Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Determine the total head and total pressure of water, Determine the total h...

Determine the total head and total pressure of water flowing at  in a pipe which has the following data: Flow= 2,500 gpm; Elevation = 30 ft; Pressure = 40 psi; Pipe Diameter =

Moment distribution, Moment Distribution: You have learnt about moment...

Moment Distribution: You have learnt about moment distribution procedure after deriving the slope deflection equation for the members. The concepts of distribution factor and

Determine the thickness of flexible pavement layer, Determine the thickness...

Determine the thickness of flexible pavement layer 2 given the following:  FACTS: Total Structural Number required = 7.0 Total number of layers = 2 Layer 1 consists of

Keywords related to water transportation, Keywords related to water transpo...

Keywords related to water transportation: Oceanic Shipping: Shipping taking place in the oceans. Coastal Shipping: Shipping taking place along the coast line. Inlan

Explain the unconfined compression strength of the clay, A square group of ...

A square group of 9 piles was driven into soft clay extending to a large depth. The diameter and length of the piles were 30 cm and 9 m respectively. If the unconfined compression

Two pegs test, the distance between two pegs M and N is 7,063 as measured o...

the distance between two pegs M and N is 7,063 as measured on a slope. the height measured on the pegs are that M=1.814M and N=0.5687M

State the importance of structural element, State the importance of structu...

State the importance of structural element If this structural element is used as a beam element, subjected to self load and other imposed transverse loads, then the bottom fibr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd