engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

Theory of elasticity and plasticity, derivation for strain energy stored in...

derivation for strain energy stored in a body due to torsion

Define the finish-to-start dependency, Sheet rock cannot be installed in th...

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

Define deferred maintenance- underwater inspection of bridge, Define Deferr...

Define Deferred maintenance - underwater inspection of bridge? Many problems of the substructure can be traced to lack of any maintenance in time, which again can be due to lac

Simply supported beam, draw the shear force and bending moments of a beam

draw the shear force and bending moments of a beam

Stairs, what are the basic reqiureents for stairs. explain the basic proced...

what are the basic reqiureents for stairs. explain the basic procedures for stair construction

Precast concrete jacking pipes, Question While precast concrete jackin...

Question While precast concrete jacking pipes , from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons? Answer Grout h

Estimate Bridge Pier Concrete, Takeoff the 3 elements for the following bri...

Takeoff the 3 elements for the following bridge pier components: 1. Pier Footing, 2. Pier Column, 3. Pier Cap (Top). • Misc Items to include Shear Key. • Misc Items to exclude Reba

Show the application of concrete crash barriers, Q. Show the application of...

Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl

Calculate the annual cost of alum - coagulation, Incoming water contains 2....

Incoming water contains 2.5 mg/L as a substance of natural alkalinity (HCO 3 - ). The flow rate is 9.5 ML/day). (a) What feed rate is required if the alum dose is 7 mg/L and

Design of steel structure, design acolumn spice for column sections SC 250 ...

design acolumn spice for column sections SC 250 and SC 220 carrying a load of 500 KN

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd