Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Write the benefits of broadcast model approach, a. Determine the non-functi...

a. Determine the non-functional system requirements that might be chosen for an application for a particular style and structures? b. Write the benefits of broadcast model appro

Device drivers in assembly, Device drivers are special programs installed b...

Device drivers are special programs installed by config.sys file to control installable devices.  So personal computers can be expanded at some future time by installation of new d

Determine about the verilog task, Determine about the Verilog Task - Ta...

Determine about the Verilog Task - Tasks are capable of enabling a function as well as enabling other versions of a Task. - Tasks also run with a zero simulation however the

Illustrate control and timing signals, Q. Illustrate control and timing sig...

Q. Illustrate control and timing signals? The requirement of I/O from different I/O devices by processor is quite unpredictable. In fact it relies on I/O needs of particular pr

What is the difference between vb6 and vb.net, What is the difference betwe...

What is the difference between VB6 and VB.Net? 1,Object-based Language 2,Doesnot support Threading 3 Not powerful Exception handling mechanism 4,Does not having suppor

What is analysis iteration, Analysis Iteration   To understand any prob...

Analysis Iteration   To understand any problem completely you have to repeat task which implies that analysis requires repetition. First, just get overview of problem, make a r

Explain activities of an operating system, List the major activities of an ...

List the major activities of an operating system with respect to memory management, secondary storage management and process management. Operating system is causes for followin

Disk operating system, Q. Disk operating system? The operating system (...

Q. Disk operating system? The operating system (OS) is the first program that should be loaded into the memory of your PC before you can use it for any application. You can st

What do you mean by work flow automation, What do you mean by work flow aut...

What do you mean by work flow automation? Work Flow Automation: Organizations frequently standardize processes across the association and encourage users to accept them. E

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd