Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Applications and disadvantages of electro chemical machining, Applications ...

Applications and Disadvantages of Electro Chemical Machining Disadvantage of Electro Chemical Machining 1. The tools are more difficult to design. 2. Initial cost is hi

Binomial distribution, Binomial distribution: Let X follow a binomial ...

Binomial distribution: Let X follow a binomial distribution with parameters n = 4 and p = 0.5. Tabulate P ( ¦X - μ¦ ≥ k ) and σ 2 /k 2 for k = 1,2,3,4,5 and verify that Cheby

Explain the information phase of radial drilling machine, Information Phase...

Information Phase: Step: To secure all and complete information and gather facts and from best sources.   Our project is selected based on the current problem face by the

What do you mean by filler metals, Q. What do you mean by Filler metals? ...

Q. What do you mean by Filler metals? Use filler metal that is similar in chemistry, corrosion resistance, and mechanical properties of the base metal being welded. Filler m

Diesel cycle, wath is diesel cycle with diagram

wath is diesel cycle with diagram

Explain roughness width and roughness width cut off, Explain Roughness widt...

Explain Roughness width and Roughness width cut off? Roughness width: - Roughness width is the distance parallel to the normal surface between successive peaks or ridges whic

Creep - flat footed rail, Creep: Creep of rails is the forward moveme...

Creep: Creep of rails is the forward movement of rails in the direction of dominant traffic over a period of time. Creep is undesirable because it disturbs the gauge of the t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd