Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Calculate dead, A building cross section is shown below. The building consi...

A building cross section is shown below. The building consists of eight (8) of the shown frames placed at distance of 20 feet oc for a total length of 140 feet. The glulam beams ar

Define carbonation - underwater inspection of bridge, Define Carbonation - ...

Define Carbonation - underwater inspection of bridge? Carbon dioxide is present in the air and attacks the concrete directly. It has the effect of destroying the normal passivi

Jacking face for pipe-jacking, Ground settlement occurs ahead or behind the...

Ground settlement occurs ahead or behind the jacking face for pipe-jacking? It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 ti

Butt weld – from one side vs from both sides, Q. Butt weld – from one side ...

Q. Butt weld – from one side vs from both sides? In the design of butt weld strength, it's normally presumed that its strength is at least equivalent to parent metal. To improv

Estimation, What are the various methods of recording measurements? List fi...

What are the various methods of recording measurements? List five items each for various methods of recoding measurements?

Self compacting concrete, what will be the w/c ration and cement/fly ash ra...

what will be the w/c ration and cement/fly ash ration for the particular mix design

Present worth of an infinite series of annual amount, The construction of a...

The construction of a new bakery requires the property development firm to pay the municipality the cost to expand its sewage treatment plant. In addition to the expansion costs, t

State the problem and phases of site investigation, State the Problem and p...

State the Problem and phases of site investigation The site investigation is to be performed to obtain the solution for the following problems: i)  Foundation problems ii

Determine the crash rate - transportation, A five-mile long section of two-...

A five-mile long section of two-lane road has an AADT of 8,000.  There have been six crashes on this section of road during the past two years.  What is the crash rate? R sec

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd