engineering economics, Civil Engineering

Assignment Help:
Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#

Related Discussions:- engineering economics

Desirable characteristics of a pavement, Desirable Characteristics of a Pav...

Desirable Characteristics of a Pavement: In order to fulfill the above function, the pavement has to have the following desirable properties : (a) It should be structurall

Gts bench mark, Gts bench mark in thane district maharashtra

Gts bench mark in thane district maharashtra

Function of prime coat in bituminous pavement, Q. Function of prime coat in...

Q. Function of prime coat in bituminous pavement? The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the pre

State about the prestressing steel, State about the Prestressing Steel ...

State about the Prestressing Steel For prestressed concrete members, the high-tensile steel, used generally, consists of wires, bars or strands. The high tensile strength of s

Open channel, design of irrigation channel permissible velocity table

design of irrigation channel permissible velocity table

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Conducting triaxial test, Question In conducting triaxial test to deter...

Question In conducting triaxial test to determine shear strengths for soil samples, what consolidation pressures should be specified? Answer It appears that the sele

Haley''s formula in pile driving, Question What is major difference bet...

Question What is major difference between "hammer efficiency" and "coefficient of restitution" at what time using Haley's formula in pile driving?   Answer Hammer ef

How to calculate the total loss of prestress, How to calculate the total lo...

How to calculate the total loss of prestress As a general guide, it may be taken that total loss of prestress may be in the range of 20 to 25 percent of the initial prestress,

Contour interpolation, given A,B,C,and D are four plotted points at 2 centi...

given A,B,C,and D are four plotted points at 2 centimeter apart and their ground reduced levels are 57.5 meter 63.2 meter 68.2 meter and 59.2 respectively.it is required to draw co

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd