An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Calculate the horizontal distance, Calculate the Horizontal Distance A ...

Calculate the Horizontal Distance A surveyor's total station measured slope distance near station 3245+26.35 is recorded as 437.380-m with a zenith angle of 118º 48' 07" and a

What is over vibration of fresh concrete, Q. What is Over vibration of fres...

Q. What is Over vibration of fresh concrete? For proper compaction of concrete by immersion vibrators, vibrating part of the vibrators must be completely inserted into the conc

Determine about the pre-stressed concrete beam, Determine about the pre-str...

Determine about the pre-stressed concrete beam A pre-stressed concrete beam has a width of 200 mm and an overall depth of 400 mm. The permissible stresses in tension and compre

Stabilised pavement layers, Stabilised Pavement Layers: Soil stabilis...

Stabilised Pavement Layers: Soil stabilisation is the process of treating a soil in such a manner as to alter and improve its properties for use as a pavement layer on sub-gr

Fixed and pinned connection between piles and pile caps, Q. Fixed vs pinned...

Q. Fixed vs pinned connection between piles and pile caps? The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile hea

Softening point of bitumen, Hi, i need discussion for softening point of bi...

Hi, i need discussion for softening point of bitumen 7.5 ?C

Shallow bedrock condition adverse for open berth piers, Question What i...

Question What is the reason that shallow bedrock condition adverse for open berth piers? Answer Most severe load on piers generally is horizontal load due to berthing

Design, what is the procedure to design the beam and column?

what is the procedure to design the beam and column?

Mini projects, is there any innovative projects in disaster management ?

is there any innovative projects in disaster management ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd