Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Resultant of non coplanar concurrent force system, Resultant of Non coplana...

Resultant of Non coplanar concurrent force system: How do you find resultant of Non coplanar concurrent force system? Sol.: The resultant of non concurrent force system

First law of thermodynamics, common formula for first law of thermodynamics...

common formula for first law of thermodynamics #Minimum 100 words accepted#

Low lube oil pressure security in API612 , What type of low lube oil securi...

What type of low lube oil security recommended for API612 steam turbines.(Electronic/Mechanical). Please give refrences

Determine the length of arc, Data given for gear problem T P = 30 TG = ...

Data given for gear problem T P = 30 TG = 80 φ = 20o m = 12 mm Addendum = 10 mm then determine the length of path of contact, length of Arc of contact and contact Ratio.

Hazardous areas classification, Hazardous Areas are formally ranked as bein...

Hazardous Areas are formally ranked as being a designated hazardous area using the relevant regional or country standards that are directly applicable to the plant design under con

What is value engineering, Value engineering & Value analysis VA may b...

Value engineering & Value analysis VA may be defined as looking at an existing product or a product already in production to see if changes in design or process can reduce prod

Predictive control algorithms, Predictive Control Algorithms Escaping S...

Predictive Control Algorithms Escaping Scheduling Errors via Partial Look-ahead Since previously mentioned above, the heuristic priority rules that are normally utilized in

Find the magnitude and position of maximum bending moment, A simply support...

A simply supported beam of length 5m takes a uniformly increasing load of 800 N/m at one end to 1600 N/m at the other end. Draw the shear force and the Bending moment diagrams for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade