Economic Order Quantity:
Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.
Solution
d' in above example is
d = 500 /250 = 2 and lead time is 12 days.
From the equation,
R = d'L + z σL = 2 (12) + z (20)
Since, in this case z is 1.64. Substituting this value of z, we achieved
R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units
This illustrated that when the stock on hand gets down to 56 units, order 100 more.
Find the maximum shear stress - stepped circular bar: A stepped circular bar ABC 4 m long fixed at one of the end 'A' is subjected to a torque of 10 kN-m. If the portion AB is
Describe the basic concept of descriptive interface Descriptive interfaces are the window to other CAD systems, to the master databases or to the manufacturing activities. The
(a) Following consideration were recorder during a test on a single cylinder oil engine : Bore = 300 mm; speed =300 r.p.r.; stroke = 450 mm; net break load = 1.5KN;
Calculate for spring amount of load carried: The table below gives specific of a compound spring consisting of two co-axial close-coiled springs. If the spring is subjected to
What is alternating quantity?
Develop a computer program for the “Gear Transmission Systems” with consideration that each gear designer will have a different view as to what the most important design factors ar
A heating section consists of a 10 in diameter duct which houses a 8 kW electric resistance heater. Air enters the heating section at 14.7 psia 40oF, and 35 percent relative humidi
I have a project due in 20 hours and I need help please.
i want to analysis and test using fluent ansys
Q. Design Temporary Storage? It is sometimes acceptable to store drums temporarily on spill containment pallets. Each pallet should be capable of capturing the contents of at l
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd