Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Translate sentence into predicate logic - ai, Translate the following sente...

Translate the following sentences into predicate logic, using identity (=). a. Everyone was drunk except John. b. Christine rides a bike, but everyone else drives a car. c

Explain about common addressing modes, Q. Explain about common addressing m...

Q. Explain about common addressing modes? Most of machines use a set of addressing modes. The following tree displays common addressing modes: Figure: Common Addres

Draw the logic circuit of Decimal to BCDencoder, What is an encoder? Draw t...

What is an encoder? Draw the logic circuit of Decimal to BCD encoder and explain its working. Ans. Encoder: It is a combinational logic circuit which converts alphanumeric ch

Describe the characteristics of mainframes, Problem 1 (a) List and desc...

Problem 1 (a) List and describe the characteristics of mainframes, minicomputers and microcomputers. (b) Briefly describe what is meant by electronic commerce and what b

Verilog, http://www.cse.psu.edu/~dheller/cmpen331/Homework/Homework4.htmlwo...

http://www.cse.psu.edu/~dheller/cmpen331/Homework/Homework4.htmlwords accepted#

Message passing programme development environment, In a multicomputer syste...

In a multicomputer system the computational load amid different processors should be balanced.  To pass information between different nodes message passing technique is used. The p

Algebra, Discrete Mathematics - (A?B)-(AnB)=(A-B)?(B-A) - prove by cases?? ...

Discrete Mathematics - (A?B)-(AnB)=(A-B)?(B-A) - prove by cases?? State which law you have used at each step. I''ve just started learning this, this semester .. and i havnt quite

Develop the website, In this part you are required to develop the website t...

In this part you are required to develop the website that you designed in Your written report must describe any changes that you make to theoriginal plan with justification.

Structured analysis and design approach, Q. Structured Analysis and Design ...

Q. Structured Analysis and Design Approach? The objective of structured system analysis and design is to reduce maintenance time as well as effort. Modeling is the act of drawi

Difference between property get, Set Value is ready to ActiveX Object from ...

Set Value is ready to ActiveX Object from the form. Let Value is retried to ActiveX Object from the form. Get- Assigns the value of an expression to a variable or property.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd