Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Raft and beam foundation, why is weight of raft not considered in structura...

why is weight of raft not considered in structural design of raft and beam

Light-weight aggregate prestressed concrete, Light-weight Aggregate Prestre...

Light-weight Aggregate Prestressed Concrete The use of  light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of  light-

Butt weld – from one side vs from both sides, Q. Butt weld – from one side ...

Q. Butt weld – from one side vs from both sides? In the design of butt weld strength, it's normally presumed that its strength is at least equivalent to parent metal. To improv

Rail tensors, A hydro stressor consists essentially of a hydraulic pump whi...

A hydro stressor consists essentially of a hydraulic pump which transmits its force through connecting vans to clamps which grips the rail. In case of mechanical tensor the force i

Strength of Materials, How can I get theratio of the maximum deflections of...

How can I get theratio of the maximum deflections of a beam simply supported at its ends with an isolated central load and that of with a uniformly distributed load over its entire

Show afflux and scour in alluvial rivers, Q. Show Afflux and scour in alluv...

Q. Show Afflux and scour in alluvial rivers? In case of alluvial rivers, the river bed comprises scourable material like sand. Constriction of bridge waterway causes increase

State active earth pressure behind a vertical wall, With the aid of Mohr's ...

With the aid of Mohr's circle diagram describe what means by active and passive Rankine states is in a cohesionless soil with a horizontal surface. As obtain an expression for the

Engineering mechanics, Characteristics of couple #Minimum 150 words accepte...

Characteristics of couple #Minimum 150 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd