Edge piles take up more loads than central piles, Civil Engineering

Assignment Help:

Edge piles take up more loads than central piles in rigid cap

Because of the effect of interaction of individual piles, central piles tend to settle more than the edge piles when the pile cap is under a uniform load. For the pile cap to be rigid, local deformation of central piles would not take place. In its place, stiff pile cap would transfer the loads from central piles and redistribute them to the outer piles. Consequently raking piles at the edge take up a higher fraction of the total loads and are subjected to higher axial and bending loads in case the pile cap is stiff. In the extreme case, side piles can take up as much as about two to three times the loads in the central piles and this can lead to the failure of these raking edge piles.

There are numerous choices regarding the design to tackle the uneven distribution of loads. The first one includes the lengthening of side piles to stabilize the piles under high loads. Though the increased length of outer piles tends to attract more loads and this seems not to be a good solution. Other way out is to lengthen the central piles aiming at getting more loads and this evens out the load distribution among the piles. 

1914_Edge piles take up more loads than central piles.png

Fig: Stress bulb effect on load distribution in piles


Related Discussions:- Edge piles take up more loads than central piles

Determine the concept of resultant force at a section, Resultant force at a...

Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw

What is the station at point b, What is the station at Point B? SO...

What is the station at Point B? SOLUTION 3 Station at Point A = Sta 22+45  Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273'  = Sta 32+73

Segmentation, how can we increase revenue to raise on fortune 500 list?

how can we increase revenue to raise on fortune 500 list?

Determine the total stopping sight distance in feet, Determine the total St...

Determine the total Stopping Sight Distance in feet A motorist is travelling down a 6% grade at 65 mph and needs to stop because of a crash scene.  Assuming a 2.0 sec PRT and 1

What are the long spam bridge girders, What are the long spam bridge girder...

What are the long spam bridge girders The pre-tensioned construction finds more use and application in the construction of those structural concrete members which are of small

About distomat, what is distomat? functipns &properties

what is distomat? functipns &properties

Estimate Bridge Pier Concrete, Takeoff the 3 elements for the following bri...

Takeoff the 3 elements for the following bridge pier components: 1. Pier Footing, 2. Pier Column, 3. Pier Cap (Top). • Misc Items to include Shear Key. • Misc Items to exclude Reba

Calculate the invert elevation of the sewer pipe, 1. The center line elevat...

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly: 2. A design engineer c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd