Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Economic Order Quantity:
Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.
Solution
d' in above example is
d = 500 /250 = 2 and lead time is 12 days.
From the equation,
R = d'L + z σL = 2 (12) + z (20)
Since, in this case z is 1.64. Substituting this value of z, we achieved
R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units
This illustrated that when the stock on hand gets down to 56 units, order 100 more.
can a swimming pool that is full be cracked or lifted by hydrostatic pressure?
Q. Describe about Water disposal system? Disposal water from the Evaporator Package is cooled down to 50°C by the Disposal Cooler and is sent to Disposal Water Tank(s). Disp
A combined cycle plant is designed to develop 200MW power. The air is obtained by the compressor at 300K and 1 bar pressure. The maximum temperature of the gas turbine cycle is lim
Priority Rules A main concern rule is an algorithm that evaluates a priority number PN j for all operation j which enters the queue in front of a station (processing, cell, wo
Force required to start the roller: A roller shown in the figure given below is of mass 150Kg. What force T is required to start the roller over block A ? Sol.: Let
Q. Process of polymerization? The process of linking together of monomers, that is, of obtaining macromolecules is called "polymerization". It can be achieved by one of the two
diference between thermal and thermodynamic equallibrim
#question.want settle down where sheet metal engineers are required.
Calculate the feed in Drilling Operation Calculate the feed in m/min if a drill makes 200 revolutions per minute and penetrates to a distance of 3 mm per revolution. Solut
Tolerance Analysis This discusses the importance of assigning tolerances to the dimensions. Tolerance analysis is the process of assigning suitable tolerances. Proper assignme
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd