Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

#strength of materials., derivation of elongation of bar due to its self we...

derivation of elongation of bar due to its self weight

Throttle free play adjustment of motor cycle, Throttle Free Play Adjustmen:...

Throttle Free Play Adjustmen: A smooth operation of the throttle ensures proper acceleration of the vehicle according to the requirement of the rider. If the throttle cable is kin

Injection molding, finishing operation of telephone outer body after inject...

finishing operation of telephone outer body after injection molding

Pmi testing of alloy materials, Q. Show PMI testing of alloy materials? ...

Q. Show PMI testing of alloy materials? Suppliers and Construction Subcontractors are required to verify or conduct PMI testing of alloy materials that they procure and use and

Assumptions made in deriving torsional formulas, Assumptions made in derivi...

Assumptions made in deriving torsional formulas: What are assumptions made in deriving torsional formulas?                                           Sol.: The torsion

Molding sand , which are the different types of molding sands?explain each

which are the different types of molding sands?explain each

Show hazard assessment of plant operation, Q. Show Hazard assessment of pla...

Q. Show Hazard assessment of plant operation? Using the hazard assessment of each plant operation will help establish the layout or orientation of process units within the plan

Order sequences and order release, Order Sequences and Order Release Fo...

Order Sequences and Order Release For this system, sequences of orders for particular parts (batch size 1) are produced in the following way: for each machine, here is, for eac

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd