Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Appropriate problems for ann learning , Appropriate Problems for ANN learni...

Appropriate Problems for ANN learning - artificial intelligence-  As we did for decision trees, it is essential to know when ANNs are the correct representation scheme for the

Micrography technology, Micrography: Micrographic technology is an out...

Micrography: Micrographic technology is an outgrowth of photographic technology. Since this technology is being increasingly used to supplement computer systems, strong electr

Explain the working of any one of centralized spc, Explain the working of a...

Explain the working of any one of centralized SPC? Standby mode of operation is the easiest of dual processor configuration operations. Usually, one processor is active and

What is the session, What is the session.  Session is a collection of v...

What is the session.  Session is a collection of various groups of method. Every session is assigned to a single control terminal. This terminal is either a pseudo-device. or a

Explain optimization process of pipelining, Q. Explain Optimization process...

Q. Explain Optimization process of Pipelining ? RISC machines can use a very efficient pipeline scheme due to the regular and simple instructions. Similarly all other instructi

Bit pair recoding and 2’s complement, Explain bit pair recoding with an exa...

Explain bit pair recoding with an example? Ans: Bit pair recoding halves the maximum number of summands. Group the Booth-recoded multiplier bits in pairs and see the following

Sites are useful to the target audience members, Normal 0 false...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4 Select a range of a

C, "Super ASCII", if it contains the character frequency equal to their asc...

"Super ASCII", if it contains the character frequency equal to their ascii values. String will contain only lower case alphabets (''a''-''z'') and the ascii values will starts from

What are two reasons for using layered protocol, What are two reasons for u...

What are two reasons for using layered protocol? Layered protocol implies protocols used into each layer are the layer's own business that is they don't influence protocol of a

What is reification, What is reification? It is the promotion of someth...

What is reification? It is the promotion of something that is not an object into an object. Helpful method for Meta applications. It shifts the level of abstraction. Promote

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd