Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Nitrides-silicides and sulfides, Nitrides, Silicides and Sulfides Nitr...

Nitrides, Silicides and Sulfides Nitrides contain very high melting point but initiate to oxidize at low temperature. They have poor resistance also to chemicals. Boron nitrid

Study and design of pattern, TO Study And Design Of Pattern A pattern i...

TO Study And Design Of Pattern A pattern is an element used for making cavities in the mould, into which molten metal is poured to produce a casting. It is not an exact replica

Calculate the maximum bending moment, A shaft is supported on bearings A an...

A shaft is supported on bearings A and B, 800 mm between centres. A 20° straight tooth spur gear having 600 mm pitch diameter, is located 200 mm to the right of the left hand beari

Corporate level - safety organization, Corporate level - Safety Organizatio...

Corporate level - Safety Organization This is a corporate level and there should be a company director which is engaged in formulating safety policies at corporate level. The

Strength of material, Draw complete shear and moment diagrams for a 3...

Draw complete shear and moment diagrams for a 3 m long cantilever beam having a uniform distributed load of 2 kN/m along its length.

Physical properties of materials, why is physical properties of materials i...

why is physical properties of materials important in design and for industrial application?

Discover the fixing torques set up at the ends of the shaft, Discover the f...

Discover the fixing torques set up at the ends of the shaft: A solid shaft 6.5 m long is securely fixed at each of the end. A torque of 91 Nm is applied to the shaft at a sect

Two stroke engine - thermodynamics, T w o Stroke Engine In the two st...

T w o Stroke Engine In the two stroke engine, instead of valves ports are given, these are opened and closed by moving piston. Through inlet port, the mixture of air and fuel

The continue dimension command-autocad, The Continue Dimension Command ...

The Continue Dimension Command You can use the Continue command to add a string of dimensions. In the illustration above the "36mm" dimension has been continued from the "64mm"

Marshalling yard, Marshalling Yard: Function The marshalling ...

Marshalling Yard: Function The marshalling yard is a facility where goods wagons are sorted out for being dispatched to different stations. After being sorted out, th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd