Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How can we create an outline around text, Place some text wherever. Then cl...

Place some text wherever. Then click "Create path from text" in the "Text tool option" window. Then use "Edit" -> "Stroke path" and choose the appropriate options in the following

History of e-commerce, In 1960: The purpose of e-commerce was to exchange t...

In 1960: The purpose of e-commerce was to exchange the electronic data. In 1970s: Electronic Fund Transfers or EFT was developed which considered as huge impact in the emerging

Define the actions a process take upon receiving a signal, Define the vario...

Define the various actions a process might be take upon receiving a signal? There are various actions a process might be take upon receiving a signal here are three different d

What is an activex interface, An ActiveX interface is a group of linked fun...

An ActiveX interface is a group of linked functions that are grouped together

Illustrate organisation of dram chip, Q. Illustrate Organisation of DRAM Ch...

Q. Illustrate Organisation of DRAM Chip? The given figure is a typical organisation of 16 mega bit DRAM. It displays a typical organisation of 2048 × 2048 × 4 bit DRAM chip. Me

Dbms, sketch a neat E-R diagram for hotel management system with real time ...

sketch a neat E-R diagram for hotel management system with real time example

Why are interrupt masks provided in any processor, Why are interrupt masks ...

Why are interrupt masks provided in any processor? Interrupt mask enable the higher priority devices comes first and there for lower priority devices comes last. The interrupt

Coa, Whats the use of coa

Whats the use of coa

Subtraction using 2's complement method of binary number, Subtraction of 00...

Subtraction of 0011.1001 - 0001.1110 using 2's complement method Ans. Firstly 1's complement of 0001.1110 is 1110.0001 and 2's complement is 1110.0010. If a last carry

Explain the importance of computer architecture, Explain the importance of ...

Explain the importance of Computer architecture Computer architecture courses cover application, organization, architecture, logic and transistor layers. However, four other la

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd