Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Calculate the maximum stress, Determine the analytical solution for the max...

Determine the analytical solution for the maximum stress in the member shown. Submit screen shots that show the shape of the elements that result with a global element size of 0.15

New rule with local one step ahead prediction: wls rule, New Rule with Loca...

New Rule with Local One Step Ahead Prediction: WLS Rule Along with an observation to improve the performance measure of the system, a dynamic posteriori rule, the WLS that is

Evaluate the throat diameter of choke, (a) Illustrate why a rich mixture is...

(a) Illustrate why a rich mixture is required for the following (i) idling (ii) sudden acceleration (iii) Maximum power (b) A simple jet carburetor is required to supply 5Kg

Find out the wave retarders in tandem, Wave Retarders in Tandem Write th...

Wave Retarders in Tandem Write the Jones matrices for the following retarders: (a) A π/2 wave retarder with the fast axis along the x direction. (b) A π wave retarder with

Show the geometric similarity, Q. Show the Geometric Similarity? When m...

Q. Show the Geometric Similarity? When model is required to provide an aid merely for visualisation, scaler reproduction of form is sufficient which is termed Geometric Similar

Predictive control algorithms, Predictive Control Algorithms Escaping S...

Predictive Control Algorithms Escaping Scheduling Errors via Partial Look-ahead Since previously mentioned above, the heuristic priority rules that are normally utilized in

Define power metallurgy, Power Metallurgy- The more appropriate name shoul...

Power Metallurgy- The more appropriate name should be "Particulate Processing Methods". Here the particles of various sizes of metals, ceramics, polymers and glass etc, are presse

Show conceptual layout of plant, Q. Show Conceptual Layout of plant ? D...

Q. Show Conceptual Layout of plant ? During the Evaluate phase of a project, the early concept design considers broad information of the expected installation, and its basic cr

Writing of a welding procedure specification (wps), Writing of a Welding Pr...

Writing of a Welding Procedure specification (WPS ) A typical working procedure specification is written with all the factors of production in mind. Both experience and latest t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd