Economic order quantity, Mechanical Engineering

Assignment Help:

Economic Order Quantity:

Assume an economic order quantity case where annual demand D = 500 units, economic order quantity Q = 100 units, the wanted probability of not stocking out P = 0.95, the standard deviation of demand during lead time σ L = 20 units, and Lead time L = 12 days. Discover the reorder point. Suppose that demand is over a 250 = workday year.

Solution

d' in above example is

 d = 500 /250 = 2   and lead time is 12 days.

 From the equation,

R = d'L + z σL  = 2 (12) + z (20)

Since, in this case z is 1.64. Substituting this value of z, we achieved

R = 2 (12) + 1.64 (20) = 24 + 32.8 = 56.8 units

This illustrated that when the stock on hand gets down to 56 units, order 100 more.


Related Discussions:- Economic order quantity

Functions of the piston ring , Functions of the Piston Ring To for...

Functions of the Piston Ring To form a seal for high pressure gases from the combustion chamber, against leak into the crankcase. To provide sufficient lubricating oi

Illustrate vacancy defect and screw dislocation, Illustrate vacancy defect ...

Illustrate vacancy defect and screw dislocation with diagram. Also show the induced nature of stress and stress by mean of diagram. Illustrate interstitial defect and edge disl

Different types of constrained motions, (a) Illustrate with examples the di...

(a) Illustrate with examples the different types of constrained motions ? (b) Describe in detail the following Mechanism : (i) Single slider crank chain mechanism (ii) Fou

Explain about vessel design loads, Q. Explain about Vessel Design Loads? ...

Q. Explain about Vessel Design Loads? Vessels and their supports shall be designed for all of the following conditions: • Erection: dead weight of fully dressed, empty vesse

Determine the relative maximum error, a) Round off the numbers 865250 amd 3...

a) Round off the numbers 865250 amd 37.46235 to four significant figures and compute Ea, Er, Ep in each case. b) IF u= 4 x 2 y 3 /z 4 and errors in x, y, z be 0.001, determine

Drill bit-tool and equipment , Drill Bit: This is a drilling tool used in ...

Drill Bit: This is a drilling tool used in drilling machines. The application of this tool is to make holes. Figure shows drill bit. Figure: Drill Bit

Illustrate types of pipe racks, Q. Illustrate types of pipe racks? The ...

Q. Illustrate types of pipe racks? The following types of pipe racks may be required: • Interconnecting pipe rack (elevated). • Unit pipe rack (elevated). • Pipe ra

Determine the change in diameter, Determine the change in diameter: A ...

Determine the change in diameter: A thin spherical shell of 1.8 m diameter is 10 mm thick. This is filled with a liquid so that the internal pressure is 1 N/mm 2 . Determine t

Hot and cold working, What is the difference between hot and cold working

What is the difference between hot and cold working

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd