Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Management of financial requirements , Management of Financial Requirements...

Management of Financial Requirements:  To start an own workshop or any business you need monetary support. You need to ensure availability of the required money including working

Calculate number of cycles to fracture, Calculate number of cycles to fract...

Calculate number of cycles to fracture: If the plastic deformation is taken into consideration calculate number of cycles to fracture in above Example. Solution Δ K I

Develop-implement method to identify numerically equivalent, For example, i...

For example, if one were provided with the set [3 1 3 -4 -6], the resulting answers would be [3 1 -4], [3 1 -4], an [3 3 -6], as these are the three sets of three values which sum

Determine in brief about the residual soils, Determine in brief about the R...

Determine in brief about the Residual soils Residual soils are generally very complex and varied. They are the products of in-situ disintegration of rocks and weathering. The g

Explain roughness width and roughness width cut off, Explain Roughness widt...

Explain Roughness width and Roughness width cut off? Roughness width: - Roughness width is the distance parallel to the normal surface between successive peaks or ridges whic

Calculation of seismic response loads, Q. Calculation of seismic response l...

Q. Calculation of seismic response loads? The seismic design requirements and the specification of criteria variables for the calculation of seismic response loads for the desi

Ventilation fan belt assembly, The aim of this assignment is for the studen...

The aim of this assignment is for the student to use the information, data and analysis techniques presented during lectures to design a belt drive transmission for a ventilation f

What are advantages and limitations of job evaluation, a) Describe producti...

a) Describe productivity. Give comparison of production and productivity. b) Write down characteristics of batch production. c) What are advantages and limitations of job eva

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd