engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

What do you mean by manhole loss, Q. What do you mean by Manhole loss? ...

Q. What do you mean by Manhole loss? Manholes are provided in locations where there are changes in direction, size and gradient of gravity pipelines. Generally practice for str

Digit of cells for concrete box girder bridges, Question How does an engine...

Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o

Loss of camber in steel girders, Steel triangulated (open web) girders are ...

Steel triangulated (open web) girders are provided with camber to compensate for deflection under load. Out of the total design camber, the part corresponding to dead load is calle

Characteristic strength of concrete, In addition to its own weight, the bea...

In addition to its own weight, the beam in Figure is to carry a uniformly distributed live load of 12 kN/m. Figure 1 also shows the cross-sectional details of the beam. Design a

Building Technology, which IS code give details about Strength of Brick?

which IS code give details about Strength of Brick?

State average increase of pressure in the clay stratum, A building was to b...

A building was to be constructed on a clay stratum. Preliminary analysis showed a settlement of 60 mm in 6 years and an ultimate settlement of 250 mm. The average enhance of pressu

Explain plate jig, Explain Plate jig 1) The major parts of this jig is ...

Explain Plate jig 1) The major parts of this jig is plate from which it takes its name other necessary parts and drill bush and locating pins. 2) Plate jigs are general for

Explain the departure of a line - transportation, Explain the Departure of ...

Explain the Departure of a line - Transportation Departure of a line is the distance that the line extends in an east or west direction. A line that runs towards east has a pos

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

Explain the analysis of singly reinforced rectangular beams, Explain the An...

Explain the Analysis of Singly Reinforced Rectangular Beams: 1. Determine the area of steel reinforcement, As. Multiply the number of bars by the area of each bar. 2. Calcul

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd