Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Write a bash shell script, Write a BASH/C shell script which takes name of ...

Write a BASH/C shell script which takes name of one or more files as a command line argument, and prints the following information for each file: owner, number of words in the file

Risc architecture - computer architecture, RISC  architecture - computer a...

RISC  architecture - computer architecture: What is reduced regarding it? The answer of this question is that to make all instructions the equal length the number of bits that

What is cgi, CGI stands for Common Gateway Interface, and is a mechanism by...

CGI stands for Common Gateway Interface, and is a mechanism by which a browser is permitted to communicate with programs running on a server. If you look at every word in turn it m

Find the generating function, Find the generating function to denote the nu...

Find the generating function to denote the number of ways the sum 9 can be acquired while 2 distinguishable fair dice are tossed and the first shows an even number and the second s

Disadvantages of pipeline - computer architecture, Disadvantages of pipelin...

Disadvantages of pipeline: Pipeline architecture has 2 major disadvantages.  First is its complexity and second is the inability to constantly run the pipeline at full speed,

Binary, 8:1 Mux for a given function, f=S (0, 1,5,7,9, 13)..

8:1 Mux for a given function, f=S (0, 1,5,7,9, 13)..

Invariant of the class, What are the conditions that have to be met for a c...

What are the conditions that have to be met for a condition to be an invariant of the class? Ans) ? The condition should hold at the end of each constructor. ? The conditi

In what way the protection fault handler concludes, In what way the protect...

In what way the protection fault handler concludes? After finishing the implementation of the fault handler, it sets the change and protection bits and clears the copy on write

Define side tone is essential in telephone communication, A certain amount ...

A certain amount of side tone is essential in telephone communication. Ans: It is true that a specific amount of side tone is necessary in telephone communication.

Bernstein conditions for detection of parallelism, Bernstein Conditions for...

Bernstein Conditions for Detection of Parallelism For implementation of instructions or block of instructions in parallel, it should be guaranteed that the instructions are ind

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd