Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Computer organization, using one-address instructions,write a program to co...

using one-address instructions,write a program to compute X=A-BxC

Give the example of spreadsheet, Give the example of Spreadsheet By sel...

Give the example of Spreadsheet By selecting cell C1 and dragging the formula down to C5 the below formulae will be replicated in C2 to C5: (A2*B2), (A3*B3), (A4*B4) and (A5*B5

Implement simplified expression using nor gates only, Q. For function F(x,y...

Q. For function F(x,y,z) = ∑m (1,2,3,5,6) using TRUTH TABLE only 1. Find POS expression 2. Implement this simplified expression using two level OR-to-AND gate network 3. I

State in brief about virtual memory, What is Virtual memory The term v...

What is Virtual memory The term virtual memory signifies something that appears to be present though actually it is not. Virtual memory technique enables users to use more mem

Write a verilog code for synchronous and asynchronous reset, Write a Verilo...

Write a Verilog code for synchronous and asynchronous reset? Synchronous  reset, synchronous means clock dependent so reset must not be present in sensitivity disk eg: alway

Linq file extension, What is the LINQ file extension that interacts with Co...

What is the LINQ file extension that interacts with Code Behind objects. Ans) its .dbml

Script in multi user mode, What Component of LoadRunner would you use to pl...

What Component of LoadRunner would you use to play Back the script in multi user mode? Ans) The Controller component is used to playback the script in multi-user mode. This is c

Differentiate between synchronous and asynchronous i/o, Differentiate betwe...

Differentiate between synchronous and asynchronous input/output with the help of an example. The input-output operation is asynchronous input/output operation since after the s

Conversion of bcd number to binary using a procedure, Q. Conversion of BCD ...

Q. Conversion of BCD number to binary using a procedure? Conversion of BCD number to binary using a procedure. Algorithm for conversion procedure: Take a packed BCD digit

Determine about the term- voice synthesis, Voice synthesis Loud speakers ...

Voice synthesis Loud speakers and special software are used to output information in the form of sound to help blind and partially-sighted people; it also helps people who have d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd