Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Describe the instruction set architecture, Q. Describe the instruction set ...

Q. Describe the instruction set architecture? The significant role of the Central Processing Unit (CPU) is to perform calculations, to coordinate all other hardware components,

Order in which filters get implemented, If we have multiple filters implet...

If we have multiple filters impleted, what is the order in which these filters get implemented?   Ans) 1. Authorization filters 2. Response filters 3. Action filters

What is a priority interrupt, What is a Priority Interrupt? A priority ...

What is a Priority Interrupt? A priority interrupt is an interrupt that establishes a priority over the various sources to determine which condition is to be serviced first whe

Dbms, documentation for dbms report

documentation for dbms report

What is monitoring-and-surveillance agents, Q. What is monitoring-and-surve...

Q. What is monitoring-and-surveillance agents? ANSWER: Monitoring-and-surveillance agents or predictive agents are intelligent agents that examine and report on equipment.

A digital signature, A digital signature is   encrypting information

A digital signature is   encrypting information

Main features of TCP, The main features of TCP are: Reliability: TCP...

The main features of TCP are: Reliability: TCP makes sure that any data sent by a sender arrives at destination as it was sent. There can't be any data loss or change in the

What is the significance of nonactionattribute, In general, all public proc...

In general, all public processes of a controller class are treated as action processes. If you require prevent this default behaviour, just decorate the public process with NonActi

Explain inheritance, Can you explain what inheritance is and an example of ...

Can you explain what inheritance is and an example of when you might use it? The process of deriving a new class from an existing class is known as Inheritance. The old class i

Can we delete a domain, Can you delete a domain, which is being used by dat...

Can you delete a domain, which is being used by data elements? No.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd