Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Unencoded micro-instructions, Unencoded micro-instructions One bit ...

Unencoded micro-instructions One bit is required for each control signal; so number of bits needed in a micro-instruction is high. It represents a detailed hardware vi

Human intelligence in culture - artificial intelligence, Human intelligence...

Human intelligence in culture: Understand human intelligence in culture  "AI" can be seen as just the latest tool in the philosopher's toolbox for answering questions about

Differences between internal and external fragmentation, Explain the differ...

Explain the differences between Internal and external fragmentation. Internal and external fragmentation (1) While memory allocated to a process is a little larger than th

Display the map centered on the users location, Question: a) The follo...

Question: a) The following is a description of the navigation options in a mobile web site which provides public bus time slots for a city. It is an interesting service for m

Java, mine sweeper algorithm.

mine sweeper algorithm.

Programming, Write a procedure for each of the following: (i) To find the m...

Write a procedure for each of the following: (i) To find the maximum MAX of the values in the list. (ii) To find the average MEAN of the values in the list. (iii) To find the produ

Show the programmes for parallel systems, Q. Show the Programmes for Parall...

Q. Show the Programmes for Parallel Systems? Adding elements of an array using two processor      int sum, A[ n] ;  //shared variables

Computer graphics, raster scan and random display technology

raster scan and random display technology

What are conditional chain statement, What are conditional chain statement?...

What are conditional chain statement? ON CHAIN-INPUT similar to ON INPUT. The ABAP/4 module is called if any one of the fields in the chain having a value other than its in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd