Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

What is collocated network operation, What is Collocated network operation ...

What is Collocated network operation As wireless LANs become more popular, it is likely for two or more wireless LANs to operate in the similar area or in some area where inter

Main advantages of using rubber dams, Question In assortment of dams in...

Question In assortment of dams in drainage channels, what are the main advantages of using rubber dams instead of steel-gate dams ? Answer Key Advantages of rubber d

Explain interim inspection - underwater inspection of bridge, Explain the I...

Explain the Interim inspection - underwater inspection of bridge An interim inspection is an inspection scheduled at the discretion of the engineer. An interim inspection is us

Process of lubrication of girder bearing, Q. Process of Lubrication of Gird...

Q. Process of Lubrication of Girder Bearing? Oiling and greasing of bearings is done to ensure that the bearings are well lubricated and working freely to permit expansion and

Different type of stones, Different type of Stones Stones used for civi...

Different type of Stones Stones used for civil engineering works can be classified in the following 3 ways:    Geological    Physical    Chemical

Structural analysis & design, This is an optional team assignment. This gra...

This is an optional team assignment. This grade will replace your lowest two homework grades. You may work in teams of 3-4 students. Design the lightest concrete cantilever beam

What is partial prestressing, What is Partial Prestressing It is a form...

What is Partial Prestressing It is a form of prestressing in which tensile stresses are permitted, upto a limited extent, in concrete under working loads. As the permitted tens

Foundation, difference between piles and pier

difference between piles and pier

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd