Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Explain the shrink factor of soil, Explain the Shrink Factor of Soil In...

Explain the Shrink Factor of Soil In addition to the swell factor and its associated load factor, soil also has a shrink factor. While the first two relate the volume of an equ

.levelling, differentiate between Dumpy level:The Wye or Y level:Cooke''s r...

differentiate between Dumpy level:The Wye or Y level:Cooke''s reversible level: Cushing''s level:Tilting level and Automatic level

Pipes, difference between delievery and suction pipe?

difference between delievery and suction pipe?

Determine the weight of solids mixed in the suspension, In a hydrometer ana...

In a hydrometer analysis, the corrected hydrometer reading in a 1000 ml uniform soil suspension at the start of sedimentation was 28. After a lapse of 30 minutes, the corrected hyd

Human resource, Ask question #Minimum 100 words acceFor this discussion, lo...

Ask question #Minimum 100 words acceFor this discussion, look at a specific country of your choice. Develop two brief introductions, one for a U.S. peer, and one for a peer in anot

Define the phreatic line and phreatic zone, Define the Phreatic Line and Ph...

Define the Phreatic Line and Phreatic Zone Phreatic Line: In an unconfined aquifer, it represents the water table.   Phreatic Zone: In an unconfined aquifer, it is located b

Define pneumatic tools for underwater inspection of bridge, Define Pneumati...

Define Pneumatic Tools for Underwater Inspection of Bridge? These are more efficient than hand tools and cause less diver fatigue. The disadvantages are that below about 20 m,

Steel, sir i want to know that which pages of IS800:2007 is used for steel ...

sir i want to know that which pages of IS800:2007 is used for steel design of tension member, compression member, collumn, beam, connections, trusses etc.. please give me the topic

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd