Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Virtual memory and organization of a cache memory, Described virtual memory...

Described virtual memory Ans: Data is to be stored in physical memory locations that have addresses different from those that specified by the program. The memory control circu

Determine the binary equivalent of hexadecimal FA, The binary equivalent of...

The binary equivalent of (FA) 16   is ? Ans. (FA) 16 = (11111010) 10

What is a PCI bus and discuss its aspects and usage, What is a PCI bus? Dis...

What is a PCI bus? Discuss its aspects and usage. Peripheral Component Interconnect (PCI): This bus was developed by Intel and introduced in 1993. It is geared specifically to

Show the foundation of ALU design, Q. Show the foundation of ALU design? ...

Q. Show the foundation of ALU design? The foundation of ALU design starts with micro-operation implementation. Thus let's first explain how bus can be used for Data transfer m

Illustrate decimal fixed point representation, Q. Illustrate Decimal Fixed ...

Q. Illustrate Decimal Fixed Point Representation? The point of this representation is to keep the number in decimal equivalent form and not binary as above. A decimal digit is

Colour management, There are three primary colours in pigments - Red, Yello...

There are three primary colours in pigments - Red, Yellow and Blue. There are two ways to produce more colours:   Physical Mixing: Physically mix colours to produce a new colour

Show SNMPs representation in ASN.1 syntax, An SNMP integer whose value is 2...

An SNMP integer whose value is 200 has to be transmitted. Show its representation in ASN.1 syntax. An ASN.1 transfer syntax describes how values of ASN.1 types are unambiguousl

Manipulate the presentation and attributes interactive list, How can you m...

How can you manipulate the presentation and attributes of interactive lists? ---Scrolling by Interactive Lists. ---Setting the Cursor from within the Program. ---Changing

What are the steps to design algorithm, What are the steps to design algori...

What are the steps to design algorithm? Formulate algorithm for each operation. Analysis specification tells what the operation does. The algorithm shows how it is done. The st

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd