Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain about the term- video conferencing, Video Conferencing Video co...

Video Conferencing Video conferencing continues to grow in popularity. Why is this? Some reasons are listed below: - Communication links are now much faster thus sound quali

Illustrate the categories of micro computers, Illustrate the categories of ...

Illustrate the categories of micro computers Micro computers are usually categorized into desktop models and laptop models.  They are awfully limited in what they can do when c

Illustrate arithmetic shifts with example, Q. Illustrate Arithmetic shifts ...

Q. Illustrate Arithmetic shifts with example? Arithmetic shifts ARITHMETIC SHIFT LEFT and ARITHMETIC SHIFT RIGHT are same as LOGICAL SHIFT LEFT and LOGICAL SHIFT RIGHTexcept th

Instruction issue degree in superscalar processing, Q. Instruction Issue de...

Q. Instruction Issue degree in superscalar processing? The major concept in superscalar processing is how many instructions we are able to issue per cycle. If we are able to is

Write an algorithm for deadlock detection, Write an algorithm for deadlock ...

Write an algorithm for deadlock detection. An algorithm for deadlock detection: 1. Assume that Work and Finish be vectors of length m and n, correspondingly. Initialize:

How are the instructions executed and interpreted, Q. How are the instructi...

Q. How are the instructions executed and interpreted? All computers have a Unit which performs arithmetic and logical functions. This Unit is called as Arithmetic and Logic Uni

Arbitrary categorisation - learning decision trees, Arbitrary categorisatio...

Arbitrary categorisation - learning decision trees: Through visualising  a set of boxes with some balls in. There if all the balls were in a single box so this would be nicely

Communications and synchronization, Communications Parallel tasks class...

Communications Parallel tasks classically need to exchange data. There are many ways in which this can be accomplished, such as, through a network or shared memory bus. The act

What is dialog module, What is dialog Module? A dialog Module is a call...

What is dialog Module? A dialog Module is a callable sequence of screens that does not belong to a certain  transaction. Dialog modules have their module pools, and can be know

Basic need of random access memory, Q. Basic need of Random Access Memory? ...

Q. Basic need of Random Access Memory? Main memory is Random access memory. It is generally organised as words of fixed length. Length of a word is termed as word length. Every

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd