Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Air conditioning systems., an air conditioning system is to take place in a...

an air conditioning system is to take place in an outdoor air at 10 degrees celcius and 30% 0f relative humidity at a steady rate of 45 m^3/min and to condition it to 25 degrees ce

Calculate the heat supplied from the outer surface, Consider laminar flow i...

Consider laminar flow in a circular tubewith a fully developed velocity profile.Let the heat be added at a constant rate along the tube from  x+ =0  to  x+ =0.10 . Thereafter ,let

Determine the reactions at supported end, A steel dia 10 mm passes through ...

A steel dia 10 mm passes through a brass tube of internal dia 15mm and external dia is 25 mm. The bolt is tightened by a nut. The length of tube is reduced by 1.5mm and the length

GOVERNOR, IN CASE OF WILSON HARTNELL GOVERNOR THERE TWO MAIN SPRINGS AND TH...

IN CASE OF WILSON HARTNELL GOVERNOR THERE TWO MAIN SPRINGS AND THERE ARE ONE AUXILIARY SPRING. AND NATURE OF SPRINGS ARE TENSION ALWAYS HOW IT CAN POSSIBLE? WHEN SLEEVE WILL MOVE D

Schedule evaluation, Schedule Evaluation Each continuations of a partia...

Schedule Evaluation Each continuations of a partial schedule that are produced in step 1 are ranked as per to their respective cost function. This cost function might be dissim

Locomotive boiler, advantages and disadvantages of locomotive boiler

advantages and disadvantages of locomotive boiler

Loosening a part with multiple fasteners services tips, Loosening a Part wi...

Loosening a Part with Multiple Fasteners: Loosening a part with multiple fasteners should be done from the outside to inside in a criss-cross pattern, loosening the small fastener

Evaluate the point of contraflexure, Evaluate the point of contraflexure: ...

Evaluate the point of contraflexure: An overhanging beam of 15 m span is carrying a consistently distributed load of 1 kN/m over the length of 10 m at a distance 5 m from the

Friction, Friction: When a body moves or tends to move over the other ...

Friction: When a body moves or tends to move over the other body, a force opposing the motion develops at the contact surfaces. This force that opposes the movement or the ten

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd