Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Does the selected system meet the requirements, Does the selected system me...

Does the selected system meet the requirements of the application (building purging, make-up air, filtration, ventilation)? Is the system suitable for the intended building usag

Design of a filament winding machine, How can I achieve a back and forth mo...

How can I achieve a back and forth movement of carriage system. How can I reverse the motor to go back and forth.

Vibration, A bump/impact test is a simple technique used to determine a str...

A bump/impact test is a simple technique used to determine a structure’s natural frequency. Sketch a typical time wave response curve of such a test, then label the impact point an

Closed system - thermodynamics system, Closed System: The system tha...

Closed System: The system that can exchange energy with the surrounding but not the mass. The quantity of matter hence remains fixed. And the system can be described as cont

Determine the rate of heat removal - mechanics, Determine the rate of heat ...

Determine the rate of heat removal: Carbon dioxide passing through heat exchanger at rate of 100kg/hr is cooled down from  800 0 C to 50 0 C . Write down the steady flo

What is polymers, Q. What is polymers? The term "polymer" is derived fr...

Q. What is polymers? The term "polymer" is derived from the two Greek words: poly, meaning "many", and meros meaning "parts" or "units". Thus polymers are composed of a large n

Design study, how to produce a design that meets the specification given: B...

how to produce a design that meets the specification given: Beam Dimensions W, H and T, where H=2W and T=W/20 • Bolt Size D1 • Side Plate thickness T2 and width W2 • Cradle Plat

Evaluate the stress in the bolt, (a) A steel bolt 650 mm 2 cross-sectional...

(a) A steel bolt 650 mm 2 cross-sectional area passes centrally through a copper tube to 1200mm 2 cross-sectional area. The tube is 500mm long and closed by rigid washers, which

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd