Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Internal conditioning, types of internal conditioning with explanations and...

types of internal conditioning with explanations and examples

Difference between static call and dynamic call, In the case of Static call...

In the case of Static call, the called program is a stand-alone program, it is an executable program. During run time we can call it in our called program. As about Dynamic call, t

Calculate width and height of the grid, Given a cell, we must determine its...

Given a cell, we must determine its neighbouring cells i.e. those with which it shares a wall. The cells with an x are the neighbours of the cell c. Write the function getneighbour

Explain the differences between logical and physical address, Explain the d...

Explain the differences between Logical and physical address space Logical Vs physical address space (1) An address produced by the CPU is commonly referred to like a logica

Unix , how to write algorithum for unix progam

how to write algorithum for unix progam

Define the register length, Q. Define the Register Length? Register Le...

Q. Define the Register Length? Register Length: Asignificant characteristic related to registers is length of a register. Generally the length of a register is dependent on it

Rsa encryption function- cryptography, The general method for constructing ...

The general method for constructing the parameters of the RSA cryptosystem can be described as follows: Select two primes p and q Let N = pq and determine ∅ (N) = (p - 1

Explain the working of hundred-line exchange, In a hundred-line exchange 24...

In a hundred-line exchange 24 two-motion selectors are used. Draw the schematic you suggest for this exchange and explain its working. How many simultaneous calls can be made durin

Where particular header ends & next item begins of ipv6, As IPV6 contain mu...

As IPV6 contain multiple headers, how does it know where particular header ends and next item begins? Several headers types contain fixed size. For illustration a base header h

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd