Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Design and sketch a knuckle joint to transmit a tensile load, Give a genera...

Give a generalized definition of factor of safety. Illustrate the factors responsible for Un-certainities in design necessitating a suitable factor of safety. How is ‘factor of saf

General resource models, General Resource Models In  computer  control...

General Resource Models In  computer  controlled scheduling,    material,  machine handling  equipment,  tooling  and  buffer  space  should  be comprised. The explicit consid

Evaluate maximum stress, Show that for a flat circular steel plate subjecte...

Show that for a flat circular steel plate subjected to uniform pressure on one surface, the maximum stress when the periphery is freely supported is 1.65 times that when the periph

What could be the characteristics of tool materials, (a) What could be the ...

(a) What could be the characteristics of tool materials. (b) Describe several tool materials with their composition.

Constituents of seam welding, Constituents of seam welding The essentia...

Constituents of seam welding The essential elements of a seam welding machine are: Main frame containing welding transformer and tap switch. Welding head consisting o

Simply supported beam - shear force diagram, Simply supported beam - Shear ...

Simply supported beam - Shear Force diagram: A simply supported beam of length 8 m is subjected to a consistently varying load from zero at centre to 3 t/m at both of ends. Dr

Calculate the spindle speed in milling operation, Calculate the Spindle Spe...

Calculate the Spindle Speed in Milling Operation Calculate the spindle speed (N) if a copper job is to be milled by  (a) stellite cutter  (b) cemented carbide cutter.

Need of alternate conceptual system design, What do you mean by Management ...

What do you mean by Management Information System (MIS)? What are its advantages ? Also give the qualities of an ideal MIS. What is the basic need of alternate conceptual system

Disadvantages of two stroke engine, Disadvantages of two stroke engine: ...

Disadvantages of two stroke engine: The following are some of the disadvantages of two stroke engine when compared with four stroke engine: 1. As firing takes place in ever

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd