Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Constructor, what is meant by private copy constructor

what is meant by private copy constructor

When a network uses a star topology, A Network uses a star topology if? ...

A Network uses a star topology if? A Network utilizes a star topology if all computers attach to a single central point.

What is connection, An established communication session among a server and...

An established communication session among a server and a workstation.

C programming, Find out useless nonterminal symbols use c program.

Find out useless nonterminal symbols use c program.

External report cannot be called, When calling an external report the param...

When calling an external report the parameters or select-options specified in the external report cannot be called.

Which transistor is used in every cell of eprom, Floating gate Avalanche In...

Floating gate Avalanche Injection MOS (FAMOS) transistor is used in every cell of EPROM.

Conclusion - artificial intelligence , Conclusion - artificial intelligence...

Conclusion - artificial intelligence : If we can determine what the exactly state of the world will be after an agent's action, so we can say the environment is deterministic.

Illustrate the text area, specifies a form field where user can enter large...

specifies a form field where user can enter large amounts of text. In most respects, works like an field. It can have a name as well as a def

Mapping design principle, The following definition of mapping is adapted fr...

The following definition of mapping is adapted from the first edition of the Set Book: Mapping concerns the relationship between controls and their effects in the world. Nearly al

By which finders are connected, In step by step switching line finders are ...

In step by step switching line finders are connected to the (A) Calling subscriber.                   (B) Switching network. (C) Called subscriber.                    (

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd