Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Explain about structural design of combined footing, Explain about structur...

Explain about structural design of combined footing. Structural Design of Combined Footing The rectangular and trapezoidal combined footings are designed assuming uniform so

Neutral layer and neutral axis, Neutra l Layer and Neutral Axis In the...

Neutra l Layer and Neutral Axis In the beam or cantilever, there is one layer which retains the original length of it even after bending. So in this layer tensile stress and c

Describe mould surface coating, Describe Mould Surface Coating? Mould...

Describe Mould Surface Coating? Mould surfaces are coated (after the pattern is drawn out) with certain materials possessing high refractoriness. It eliminates the poss

Give shear force and bending moment diagrams, A simply supported beam ABC w...

A simply supported beam ABC with supports at A and B , 6m apart and with an overhang BC 2 metres long takes uniformly distributed load of 1.5 KN/metre length over the entair length

Determine the flow rate - material balances, 1. A continuous steady-state p...

1. A continuous steady-state process involving components A, B, and C is shown below, along with the known process information a) On the flowchart, assign variables for the unkn

ESSENTIALS OF PROJECT MANAGEMENT, Ask qu1. A small maintenance project cons...

Ask qu1. A small maintenance project consists of the following 10 jobs, whose precedence relationships are identified by their node numbers: JOB NODE NUMBERS ESTIMATED DURATION (DA

Compound BArs, three vertical, parallel straight rods, each 2.6m in length ...

three vertical, parallel straight rods, each 2.6m in length have their upper ends firmly secured and their lower supporting a rigid horizontal bar with a weight of 8KN, which cause

Probability, Airlines like to overbook their flights (this is a vibrant are...

Airlines like to overbook their flights (this is a vibrant area of research called yield management). It is estimated that 10% of the people who book their flight do not show up. H

Find out load carried and compressive stress - steel bar, Find out load car...

Find out load carried and compressive stress: The concrete column 300mm x 300mm in section can be reinforced by 10 longitudinal 20mm diameter round steel bars. The column car

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd