Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Key role of drilling fluid in rotary drilling, Question What is key rol...

Question What is key role of drilling fluid in rotary drilling in site search? Answer Drill fluid in rotating serves two main reasons. (i) Facilitate rotation of

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Culverts - causeway and bridges, Culverts, Causeway and Bridges: Roads...

Culverts, Causeway and Bridges: Roads have to cross several natural streams like - rivers and canals. They also have to cross railway lines and cross-roads. The structures nee

Soil mechanics, what is the total volume required for the gravel material o...

what is the total volume required for the gravel material of 6.5mx2314mx0.1m with a relative density of 2.919 and a loose bulk density of 1668kg/m3

Airport., draw a typical layout of airport ?

draw a typical layout of airport ?

Define limitations of radiography - inspection of bridge, Define Limitation...

Define Limitations of Radiography - Underwater Inspection of Bridge? i. Radiography is a costly and time consuming method, which re- quires extensive safety measures to be adop

Internal energy, For a system   Q =W+ ΔE where ΔE is the change in E,...

For a system   Q =W+ ΔE where ΔE is the change in E, the stored energy in the  ΔE system. E has various forms   1. Kinetic Energy 2. Potential Energy Work do

Torpedo splice triple wedges, Torpedo splice triple wedges In a Torpedo...

Torpedo splice triple wedges In a Torpedo splice triple wedges, shown in Figure, are provided to firmly hold tendon wires. Whole assembly of the splice is housed in a sleeve. L

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd