Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Chapter 9, define of window pivoted

define of window pivoted

Explain working of ultrasonic system for concrete elements, Explain the wor...

Explain the working of Ultrasonic System for Concrete Elements? Ultrasonic methods can be used underwater for overall assessment of the strength of concrete based on sound velo

What is activated sludge process, Q. What is Activated Sludge process? ...

Q. What is Activated Sludge process? The term Activated Sludge is used to indicate the sludge which is obtained by settling sewage in presence of abundant oxygen. The Activated

Timber, Cross-section of exogeneous tree

Cross-section of exogeneous tree

Determine the settlement of the foundation, The thiclcness of the normally...

The thiclcness of the normally consolidated soft clay layer is 6 m. The natural water content is 31 percent. The specific gravity of the soil being 2.68 with a liquid limit of 4

Assignment, I need to find support reactions at O for the beam with a distr...

I need to find support reactions at O for the beam with a distributed load, a 6 kN moment couple at A and a 3 kN axial load as shown in picture.

Explain types of tiles, Q. Explain Types Of Tiles? Different types of t...

Q. Explain Types Of Tiles? Different types of tiles available in the market for floor and walls & dado are as under - 1. Glazed tiles , 2. Ceramic tiles , 3. Granit

Calculate the hydrostatic force, The steel oil container shown in the figur...

The steel oil container shown in the figure has a circular lid centred on its sloping wall. The lid is hinged at A and held closed with a frictionless stopper at B. The lid is made

Chemistry, discuss various chemical reactions involved in lime soda process...

discuss various chemical reactions involved in lime soda process ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd