metre run extends to a long distance. Verify the intensity of vertical stress at a point, 2 m below the

Hydraulics, what is hydraulic grid line

what is hydraulic grid line

Strenght of meterials 2, Difference between direct and bending stress diagr...

Difference between direct and bending stress diagrams

Transportation Engineering, can u help with assignment and how much per ass...

can u help with assignment and how much per assignment

Determine the final stresses in the bolt, Determine the final stresses in t...

Determine the final stresses in the bolt: A steel bolt of diameter 12 mm and length 175 mm is used to clamp a brass sleeve of length 150 mm to a rigid base plate as in Figure.

Arches and lintels, classification of arches based on their shape are?

classification of arches based on their shape are?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd