Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

How can you test hardness of the prepared mould, Q. How can you test hardne...

Q. How can you test hardness of the prepared mould? Hardness test: The hardness of the prepared mould surface is tested to check the ramming density of the sand. The instrume

Thermal properties-ceramics-refractory and abrasive material, Thermal Prope...

Thermal Properties Each solid expand on heating and convention on cooling. The thermal expansion of solids is due to basic structure whether atoms occupy mean position on a fi

Order holons , This type of holon is mainly concerned along wit...

This type of holon is mainly concerned along with carrying out the work in a fine and correct way at correct time.

hammers and mallet-tool and equipment , Hammer/Mallet: Hammer is used to ...

Hammer/Mallet: Hammer is used to strike a job to bring it in shape or otherwise. It is made of carbon steel. The wooden handle does not allow the shock to hand but handles made in

Scraper launchers and receivers, Q. Scraper Launchers and Receivers? Sc...

Q. Scraper Launchers and Receivers? Scraper launchers and receivers associated with the pipelines shall be located in open, well-ventilated areas with the opening directed away

Frames, Introduction and conclusion on frames

Introduction and conclusion on frames

Construction of railway line, Construction of Railway Line: Earthwo...

Construction of Railway Line: Earthwork Earthwork in embankment is made up of soil from nearby borrowpits. The soil is deposited in layers of 25 cm and compacted at o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd