Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Pipelining - computer architecture, Pipelining - computer architecture: ...

Pipelining - computer architecture: The Pipeline Defined According to John Hayes "A pipeline processor consists of a sequence of processing circuits, called stages or

Formal analysis of visual elements, Formal Analysis: The second step o...

Formal Analysis: The second step of the art critiquing process often begins with an analysis of the artworks formal elements and how they are the organised. The formal elem

What is the demand of mobile application developers, Desktop based IT appli...

Desktop based IT application is present but the mobile is future. All the applications that were made to work only on counter top are being ported to mobile. In the coming 10 years

Why did my jdbc code throw a rollback sqlexception, Your JDBC code may thro...

Your JDBC code may throw the following exception: "The coordinator has rolled back the transaction.No further JDBC access is permitted within this transaction." The WebLogic

Assessing heuristic searches-artificial intelligence, Assessing Heuristic S...

Assessing Heuristic Searches Given a specific problem you want to create an agent to solve, there can be more than one way of specifying it as a search problem, more than one o

What is insert module and goal seek functions there in vba, Visual basic ap...

Visual basic applications have very rich and flexible applications but there is single limitation when using pointer function. Windows API has limited support for function pointers

Describe about frameset, Q. Describe about Frameset? Now make a master ...

Q. Describe about Frameset? Now make a master page in which you write below code. My Frame Page -- The Master Page

What is artificial intelligence language processing, Artificial intelligenc...

Artificial intelligence language processing (AILP) is a field of computer science and linguistics concerned with the interactions among computers and human (natural) languages; it

Explain about instruction register and flags, Q. Explain about Instruction ...

Q. Explain about Instruction Register and Flags? The Instruction Register: It comprises the operation code (opcode) and addressing mode bits of the instruction. It assists in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd