Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Mips - computer architecture, MIPS - computer architecture: The MIPS ...

MIPS - computer architecture: The MIPS ISA, so far 3 instruction formats Fixed 32-bit instruction 3-operand, load-store architecture 32 general-purpose register

Multi-layer network architectures, Multi-Layer Network Architectures - Arti...

Multi-Layer Network Architectures - Artificial intelligence: Perceptrons have restricted scope in the type of concepts they may learn - they may just learn linearly separable f

Illustrate working of J-K flip-flop, Q. Illustrate working of J-K flip-flop...

Q. Illustrate working of J-K flip-flop? J-K flip-flop is also a modification of SR flip-flop since it has 2 inputs same as S and R and all possible inputs combinations are vali

Explain the violating basic security principles, Explain the violating basi...

Explain the violating basic security principles There are drawbacks to permitting users to access the Intranet as well as not permitting them. A simple consideration such as a

What features are needed to implement top down parsing, The features are ne...

The features are needed to implement top down parsing are? Ans. Source string marker, Prediction making mechanism and also matching and backtracking mechanism features are need

How to create user interfaces for lists, How to create user interfaces for ...

How to create user interfaces for lists? The R/3 system automatically, obtains a graphical user interface (GUI) for your lists that offers the basic functions for list process

Convert the following into pos form, Q. Convert the following into POS form...

Q. Convert the following into POS form 1.  (AB + C + DC)(AB + BC + D) 2.  WYZ + XYZ + W'X'Y + W'XYZ 3.  XY + XZ + X'YZ' 4.   (A+B'+C) (AB+AC') 5.   F(A,B,C,D)=M(0,3,

Documentation introduction, Documentation is done to give others with infor...

Documentation is done to give others with information and ease maintenance. The best documentation is done in the headers (function and scripts) and directly in the code. Any usefu

Variable-partition multiprogramming, Choose the descriptions below with the...

Choose the descriptions below with the most appropriate memory management scheme (A through D).  Solutions may be used once, more than once, or not at all. A.     Fixed-partitio

Explain about the postpurchase interaction briefly, Explain about the postp...

Explain about the postpurchase interaction briefly. Postpurchase Interaction: Customer support and service: The considerations at such can be explained by the followin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd