Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Machine design, The connecting rod of a four stroke cycle Diesel engine is ...

The connecting rod of a four stroke cycle Diesel engine is of circular section and of length 550 mm. The diameter and stroke of the cylinder are 150 mm and 240 mm respectively. The

Calculate the primary voltage and real power measurements, Question: A ...

Question: A 7.2kVA single phase 50Hz, 480Vrms: 240Vrms transformer can be modelled using the primary referred approximate equivalent circuit shown in Figure 1 below. Fi

Boiler, Working, specification construction of Lancashire boiler

Working, specification construction of Lancashire boiler

Determine wheel diameters at the pitch circle of blades, A pelton wheel wor...

A pelton wheel works at the foot of a dam because of which the head available at the nozzle is 220m. the nozzle diameter is 20 c.m. and coefficient of speed 0.98. The wheel operate

Ordinate dimensions-autocad, Ordinate Dimensions Ordinate dimensions ar...

Ordinate Dimensions Ordinate dimensions are not really a dimensions at all in that they did not indicate a measurement aur dimensions. Rather they annotate known co-ordinate po

Longitudinal stress in the plate section through the rivets, A steam boiler...

A steam boiler, 3 m in diameter, is made of 25 mm thick mild steel plates. The efficiency of longitudinal riveted joint is 88% and that of circumferential riveted joint is 70%. Cal

Stone slab culverts with abutments, Stone Slab Culverts with Abutments and ...

Stone Slab Culverts with Abutments and Piers: Where good quality stone slabs are available like granite slabs, they can be used for superstructure of culverts, with suitable

Calculate the diameter of the single pipe, a) Three pipes of lengths 800m, ...

a) Three pipes of lengths 800m, 400m, 500m and of diameter 500mm, 400mm and 300mm respectively are connected in series. Pipes are to be removed by a single pipe of length 1700m. Ca

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd