Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Expalin massively parallel system and scalability, Massively Parallel Syste...

Massively Parallel System Indicates to a "parallel computer system" involving a huge number of processors. The numbers in a huge number of processors keeps increasing and curre

Tcp connection , a) What command do you use to file all active and availabl...

a) What command do you use to file all active and available sockets? These should also contain UNIX domain sockets, which are primarily used for local connections.   b) What sta

Critical path analysis, Given the information provided in Table 1: ...

Given the information provided in Table 1: Prepare an Activity on the Node (AON) Network Diagram ( I recommend you  use MS Project or any drawing tool); Prepare

3D rotation, Magnify a triangle with vertices A = (0,0), B = (3,3) and C = ...

Magnify a triangle with vertices A = (0,0), B = (3,3) and C = (6,4) to twice its size in such a way that A remains in its original position.

Define rotational latency and disk bandwidth, Define rotational latency and...

Define rotational latency and disk bandwidth. Rotational latency is the additional time waiting for the disk to rotate the desired sector to the disk head. The disk bandwidth i

Exit command, Your shell must accept the exit command. This command will ...

Your shell must accept the exit command. This command will be in the form: e x i t When you encounter this command, your shell should terminate. Please note that when you

Define programmable logic array and programmable array logic, Define Progra...

Define Programmable Logic array & Programmable Array Logic? Combinational ckt is implemented with ROM Do not care conditions become an address input. PLA is alike to ROM. PLA d

Write the program to use arrays, In class SlotCollection, remove the fields...

In class SlotCollection, remove the fields slot1, slot2, slot3 and slot4 and replace them by an array of slots. Modify the rest of the program to work using this array. There is

What is meant by Wired-AND connection of digital ICs, What is meant by Wire...

What is meant by Wired-AND connection of digital ICs?                                                                                                               Ans: Wir

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd