engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

Water absorption test - tests on stones, Water Absorption Test: In t...

Water Absorption Test: In this test cube specimen weighing approximate 50 grams are prepared and the test is carried out in the steps following: 1.    Note down the weigh

Installation of band drains, Question For drained reclamation, what wil...

Question For drained reclamation, what will significance of smear zone bring by installation of band drains ? Answer Throughout installation of band drains, smear zon

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

General requirement for civil engineering, Question General requirement for...

Question General requirement for Civil Engineering Works in 1992 Edition, Clause 15.09 details that tying wires for strengthening adjacent to and above Class F4 and F5 closes must

Determine the coefficient of compressibility, A saturated clay layer 4 m th...

A saturated clay layer 4 m thick is located 6 m below GL. The void ratio of the clay is 1.0. When a raft foundation is located at 2 m below GL, the stresses at the top and bottom o

Deflection of beam, a simply supported beam with concentric load

a simply supported beam with concentric load

Define project scheduling - types of methods, Define Project Scheduling - T...

Define Project Scheduling - Types of Methods Project Scheduling - Distinction between the Major Types of Schedule Diagrams Precedence Diagrams (PDM)   a) Activ

Granite tiles for construction material, Q. Granite Tiles for construction ...

Q. Granite Tiles for construction material? At every important station for public urinals granite may be used as wall cladding drain and foot rest material. The water sinks at

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd