engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

Define the reservoirs - hydraulic system, Define the Reservoirs - Hydraulic...

Define the Reservoirs - Hydraulic System Typically designed for multiple functions - clean water supply, creating recreational opportunities and flood protection. Reservoirs ar

Concrete cracking, Attached information shows construction details of a wat...

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped

Explain about noise absorptive materials, Q. Explain about Noise absorptive...

Q. Explain about Noise absorptive materials? The fundamental mechanism of noise absorptive material is to change the acoustic energy into heat energy. Amount of heat produced i

State the location and spacing of borings, Location and spacing of borings ...

Location and spacing of borings The location, spacing of geophysical profiles, soundings and borings should be such that,  you will be in a position to accurately predict the

Bleeding test for grout – an essential requirement, Q. Bleeding test for gr...

Q. Bleeding test for grout – an essential requirement? Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial st

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Timber, What is exogenous tree?

What is exogenous tree?

State the total load which the raft can support, A raft, 8 m × 24 m, is fou...

A raft, 8 m × 24 m, is founded at a depth of 4 m in sand with a value of N = 20 up to great depth. Illustrate the total load which the raft can support? What will be the total c

Shear and tensile strength, What is the difference between shear and tensil...

What is the difference between shear and tensile strength? Ans) Tensile Strength for a Bolt is explained by applying a Force along it long axis. Shear Strength for a Bolt is exp

Define the pre-tensioned concrete construction, Define the pre-tensioned co...

Define the pre-tensioned concrete construction We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd