engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

How to calculate the combined stresses, Compute the stresses at top and bot...

Compute the stresses at top and bottom fibers in a simply supported pre-stressed concrete beam with a rectangular cross section, 250 mm wide and 450 mm deep, as shown in Figure, at

Closing and opening of expansion joints and contraction join, Question ...

Question In case of for unreinforced concrete carriageway, what will succession of closing and opening of expansion joints and contraction joints? Answer Take a case t

Key functions of changed components of paint, Question What are key fun...

Question What are key functions of changed components of paint? Answer For regular paint application, there are largely three key components of paint, namely primer, u

Effect of rusting on steel reinforcement, Effect of rusting on steel reinfo...

Effect of rusting on steel reinforcement Corrosion of steel reinforcement inside a concrete structure is undesirable in the subsequent ways:  (i)  Presence of rust impairs

Classification of timber based on grading, Classification Based on Grading:...

Classification Based on Grading: IS 883-1970 classifies the structural timber into 3 grades-select grade, grade I and grade II. The classification is depend on, defects, permi

Designing of service reservoirs, Question In designing of service res...

Question In designing of service reservoirs , straight reinforcement in walls of reservoirs is placed at external layer. Give some specific and main reasons?   Answer

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd