Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Explain the 3-2-1 principle of location, Explain the 3-2-1 Principle of Loc...

Explain the 3-2-1 Principle of Location A work piece can be positively located by means of 6 pins so positioned that collectively they restrict the work piece in nine of it

Steam mass capacity, I have 5000 kg boiler capacity. In flow of 1 m3 gas fl...

I have 5000 kg boiler capacity. In flow of 1 m3 gas flow how much steam I can produce

Rails - flat footed rail, Rails: Rails are the part of the Permanent ...

Rails: Rails are the part of the Permanent Way on which the wheels of the train travel. The rails also maintain the gauge separation. Rails have to possess the following d

Isothermal transformation, Isothermal Transformation: Austenite is no...

Isothermal Transformation: Austenite is not normally converted in martensite instantly but the procedure continues for some time. Various steels take various time for full tr

Tributary lateral load, Tributary lateral load:   The question is on a f...

Tributary lateral load:   The question is on a fictitious 1965 building in Albany, NY. It was designed using the 1964 State Building Construction Code, in which Allowable Stress

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Explain milling fixture, Explain Milling Fixture? A milling fixture...

Explain Milling Fixture? A milling fixture is a work holding device which is firmly clamped to the table of milling machine. It holds the work piece in correct position as

Define boot strap air evaporative system, Define the following : (a) Boo...

Define the following : (a) Boot Strap Air Evaporative System (b) Simple VCR System (c) Advantage and disadvantage of VCR system over Air Refrigeration System (d) Reduce

Calculate the angle of heel, a) Derive a mathematical expression for stabil...

a) Derive a mathematical expression for stability of an automobile while accelarating in a curved path? b) A motorcycle and its rider together have a mass of 250Kg and their cen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd