Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What do you understand by scan codes, Q. What do you understand by Scan Cod...

Q. What do you understand by Scan Codes? A scan code is a code produced by a microprocessor in keyboard when a key is pressed and is unique to key struck. When this code is rec

Determine the o/p for JK flip flop with J=1 & K=0, For JK flip flop with J=...

For JK flip flop with J=1, K=0, the output after clock pulse will be ? Ans. The output will be 1 after clock pulse.

By which many computers are connected in geographical area, A large numbers...

A large numbers of computers in a wide geographical area can be efficiently connected using? A large numbers of computers in a broad geographical area can be efficiently linked

What is the vertical organizational structure, What is the Vertical Organiz...

What is the Vertical Organizational Structure? This is a traditional approach that is typified by a functional approach to work in that departments work onto tasks relevant to

Name the numerous household devices, Name the Numerous household devices ...

Name the Numerous household devices Numerous household devices now use microprocessors to control their different functions. The following is just a sample of common devices (d

What is data hazard in pipelining, What is data hazard in pipelining? What ...

What is data hazard in pipelining? What are the solutions? A data hazard is a situation in which  the pipeline is stalled due to the data to be operated on are delayed for some

How can you insert text in dreamweaver, Q. How can you insert text in dream...

Q. How can you insert text in dreamweaver? In Dreamweaver, you can type content directly into a layout cell, or you can cut and paste content from another document into a layou

What is python?, Python is an interpreter, interactive, object-oriented pro...

Python is an interpreter, interactive, object-oriented programming language. It is frequently compared to Tcl, P e r l, Scheme or Java. Python combines remarkable power with v

Explain about the e-commerce over extranets, Explain about the e-commerce o...

Explain about the e-commerce over extranets. Extranets are regarding “joining up” the supply chain-suppliers, distributors, resellers and customers are enabling business-to bus

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd