Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define the abstraction of OOA, Define the Abstraction of OOA Now, let ...

Define the Abstraction of OOA Now, let us see how objects can be seen as a problem, and find their associated data and their behaviour. You will notice that an object is an ab

Delete a user from a category, Execute the following functionality using Ja...

Execute the following functionality using Java & SQL with simple GUI interface: 1.  Insert/delete/update an XML document.  2.  Insert/delete/update a category.  3.  Alloca

Why we use debugger, Q. Why we use Debugger? Debugger is a program whic...

Q. Why we use Debugger? Debugger is a program which allows the user to test as well as debug the object file.  Theuser can use this program to perform subsequent functions.

Show encoding data options, Q. Show Encoding data options? PVM uses SUN...

Q. Show Encoding data options? PVM uses SUN's XDR library to make a machine independent data format if you request it. Settings for encoding option are:  PvmDataDefault: Use

What are the input for uml development, What are the Input for UML developm...

What are the Input for UML development UML is an attempt to standardize artefacts of analysis and design consisting of semantic models, diagrams and syntactic notations. The fi

Design principles, The usability and user experience goalsprovidet heintera...

The usability and user experience goalsprovidet heinteraction designer with high-level goals for the interactivep roduct. Thenextissueis how to design a product that satisfies thes

Cisc approach - cisc architecture, CISC Approach - CISC architecture: ...

CISC Approach - CISC architecture: The main goal of CISC architecture is to finish a task in as few lines of assembly as possible as. This is gain by building processor hardwa

In which page replacement policies balady’s anomaly occurs, In which page r...

In which page replacement policies Balady’s anomaly occurs? FIFO that is First in First Out.

Interrupts - computer architecture, Interrupts Interrupt-request lin...

Interrupts Interrupt-request line o   Interrupt-acknowledge signal o   Interrupt-request signal Interrupt-service routine o   May have no relationship t

Explain naming convention verification points, Explanation:- In functio...

Explanation:- In functional testing, you require to confirm that the objects in the application-under-test look and work as designed from build to build. To accomplish this, yo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd