Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How does the computer execute a program, Let's attempt to answer a fundamen...

Let's attempt to answer a fundamental question: 'How does the Computer execute a Program?' Let's describe this with the help of an example from higher level language domain. Pr

C programming, There is a pebble merchant. He sells the pebbles, that are u...

There is a pebble merchant. He sells the pebbles, that are used for shining the floor. His main duty is to take the length of the room’s sides. But he sometimes mistakes doing that

What are the events used for page headers and footers, What are the events ...

What are the events used for page headers and footers? The events TOP-OF-PAGE and END-OF-PAGE are used for pager headers and footers.

What are pooled tables, Normal 0 false false false EN-I...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Write a program that will solve a puzzle, You will write a program that wil...

You will write a program that will solve a version of the common newspaper puzzle \word search." In the puzzle you are given a grid lled with characters and a list of words to nd

Which TTL logic gate is used for wired anding, Which TTL logic gate is used...

Which TTL logic gate is used for wired ANDing ? Ans. Open collector output, TTL logic gate is used.

Features of an expert system, The heart of an experts systems is the ...

The heart of an experts systems is the powerful corups of knowledge that accumulates during system building. The knowledge is explicit and organized to simplify decisio

Problem specification - logic programs, Problem Specification : Hence ...

Problem Specification : Hence given the above context for "ILP" there we can state the learning problem as follows: that we are given a set of positive and a set of negative e

Difference between digital zoom and optical zoom, Question: (a) What ar...

Question: (a) What are effect presets and how can they be helpful? (b) Explain the difference between digital zoom and optical zoom. (c) Explain exposure in the context o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd