Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Polishing game, Byteland county is very famous for luminous jewels. Luminou...

Byteland county is very famous for luminous jewels. Luminous jewels are used in making beautiful necklaces. A necklace consists of various luminous jewels of particular colour. Nec

What are the major characteristics of a pipeline, What are the major charac...

What are the major characteristics of a pipeline? The major characteristics of a pipeline are: a) Pipelining cannot be executed on a single task, as it works by splitting mu

Give the syntax switch statement, Give the syntax  switch statements C...

Give the syntax  switch statements Consider the following example. This is a function which converts an integer into a vague description. It is useful where we are only concer

What are the rules of timescale directive, What are the Rules of Timescale ...

What are the Rules of Timescale directive Rules -  'Timescale directive, like all compiler directives, affects all modules compiled after directive,  whether  in  same  fi

Explain in detail about operating system, Explain in detail about Operating...

Explain in detail about Operating Systems (OS) Operating system (OS) is a program which after being initially loaded into computer by a boot program, manages all the other appl

What is the difference between wire and register, What is the difference be...

What is the difference between wire and reg Wire Wire is used for designing combinational logic, as we all know that this type of logic cannot store a value.  As  you  can

Write a bash-c shell script, Write a BASH/C shell script which takes a name...

Write a BASH/C shell script which takes a name of a directory as a command line argument, and prints unique login name of the users having files in that directory. Your code should

Write a c++ program to explain three specific classes, Make a base class ca...

Make a base class called figure that store the dimensions of several geometrical objects and compute their areas. Explain a function set_dim( ),a standard member  function and show

Difference between the physical drive and the logical drive., A physical dr...

A physical drive is drive the in which you can physically see in the computer system itself. That is the gadget itself. Logical drive is placed inside the physical drive and th

Explain characteristics of latch and flip-flop, Explain characteristics of ...

Explain characteristics of Latch and Flip-Flop. Latches are level-sensitive and transparent While the clock is high it passes input value to Output While the clock is l

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd