Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How atoms differ from the arrangement of atoms in a liquid, Q. How does the...

Q. How does the preparation of atoms in mainly solids differ from the arrangement of atoms in a liquid? Answer:- The arrangement of atoms in solids are diverse from those

What is locality of reference, What is locality of reference? Analysis ...

What is locality of reference? Analysis of program represents that many instructions ion localized areas of the program are implemented repeatedly during some time period, and

Where traffic intensity can be measured, Traffic Intensity can be measured ...

Traffic Intensity can be measured in (A)  Erlangs                                    (B) CCS (C)  CM                                         (D) All of the above Ans:

Illustrate does gas have density, Q. Illustrate does gas have density? ...

Q. Illustrate does gas have density? Answer:- Gas in addition to everything in the universe has density though some densities are not either too high or too low to be dete

Parallel computer architecture , Parallel Computer Architecture Intr...

Parallel Computer Architecture Introduction We have talked about the classification of parallel computers and their interconnection networks in that order in units 2 and

Source and destination are named the same, What happens if the both source ...

What happens if the both source and destination are named the same? Ans) The import operation present in MS Access does not overwrite or change any of the existing tables or obj

Explain about fundamental nature of a computer, Q. Explain about fundamenta...

Q. Explain about fundamental nature of a Computer? The fundamental nature of a Computer is as an information transformer. So a computer should be able to take input and process

What is home banking, Home Banking: E-commerce is used in Home Banking ...

Home Banking: E-commerce is used in Home Banking as single call or single click. Online banking (Internet banking) is a term used for performing transactions, payments etc. ove

User interface (ui), Design a easy (text-based/ graphical) UI for  your pr...

Design a easy (text-based/ graphical) UI for  your program.  The user should be encouraged for  parameter values for  the particular protocol simulation. For  example, the user sho

Define security protocols used for e-commerce applications, Define various ...

Define various security protocols used for e-commerce applications. The e-commerce systems of today are composed of very many components as like: a commerce server, client soft

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd