Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the different kinds of lock modes, What are the different kinds of...

What are the different kinds of lock modes? There are three types of lock modes:- Shared lock Exclusive lock. Extended exclusive list.

What is meant by questionnaires, What is meant by Questionnaires This ...

What is meant by Questionnaires This includes sending out questionnaires to the work force or/and to customers to find out their views of existing system and to find out how.

Main problems with evaluation functions, Main problems with evaluation func...

Main problems with evaluation functions: Superlatively, evaluation functions should be quick calculates. Wherever is chance they take a long time to estimate, so after then le

Software engineering, what is modular system ? list important properties of...

what is modular system ? list important properties of modular system

Classified the vlsi technology, The VLSI technology is still developing. Mo...

The VLSI technology is still developing. More and more powerful microprocessors and more storage space now are being put in single chip. One question that we have still not conside

Explain resource dependence, Resource Dependence The parallelism betwee...

Resource Dependence The parallelism between instructions can also be affected because of the shared resources. If two instructions are occupying the same shared resource then i

List factors that determine the storage device performance, List the factor...

List the factors that determine the storage device performance. i.Access time ii.Cycle time iii.Transfer Rate.

Code segment , Specified  the code segment below and that n is the prob...

Specified  the code segment below and that n is the problem size, answer the following queries:   // . . . int sum = 0; if(x > 12){ for(int i = 1; i     for( i

What are the special unit related fields and methods, What are the special ...

What are the special unit related fields and methods?   The most significant method (in fact pseudo method) related to units is get_enclosing_unit().  The mostly used field in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd