engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Cost effective buildings, How to construct Semi Ellitical Buildings of 15fe...

How to construct Semi Ellitical Buildings of 15feet dia., in Brick Masonry.

Radial contouring, How we can find R.L. of instrument station without movi...

How we can find R.L. of instrument station without moving of instrument.

Concrete cover to enhance fire resistance, Q. Concrete cover to enhance fir...

Q. Concrete cover to enhance fire resistance? In the event of exposing concrete structures to a fire, a temperature gradient is established across the cross section of concrete

Explain the mechanism of compaction by paver, Q. Explain the Mechanism of c...

Q. Explain the Mechanism of compaction by paver? Mechanism of compaction by paver, steel-wheeled roller and pneumatic tire rollers Paver, steel-wheeled roller and pneumat

Road binders - bitumen, Road Binders: Bitumen: Bitumen is a viscous, s...

Road Binders: Bitumen: Bitumen is a viscous, semi-solid material, dark in color, having adhesive properties, and derived from the distillation of petroleum crude in a refinery

Base of concrete retaining walls, Q. Granular fill or rock fill essential a...

Q. Granular fill or rock fill essential at the base of concrete retaining walls? It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom

What do you mean by slip siding, Q.What do you mean by Slip Siding? If ...

Q.What do you mean by Slip Siding? If the Station yard is in a gradient steeper than 1 in 260 or there is a continuous falling gradient away from the station there is a possibi

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Explain the frequency of inspection - underwater inspection, Explain the Fr...

Explain the Frequency of Inspection - Underwater Inspection? Underwater inspections must be done on every bridge identified for such inspection as per the Indian Railways Bridg

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd