Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Probable distribution function, The diameter of an electric cable, say X, i...

The diameter of an electric cable, say X, is assumed to be continous random variable with pdf;f(x)=6x(1-x), 0 b}.

Som, Maximum thermal stress in circular tapering section is

Maximum thermal stress in circular tapering section is

FLAMISH BOND, TH ADVANTAGES OF FLAMISH BOND

TH ADVANTAGES OF FLAMISH BOND

State the volume change from the plastic limit, The plastic limit and liqui...

The plastic limit and liquid limit of a soil are 33% and 45% respectively. The percentage volume change from the liquid limit to the dry state is 36% of the dry volume. Likewise, t

Concrete mix proportions, Concrete Mix Proportions Concrete mix proport...

Concrete Mix Proportions Concrete mix proportions should be chosen in such a way that concrete of adequate workability is obtained. Workability of concrete mix should be such t

Chemical prestressing, Chemical prestressing In prestressed concrete, ...

Chemical prestressing In prestressed concrete, normally tendons are stretched and are retained in a stretched condition by concrete. Consequently, concrete comes under compres

Shear and tensile strength, What is the difference between shear and tensil...

What is the difference between shear and tensile strength? Ans) Tensile Strength for a Bolt is explained by applying a Force along it long axis. Shear Strength for a Bolt is exp

Calculate the deposited amount - construction management, An engineer depos...

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-mo

Calculate the actual water cement ratio, Calculate the Actual Water Cement ...

Calculate the Actual Water Cement Ratio A jobsite delivery ticket is shown below for a grout mix.  The actual w/c ratio is most nearly: Solution:       Note, althou

Example, slope deflection with settlement

slope deflection with settlement

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd