Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Determine the centroidal moment of inertia, Determine the centroidal moment...

Determine the centroidal moment of inertia: Determine the centroidal moment of inertia of a thin flat disc shown in Figure which is having a mass m kg. By using the parallel a

Service industry growth , SERVICE INDUSTRY GROWTH: The service industry is...

SERVICE INDUSTRY GROWTH: The service industry is growing very fast in today's world market scenario. In Indian context, we can see the impact of service sector growth upon (GDP) g

Determine the ratio between moment and load, Determine the ratio between mo...

Determine the ratio between moment and load: Any close coiled helical spring of circular section extends 1 mm while subjected to an axial load of W and then given an angular r

Calculation of material removal rate, Calculation of Material Removal Rate ...

Calculation of Material Removal Rate MRR = (W i - W f ) × 1000/ 7.8 × T .......................................... (1) W i = Initial weight of work piece W f = Final w

Principal stress and principal plane, Use the graphics and the equation to ...

Use the graphics and the equation to define the term principal stress and principal planes.

Wet h2s corrosion, There is risk of wet H 2 S corrosion in all emulsion and...

There is risk of wet H 2 S corrosion in all emulsion and gas lines from the Inlet Separator up to and including the Treater. Full compliance to NACE is highly recommended to contro

Plot plan alignment, Plot Plan Alignment Generally the process units w...

Plot Plan Alignment Generally the process units will be positioned in process flow order, with common utility blocks positioned to provide economical and effective services. P

#title.If your requirement is for a sensor suitable for a he, Ask question ...

Ask question #Minimum 100 words acceptedIf your requirement is for a sensor suitable for a heavy industrial application, with a linear characteristic, working in temperatures up to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd