Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Explain the term - untensioned reinforcement, Explain the term - Untensione...

Explain the term - Untensioned Reinforcement In prestressed concrete construction, use of untensioned reinforcement also has to be made alongwith tendons. This is essential as

Use of stone aggregates in road construction, Use of Stone Aggregates in Ro...

Use of Stone Aggregates in Road Construction Stone aggregates are extensively used in roads in pavement layers. They are obtained from natural rock. The following geological

#title.cement factor, Aplease provide tables for each design mix and also t...

Aplease provide tables for each design mix and also the, high early strengh.l thanks

Average heating season outside temperature, Produce a manual determination ...

Produce a manual determination to determine the instantaneous rate of heat loss (kW) through one part of the fabric (eg roof, glazed area, wall) based on an internal building desig

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

State the term - total loss of prestress, Total loss of prestress The ...

Total loss of prestress The total amount of losses of prestresses may be accounted for in a prestressed concrete member by adding different losses which may take place for tha

What are aquifers - hydraulics system, What are Aquifers? Water bearing...

What are Aquifers? Water bearing, underground geologic formations. The subsurface formations are composed of soils and rocks with voids saturated with water.

structure analysis 2, what is ild for indeterminate beam and explain its p...

what is ild for indeterminate beam and explain its procedure

Define the degree of saturation and soil moisture content, Establish the r...

Establish the relationship among degree of saturation, soil moisture content, definite gravity of soil particles, and void ratio. The volume of an undisturbed clay sample having

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd