Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Treatment plant - sewer construction, Treatment plant - sewer construction:...

Treatment plant - sewer construction: Problem: How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant? Solution An a

Conics, what is the eccentricity of ellipse

what is the eccentricity of ellipse

Explain the typical wastewater characteristics, Explain the Typical Wastewa...

Explain the Typical Wastewater Characteristics? Total Suspended Solids = 100 - 350 mg/L (200 mg/l is the typical value)    BOD 5 = 100-300 mg/L (200 mg/L is the typical val

Reliability of settlement computations, Inspite of the problems of sample d...

Inspite of the problems of sample disturbance, if 1) e or E vs log p curve is interpreted, reasonably with some corrections for sample disturbance, 2) if the sample disturbance

Structural analysis, steps to analysis a portal frame with sway condition

steps to analysis a portal frame with sway condition

Concrete mix proportions, Concrete Mix Proportions Concrete mix proport...

Concrete Mix Proportions Concrete mix proportions should be chosen in such a way that concrete of adequate workability is obtained. Workability of concrete mix should be such t

Illustrate the term - failure due to rupture of steel, Failure Due to Ruptu...

Failure Due to Rupture of Steel This mode of  failure is likely in lightly reinforced concrete members in which the ultimate strength of  steel is attained before the concrete

Human values, give the two aspects of honesty& explain

give the two aspects of honesty& explain

Problems formed while design of pre-stressed concrete, Determine the proble...

Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by  the engineer engaged in the design of pre-stressed concrete membe

Remedial measures for problems in turbid water - absorption, Define Remedia...

Define Remedial measures for Problems in Turbid Water - Absorption? The process of absorption of light can be overcome by using higher powered lighting, or by using more light

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd