Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is a shift register, What is a Shift Register? Ans:  Shift R...

What is a Shift Register? Ans:  Shift Register: A register wherein data finds shifted towards left or right while clock pulses are applied is termed as a Shift Register.

Java, about java types

about java types

Control-centered virtual manufacturing, Control-Centered Virtual Manufactur...

Control-Centered Virtual Manufacturing This is the addition of simulations to control actual processes and models, permitting for seamless simulation for optimization throughou

Database, I got a graduate level database assignment which is due at Dec 8,...

I got a graduate level database assignment which is due at Dec 8, 11:59p.m. Can you finish it on time in high quality?

What do you mean by synchronization principles, In multiprocessing several ...

In multiprocessing several processors require to communicate with one another. So synchronisation is needed between them. The correctness and performance of parallel execution reli

Define the full form of ssl, Define the full form of SSL SSL has becom...

Define the full form of SSL SSL has become fundamental to the spread of Internet community, and commerce and trade over Internet. Over years, the spread of its use for an incr

Basic definition of program, Q. Basic defination of program? A program ...

Q. Basic defination of program? A program generally consists of a set of instructions and data specifying the solution of a particular problem. Programs (and data) expressed in

What is instruction cycle, What is Instruction Cycle The simplest model...

What is Instruction Cycle The simplest model of instruction processing can be of two steps. The CPU reads /fetches instructions (codes) from memory one at a time and executes i

Show the features of a typical floating-point representation, Q. Show the F...

Q. Show the Features of a typical floating-point representation? The features of a typical floating-point representation of 32 bits in above figure are: Left-most bit is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd