Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Difference b/w non-relocatable and relocatable programs, Differentiate bet...

Differentiate between non-relocatable and relocatable programs. A non-relocatable program is one which cannot be executed in any memory area other than the area starting at i

Define stack segment, Q. Define Stack segment ? 8086 Microprocessor su...

Q. Define Stack segment ? 8086 Microprocessor supports Word stack. Stack segment parameters tell the assembler to alert linker that this segment statement states the program s

Microcomputer - controlled breadmaking machine, Q. Microcomputer - Controll...

Q. Microcomputer - Controlled Breadmaking Machine? Figure shows a simplified schematic diagram of a microcomputer-controlled breadmaking machine. A microcomputer along with its

De morgan''s laws - artificial intelligence, De Morgan's Laws Continuin...

De Morgan's Laws Continuing with the relationship between  ∧  and  ∨ , we can also use De Morgan's Law to rearrange sentences involving negation in conjunction with these conne

Initial thought process, Initial thought process: Design a script which...

Initial thought process: Design a script which was simple and user friendly.  Integrate procedures/functions to extract data under the hood.  I focused on giving the user the o

Which translator perform macro expansion, Which translator perform macro ex...

Which translator perform macro expansion, is called? Ans. Macro pre-processor perform macro expansion.

What is sap luw or update transaction, What is SAP LUW or Update Transactio...

What is SAP LUW or Update Transaction? Update transaction (or "SAP LUW") This is a set of updates terminated by an ABAP/4 commit.  A SAP LUW may last much longer than a data

What is the role of a controller in an mvc application, The controller resp...

The controller responds to user interactions, with the application, by selecting the act method to implement and also selecting the view to render.

Determine the types of sensors, Determine the types of Sensors Differe...

Determine the types of Sensors Different types of sensors are used to give real time information to computers. Frequently, an analogue to digital converter (ADC) is required a

Physics, what is fresnel''s biprism?how it is used to determine wavelength ...

what is fresnel''s biprism?how it is used to determine wavelength of monochromatic source of light

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd