Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

State the concept of multiplicity, Multiplicity Multiplicity in an ass...

Multiplicity Multiplicity in an association specifies tells us about number of objects participate in a relationship. It decides the number of related objects. Multiplicity is

How video effects alters a video, Question : (a) What are the main aspe...

Question : (a) What are the main aspects that should be considered when dealing with green screen? (b) Explain clearly how these video effects alters a video using an illust

Problem context and specification, Problem Context and Specification : ...

Problem Context and Specification : However the development of Inductive Logic Programming has been heavily formal in mathematical in nature it means the major people in the f

How exceptions are handled in java, How exceptions are handled in java? ...

How exceptions are handled in java? Exception handing In Java: A java exception is an object which describes an exceptional condition which has occurred in a piece of code.

Write the game using writing functions, The year is 2199. For many generati...

The year is 2199. For many generations, the robotic Cyleth have faithfully served humanity. However, under the direction of the computerized superintelligence Skyweb, they have tur

What are the disadvantages of public key cryptography, What are the disadva...

What are the disadvantages of Public Key Cryptography? Disadvantages of Public Key Cryptography are as given below: a) It is used to encrypt a secret key that is used to e

Two ways in which one can retrieve data from tables, In general what are th...

In general what are the two ways in which one can retrieve data from tables? Using Select statements, Database Program.

Subtraction of 01100-00011 using 2's complement method, Subtraction of 0110...

Subtraction of 01100-00011 using 2's complement method Ans. Firstly 1's complement of 00011 is 11100 and 2's complement is 11100 + 1 = 11101. Thus If a last carry is

Functioning of registers, Functioning of registers: at any instance of time...

Functioning of registers: at any instance of time global registers and only one window of registers is visible and is addressable as if it were only set of registers. So for progra

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd