Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define the programmable logic devices (pld), Define the Programmable logic ...

Define the Programmable logic devices (PLD)? In the world of digital electronic systems there are three essential kinds of devices 1.memory, 2.microprocessors, and 3.logic. The

How does the computer execute a program, Let's attempt to answer a fundamen...

Let's attempt to answer a fundamental question: 'How does the Computer execute a Program?' Let's describe this with the help of an example from higher level language domain. Pr

Interrupts - computer architecture, Interrupts Interrupt-request lin...

Interrupts Interrupt-request line o   Interrupt-acknowledge signal o   Interrupt-request signal Interrupt-service routine o   May have no relationship t

Multiple assign statements targeting the same wire, What logic is inferred ...

What logic is inferred when there are multiple assign statements targeting the same wire? It's illegal to specify multiple assign statements to the same wire in a synthesizable

Explain technical reasons which made microsoft withdraw, Explain technical ...

Explain technical reasons which made Microsoft withdraw its support for VBA in Mac? Ans) The reasons which made Microsoft drop its carry to VBA are as follows, Microsoft visual

Explain the term- scan insertion, Explain the term- Scan Insertion Sca...

Explain the term- Scan Insertion Scan Insertion is completed by a tool and results in all (or most) of your design's flip-flops to be changed by special "Scan Flip-flops". Sca

Ring, Ring This is a easy linear array where the end nodes are connecte...

Ring This is a easy linear array where the end nodes are connected.  It is equivalent to a engage with wrap around connections. The data transmit in a ring is normally one dire

Give difference between assembler and compiler, Give difference between ass...

Give difference between assembler and compiler. Assembler: It is the translator for an assembly language of computer. An assembly language is a low-level programming language

Explain about microcomputers, Q. Explain about Microcomputers? Microco...

Q. Explain about Microcomputers? Microcomputers: A microcomputer's CPU is a microprocessor. They are characteristically used as single usercomputer though present day microco

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd