Economic Order Quantity:
Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.
Solution
d' in above example is
d = 500 /250 = 2 and lead time is 12 days.
From the equation,
R = d'L + z σL = 2 (12) + z (20)
Since, in this case z is 1.64. Substituting this value of z, we achieved
R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units
This illustrated that when the stock on hand gets down to 56 units, order 100 more.
Ad
Describe productivity. How do we calculate the productivity? Enumerate various factors effecting the productivity. Define various ways for the improvement of productivity.
Copper-Lead Alloys Copper-lead alloys, having a large percentage of lead have determined a considerable employ as bearing material lately. Straight, copper-lead alloys of such
EXPLOSIVE WELDING I CLADDING In this process, two pieces of metal are impacted together at an extremely high velocity of impact achieved by the detonation of an explosive cha
aframe of punching machine and its varios dimentions. if it has force of85kN determine others
Show continuity equation in cylindrical coordinates. Also list the assumptions made. A fluid flow is given by V = xy 2 i - 2yz 2 j - (zy 2 - 2z 3 /3) k Determine acceleration
Distribution of shearing stresses on l--sections and miscellaneous sections
COMPETENCY STATEMENT: In this programme, every learner shall be assessed on a continuous basis for his/her knowledge and skills during the programme duration. Learners' competenc
Find the magnitude of force: Q: The two parallel forces are acting at point A and B respectively is equivalent to force of 100 N acting downwards at point C and coupl
Capacity Planning: This unit defined different ways to measure capacity, set up maximum capacity, and calculate capacity utilization. The long-term and short-term strategies t
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd