Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain cell spacing and cell padding, Q. Explain Cell Spacing and Cell Pad...

Q. Explain Cell Spacing and Cell Padding? Couple of attributes known as CELLSPACING and CELLPADDING. Both are part of tag. CELLPADDING is the amount of space between

Explain the term- cycle based simulator, Explain the term- Cycle Based Simu...

Explain the term- Cycle Based Simulator This is a Digital Logic Simulation method which eliminates unnecessary calculations to achieve huge performance gains in verifying Bool

Medical diagnosis program, Diagnosis: Medical diagnosis program bases on p...

Diagnosis: Medical diagnosis program bases on probabilistic analysis have been able to perform at the level of an expert physician tin several areas of medicine. Heckerman(1981)

Unit resolution, Unit Resolution: By assuming that we knew the sentenc...

Unit Resolution: By assuming that we knew the sentence as "Tony Blair is prime minister or may the moon is made of blue cheese", is true or we later found out that the moon is

Difference between non-relocatable self relocatable programs, Differentiate...

Differentiate between non-relocatable self relocatable programs. A non-relocatable program is one which cannot be executed in any memory area other than the area starting at

Explain about open system, Q. Explain about Open System? The 'Open Syst...

Q. Explain about Open System? The 'Open System' is a system within its environment. It receives input from environment as well as provides output to environment.  Illustrati

Isoquants, what are the types of isoquants

what are the types of isoquants

Dfa, design a dfa which accept all the string over a and b ending with ab o...

design a dfa which accept all the string over a and b ending with ab or ba

Illustrate the categories of micro computers, Illustrate the categories of ...

Illustrate the categories of micro computers Micro computers are usually categorized into desktop models and laptop models.  They are awfully limited in what they can do when c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd