Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Persuasive communication , 1)   Discuss various types of persuasive communi...

1)   Discuss various types of persuasive communication you might be needed to write or present in your professional and personal life. 2)    Describe two ways to organize a resume

8086 microprocessor, In SDK – 86 kit 128KB SRAM and 64KB EPROM is provided ...

In SDK – 86 kit 128KB SRAM and 64KB EPROM is provided on system and provision for expansion of another 128KB SRAM is given. The on system SRAM address starts from 00000H and that

Convert logic circuit in a binary code, The logic circuit given below, conv...

The logic circuit given below, converts a binary code y 1 y 2 y 3 into Ans. Gray code is X1 = Y1,   X2 = Y1 XOR Y2  ,   X3 = Y1 XOR Y2 XOR Y3 For

Define a formal system, Q. Define a Formal System? A Formal System is o...

Q. Define a Formal System? A Formal System is one which is planned in advance and is used according to schedule. In this system procedures and policies are documented well in a

What is common type system, What is "Common Type System" (CTS)?  CTS e...

What is "Common Type System" (CTS)?  CTS explain all of the basic types that can be used in the .NET Framework and the operations performed on those type. All this time we hav

Determine the minimal sum of products for boolean expression, Determine the...

Determine the Minimal sum of products for the Boolean expression? Obtain the minimal sum of products for the Boolean expression f=(1,2,3,7,8,9,10,11,14,15) using Quine-McCluske

Find the physical address of instruction, Q. Find the Physical address of i...

Q. Find the Physical address of instruction? Value of Instruction Pointer and holding address of instruction = 1234h Value of code segment register (CS) = 448Ah Physical

Describe the advantages of java servlets over cgi interface, Describe the a...

Describe the advantages of JAVA servlets over CGI interface. The Advantage of Servlets Over "Tradi tional" CGI: Java servlets are extra efficient, easier to utilize more pow

Editor - tools necessary for assembly language programming, Q. Editor - Too...

Q. Editor - Tools necessary for assembly language programming? The editor is a program which allows the user to enter and modify as well as store a group of instructions or tex

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd