Economic Order Quantity:
Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.
Solution
d' in above example is
d = 500 /250 = 2 and lead time is 12 days.
From the equation,
R = d'L + z σL = 2 (12) + z (20)
Since, in this case z is 1.64. Substituting this value of z, we achieved
R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units
This illustrated that when the stock on hand gets down to 56 units, order 100 more.
Advantages and disadvantages of solid fuels
Calculate the Spindle Speed in Milling Operation Calculate the spindle speed (N) if a copper job is to be milled by (a) stellite cutter (b) cemented carbide cutter.
How ca I make an opc & fpc chart
A steel plate with dimension shown in sketch (a) below is subjected to P = 150 kN tensile force and M= 300 N-m bending moment. The plate is made of AISI 1080 steel. A hole is to be
The National Aeronautics and Space Administration (NASA) studies the physiological effects of large accelerations on astronauts. Some of these studies use a machine known as a cent
3. How to illustrate the meaning of control system in control and automation system? 4. How to illustrate the major role of CPU in a PLC and what is the major role of CPU? 5. How
Determine the point of contraflexure: Draw the shear force & bending moment diagram for 10 m span overhanging beam along overhanging part of 4 m subjected to a system of loads
how does a sachet packaging work?
Standard for the specific standard technical areas These norms are based on previously described models. Typical categories of these norms are: (a) drafting, which describe
HOW TO PREPARE A DRAWING IN FIRST ANGLE PROJECTION AND THIRD ANGLE PROJECTION AND WHAT IS THEIR BASIC PRINCIPLE AND WE DO NOT MAKE DRAWING IN 2ND ANGLE PROJECTION AND 4TH ANGLE PRO
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd