engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

Find a suitable slab thickness, The continuous one-way slab shown below is ...

The continuous one-way slab shown below is loaded with a uniform service live load of 80 psf, and a superimposed dead load of 40 psf. Assume the beam width is 16" and use f'c = 5 k

Stone, Explain briefly physical classifications of stone

Explain briefly physical classifications of stone

Three key types of reinforcement used in pre stressing, Question-What are t...

Question-What are three key types of r einforcement used in pre stressing ?   Answer- (i) Spalling reinforcement - Spalling stresses are established behind loaded

Simply supported steel frame help, I need some help sizing a rectangular pl...

I need some help sizing a rectangular plate that will distribute my load to the simply supported beams below.

What is the meaning of untensioned reinforcement, Supplementary or Untensi...

Supplementary or Untensioned Reinforcement It is that reinforcement, provided in prestressed concrete member, which is not provided in a stretched condition like tendons.

Soil in road construction, Soil in Road Construction: Road Embankme...

Soil in Road Construction: Road Embankment and Sub-grade Soil is mainly used as the material for constructing a road embankment. The road embankment supports the road

Determine the coefficient of compressibility, A saturated clay layer 4 m th...

A saturated clay layer 4 m thick is located 6 m below GL. The void ratio of the clay is 1.0. When a raft foundation is located at 2 m below GL, the stresses at the top and bottom o

Recognize the losses of prestress, Recognize the losses of prestress Re...

Recognize the losses of prestress Recognising the losses of prestress which take place after the prestressing OF concrete structural elements, it is to be appreciated that pres

Explain precedence relationships - construction management, Explain the Pre...

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd