Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

.levelling, differentiate between Dumpy level:The Wye or Y level:Cooke''s r...

differentiate between Dumpy level:The Wye or Y level:Cooke''s reversible level: Cushing''s level:Tilting level and Automatic level

Define divers in a team for underwater inspection of bridge, Define Divers ...

Define Divers in a team for Underwater inspection of Bridge? One team of divers should have minimum three members. This is a requirement of safe working. The idea is while a mi

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Timber, Cross-section of exogeneous tree

Cross-section of exogeneous tree

Explain the confined aquifer and piezometric surface, Explain the Confined ...

Explain the Confined Aquifer and Piezometric Surface Confined Aquifer Groundwater is confined by impervious geologic stratums on all sides. The water may be under pressure.

Compute the degree of saturation, The maximum dry density and optimum moist...

The maximum dry density and optimum moisture content of a soil from standard proctor's test are 18 kN/m 3 and 16% respectively. Compute the degree of saturation of the sample,

Heat transfer, Three mechanisms: 1) Conduction - occurs in solids and st...

Three mechanisms: 1) Conduction - occurs in solids and stationary fluids (liquids or gases). 2) Convection - occurs in fluids. Change in the buoyancy of the fluid due to its

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd