engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

Aslar masonry, different types of ashlar masonry

different types of ashlar masonry

Functions components of a typical expansion joint, Question What are the fu...

Question What are the functions components of a typical expansion joint ? Answer In a characteristic expansion joint, it normally contains following mechanism-joint sealant, jo

Energy absorbed in heeling during vessel berthing, Q. Energy absorbed in he...

Q. Energy absorbed in heeling during vessel berthing? When a vessel   berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of

Determine the coordinate for point r, For the project work points (x,y) sho...

For the project work points (x,y) shown in the figure the bearing of point R is due West. The coordinate for point R is most nearly:    Solution: Determine the length o

Building, What quantity of cement will be needed to lay 2000 blocks of 9 in...

What quantity of cement will be needed to lay 2000 blocks of 9 inches using a mortar ratio of 1:6 with a thickness of 25mm in-between blocks.

What do by diaphragm wall, Q. What do by Diaphragm wall? For the constr...

Q. What do by Diaphragm wall? For the construction of diaphragm walls adjacent to buildings, former experience showed that excess slurry head above groundwater level had to be

Explain national priorities list (npl) - hazardous waste, Explain National ...

Explain National Priorities List (NPL) - Also known as superfund list - Identify sites which appear to present a significant risk to public health or the environment (Throug

Determine the preliminary settlement analysis, Preliminary settlement analy...

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stra

Vitrification, what is this process?whats its procedure?need some case stud...

what is this process?whats its procedure?need some case studies

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd