Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Objectives-computerized scheduling and control manufacturing, Objectives ...

Objectives After studying this section, you should be familiarized about: The typical job shop scheduling problem, Characteristics of computer controlled scheduling,

What is value engineering, Value engineering & Value analysis VA may b...

Value engineering & Value analysis VA may be defined as looking at an existing product or a product already in production to see if changes in design or process can reduce prod

Force required to start the roller, Force required to start the roller: ...

Force required to start the roller: A roller shown in the figure given below is of mass 150Kg. What force T is required to start the roller over block A ? Sol.: Let

Mechanical design, 1. Produce the SW parts for the lugs, connector and tub...

1. Produce the SW parts for the lugs, connector and tubes. Produce an assembly to FIT at the designated points. 2. Create your own, individual, blank, customised drawing te

Explain different types of frames, (a) Explain different types of frames. C...

(a) Explain different types of frames. Compare their merits and demerits. Diagram and illustrate a frameless construction. (b) Illustration briefly the constructional features o

AOC, The objective of the project is to protect damage of the DC motors. If...

The objective of the project is to protect damage of the DC motors. If the motor is not working it will be shown with red light, if working normally then green and if working at a

Draw bending moment diagram for the beam, Draw bending moment diagram for t...

Draw bending moment diagram for the beam: A cantilever beam carries a uniformly distributed load of 2 t/m over the total length of 6 m and point loads of 5 t, 3 t, 7 t & 2 t a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd