Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain working of direct memory access, Q. Explain working of Direct Memor...

Q. Explain working of Direct Memory Access? In both programmed I/O and interrupt-driven processor is busy with executing input/output instructions and I/O transfer rate is limi

Artificial intelligence agents, Artificial Intelligence Agents: We int...

Artificial Intelligence Agents: We introduced what we'll be conversation about in Artificial Intelligence and why those things are necessary. This discussion is of course abou

C++, what is polymorphism

what is polymorphism

Illustrate working of synchronous counters, Q. Illustrate working of Synchr...

Q. Illustrate working of Synchronous Counters? The main drawback of ripple counter is delay in changing the value. How? To understand this let's take a case when state of rippl

Explain handle graphics in matlab, This is the MATLAB graphics system. It c...

This is the MATLAB graphics system. It contains high-level commands for two-dimensional and three-dimensional data visualization, image processing, animation, and presentation grap

How do you track down a transition by name, Question 1: a) How do you ...

Question 1: a) How do you track down a transition by name? b) Why Premiere Pro is considered a non-linear editor? c) Explain clearly the main problem that may arise wh

What do you mean by loader, Q. What do you mean by Loader? Loader is a ...

Q. What do you mean by Loader? Loader is a program that assigns absolute addresses to program. These addresses are produced by adding the address from where program is loaded i

Define memory address map, Define memory address map? Addressing of mem...

Define memory address map? Addressing of memory can be established by means of a table that specifies the memory address assigned to each chip. The tables, known as memory addr

Shared memory model, In the shared-memory programming model, tasks share a ...

In the shared-memory programming model, tasks share a common address space, which they read and write asynchronously. Several mechanisms such as locks / semaphores may be used to c

Pc configuration and troubleshooting, You have been asked to become the con...

You have been asked to become the consulting technician for MobTex, a local auto servicing centre. The general manager (Jo) realises that the IT system has evolved over time with l

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd