Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Example of bitwise-and operator, Example of Bitwise-AND Operator In the...

Example of Bitwise-AND Operator In the following example, the bitwise-AND operator (&) compares the bits of two integers, nNumA and nNumB: // Example of the bitwise-AND oper

Explain about hexadecimal numbers system, Q. Explain about Hexadecimal Numb...

Q. Explain about Hexadecimal Numbers system? Hexadecimal system has 16 digits that are represented as 0,1,2,3,4,5,6,7,8,9,A,B,C,D,E,F. A number (F2) H is equivalent to

Recombination - canonical genetic algorithm, Recombination: Therefore...

Recombination: Therefore during the selection and mating process then the GA repeatedly lines up pairs of individuals for reproduction. Hence the next question is how to gener

.master-slave flip flop, JK, SR, D master FF 1)draw block diagram 2) combin...

JK, SR, D master FF 1)draw block diagram 2) combinational circuits using NOR & NAND gate thank you

What are the "field" and "chain" statements, What are the "field" and "chai...

What are the "field" and "chain" Statements? The FIELD and CHAIN flow logic statements let you Program your own checks. FIELD and CHAIN tell the system which fields you are ch

What is system software, What is system software? Give an example. It i...

What is system software? Give an example. It is a collection of program that are implemented as needed to perform functions such as I.  Receiving and interpreting user comma

Mac and llc, how can we improve the way LLC and MAC are used for LAN operat...

how can we improve the way LLC and MAC are used for LAN operation.?

What do you meant by an expert system, (a) What do you meant by an Expert S...

(a) What do you meant by an Expert System (ES) and explain briefly the essential differences between a Decision Support system and ES. (b) What are decision tables and what are

Why does dma have priority over the cpu, Why does DMA have priority over th...

Why does DMA have priority over the CPU when both request a memory transfer? The data transfer monitored by DMA controller which is called as DMA channel. The CPU is included o

What are digital signatures and its uses, What are Digital Signatures and i...

What are Digital Signatures and its uses? A digital signature is an electronic quite than a written signature which can be used through someone to authenticate the identity of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd