Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain dos function call with one illustration, Explain DOS function call ...

Explain DOS function call with one illustration DOS function call In order to use DOS function calls, always place function number into register AH and load all other re

Convert ascii code to its bcd equivalent, Convert ASCII code to its BCD equ...

Convert ASCII code to its BCD equivalent. This can be achieved by simply replacing bits in upper four bits of byte by four zeros. For illustration the ASCII '1' is 32h = 0010B. By

What is the most common biometrics, What is the most common biometrics? ...

What is the most common biometrics? The most common biometrics is the given below: Face geometry (Photo): In this the computer takes the picture of your face and matches t

Define a technique of temporarily removing inactive program, is a technique...

is a technique of temporarily removing inactive programs from the memory of computer system? Swapping is a technique of temporarily eliminating inactive programs from the memor

State the benefits of encapsulation, State The Benefits of Encapsulation ...

State The Benefits of Encapsulation To hide the details of a class, you can declare that data or implementation in the private part of class so that other class clients will n

Explain the working of a 1-to-16 Demultiplexer, Using a suitable logic diag...

Using a suitable logic diagram explain the working of a 1-to-16 de multiplexer. Ans. 1-to-16 Demultiplexer Working: A demultiplexer obtains in data from one line and directs this

What is the efficient data structure used in rdbms, In RDBMS, what is the e...

In RDBMS, what is the efficient data structure used in the internal storage representation? B+ tree. Because in B+ tree, all the data is kept only in leaf nodes, that makes sea

Flowchart, how can we find compound interest through flowchart

how can we find compound interest through flowchart

Priority interrupt and synchronous bus, What is a Priority Interrupt? A...

What is a Priority Interrupt? Ans: A priority interrupt is a type of interrupt that establishes a priority over the many sources to determine which condition is to be serviced

Joint application development session leader, Q.Joint Application Developme...

Q.Joint Application Development session leader? JAD session leader: JAD leader organizes and runs the JAD. This person is trained in group management and facilitation as well

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd