Edge piles take up more loads than central piles, Civil Engineering

Assignment Help:

Edge piles take up more loads than central piles in rigid cap

Because of the effect of interaction of individual piles, central piles tend to settle more than the edge piles when the pile cap is under a uniform load. For the pile cap to be rigid, local deformation of central piles would not take place. In its place, stiff pile cap would transfer the loads from central piles and redistribute them to the outer piles. Consequently raking piles at the edge take up a higher fraction of the total loads and are subjected to higher axial and bending loads in case the pile cap is stiff. In the extreme case, side piles can take up as much as about two to three times the loads in the central piles and this can lead to the failure of these raking edge piles.

There are numerous choices regarding the design to tackle the uneven distribution of loads. The first one includes the lengthening of side piles to stabilize the piles under high loads. Though the increased length of outer piles tends to attract more loads and this seems not to be a good solution. Other way out is to lengthen the central piles aiming at getting more loads and this evens out the load distribution among the piles. 

1914_Edge piles take up more loads than central piles.png

Fig: Stress bulb effect on load distribution in piles


Related Discussions:- Edge piles take up more loads than central piles

What is meant by normally consolidated clay stratum, Determine what is mean...

Determine what is meant by normally consolidated clay stratum and over-consolidated clay stratum. Draw typical results of consolidation test data to a suitable plot relating the vo

Joints in concrete pavements, Joints in Concrete Pavements: Concrete ...

Joints in Concrete Pavements: Concrete pavements in India are of the jointed plain (unreinforced type). The following types of joints are needed in them : (a) Transverse C

Rebound hammer.., rebound hammer working mechanism with detailed specificat...

rebound hammer working mechanism with detailed specifications of the images

Example of foundation depth and arrangement, Example of Foundation depth an...

Example of Foundation depth and arrangement: For example, if the maximum discharge of a river is 1000 cu m per sec, and the silt factor is 0.60, the maximum scour depth is :

Shear stress, Shear stress distribution in circular section

Shear stress distribution in circular section

Concrete, Determine the quantity of materials required per batch and probab...

Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Strength of materials, Didtribution of shear stree over a triangular sectio...

Didtribution of shear stree over a triangular section

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd