Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate the accumulator architecture, Accumulator Architecture: An accu...

Accumulator Architecture: An accumulator is anespecially designated register which supplies one instruction operand and receives result. Instructions in such machines are usually

What are different edi components and edi services, What are different EDI ...

What are different EDI components and EDI services? Different EDI components and EDI services are illustrated as: Three main components including services in EDI System are

What is the significance of the screen number ''0'', What is the significan...

What is the significance of the screen number '0'? In "calling mode", the special screen number 0 (LEAVE TO SCREEN 0) causes the system to jump back to the last call level.  Th

Illustration of disk formatting, Q. Illustration of disk formatting? An...

Q. Illustration of disk formatting? An illustration of disk formatting is displayed in Figure below. In this case every track comprises 30 fixed-length sectors of 600 bytes eac

Html 4.0 element, , an HTML 4.0 element supported by Netscape6 and MSIE, de...

, an HTML 4.0 element supported by Netscape6 and MSIE, defines a set of text which is associated with a specific form element. For illustration, code belo

How many precision resistors requires a weighted resistor, A weighted resis...

A weighted resistor digital to analog converter using N bits requires a total of ? Ans. Digital to analog converter, a weighted resistor using N bits needs a total of N precisi

How congestion is controlled in tcp, How congestion is controlled in TCP? ...

How congestion is controlled in TCP? One of the most significant aspects of TCP is a mechanism for congestion control. In main modern internets, extreme long delays or packet l

Define strategy procedure, Q. Define Strategy Procedure? The strategy p...

Q. Define Strategy Procedure? The strategy procedure is called when loaded into memory by DOS or whenever controlled device request service. The major purpose of the strategy i

What are the functions of dispatcher, What are the functions of dispatcher?...

What are the functions of dispatcher? There are four fuctions of dispatcher:- A)  Equal distribution of transaction load to the work processes.  B) Management of buffer a

What are the techniques of data collection, What are the techniques of Data...

What are the techniques of Data Collection It can be either automatic or manual. Manual techniques can include: -  Keypads/Keyboards to type in data -  touch screens to s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd