Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is ram bus technology, What is RAM Bus technology? The key feature...

What is RAM Bus technology? The key feature of RAM bus technology is a fast signalling method used to transfer information among chips. Instead of using signals that have volta

Cognitive science applications, This branch of AI is concerned with incor...

This branch of AI is concerned with incorporating knowledge from varied disciplines such as biolog neurology psychology mathematics and several linked disciplines. It is typic

C, solution for oadovan string inc language

solution for oadovan string inc language

Emergence of computer network, Which Technologies of this age had tended to...

Which Technologies of this age had tended to the emergence of computer network? Ans: The technologies are Communication technology and Computer technology with the support of V

Classes of experts system, 1. The Consultant : A consultant is an experts...

1. The Consultant : A consultant is an experts person who possesses a high level of expertise in the area. He guide and educate the executives regarding establishing the e

Explain in brief about the insert operation, INSERT OPERATION The inser...

INSERT OPERATION The insert operation inserts a new value into a set of bits. This is done by first masking bits and then O ring them with required value. For illustration, sup

Explain input - output techniques, Q. Explain the Hard Disk Controller & F...

Q. Explain the Hard Disk Controller & Floppy Disk Controller with necessary diagrams. Q. Explain Input/Output Techniques (Data Transfer Techniques).

Explain the storage class extern, Explain The Storage Class extern The...

Explain The Storage Class extern The Storage Class extern : One method of transmitting information across blocks and functions is to use external variables. When a variable is

Differences b/w user level and kernel supported threads, What are the diffe...

What are the differences between user level threads and kernel supported threads? A thread, sometimes termed a lightweight process (LWP), is a fundamental unit of CPU utilizati

What is clearquest, Rational ClearQuest is a change-request management tool...

Rational ClearQuest is a change-request management tool that tracks and handles defects and change requests all through the development process. With ClearQuest, you can manage eac

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd