Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Average enzyme activity , Activity of a some  enzyme was calculated  in ext...

Activity of a some  enzyme was calculated  in extracts from brain, heart and lung. In every  tissue,  the activity was calculated  various  times, giving the following results (in

Terms in propositional model, Terms in Propositional model: There in f...

Terms in Propositional model: There in first-order logic allows us to talking about properties of objects that the first job for our model (Δ, Θ) is to assign a meaning to the

Quiz help, which two class die class contain in computer programing.

which two class die class contain in computer programing.

Diffrence between RISC and CISC architecture, Q. Diffrence between RISC and...

Q. Diffrence between RISC and CISC architecture? CISCs provide better support for high-level languages since they include high-level language constructs such as CASE, CALL etc

Limitation identified in amdahls law, Q. Limitation identified in Amdahls l...

Q. Limitation identified in Amdahls law? There is one main limitation identified in Amdahl's law. As said by Amdahl's law workload or problem size is forever fixed as well as n

Desirable choice for the partitioning element in quick sort, A desirable ch...

A desirable choice for the partitioning element in quick sort is First element of the list.

Reprographic technologies, Reprography: Reprography, as a term, has ga...

Reprography: Reprography, as a term, has gained international recognition in 1963. It includes "photocopying , microcopying, duplicating and in-plant printing and is character

While using ftp what is wildcard expansion in file names, While using FTP w...

While using FTP what is wildcard expansion in file names? To make this easy for users to identify a set of file names, FTP permits a remote computer system to perform usual fil

For what purpose Karnaugh map is used, Karnaugh map is used for the purpose...

Karnaugh map is used for the purpose of ? Ans. Karnaugh map is used for, to minimize the terms in a Boolean expression.

Explain high level data link control, Explain High Level Data Link Control....

Explain High Level Data Link Control. HDLC - it is High Level Data Link Control: Protocol Overall explanation: Layer 2 of the OSI model is the data link layer. One of the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd