Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Gui status in a program from the object browser, Can we create a gui status...

Can we create a gui status in a program from the object browser? Yes.  You can make a GUI STATUS in a program using SET PF-STATUS.

What is critical section problem, What is critical section problem?  Co...

What is critical section problem?  Consider a system having of 'n' processes. Each process has segment of code known as a critical section, in which the process may be changing

Avoiding overfitting - decision tree learning , Avoiding Overfitting : ...

Avoiding Overfitting : However remember there that in the previous lecture, there is over fitting that common problem in machine learning. Furthermore details to decision tree

Illustrate some notations of object modeling notations, Illustrate some not...

Illustrate some notations of object modeling notations A classifier is a mechanism which describes behavioural and structural features. In UML significant classifiers are cla

Illustrate about probability of collision, Illustrate about probability of ...

Illustrate about probability of collision? Probability of collision: There is a triangle and on this let’s assume that there are three ants one on each corner and are free t

Write a cgi program that prints date and time, Write a CGI program that pri...

Write a CGI program that prints date and time at which it was run. #!/bin/sh # # CGI script that prints the date and time at which it was run # # Output the documen

Do we require an x server to run in batch mode for gimp, Yes, you have to h...

Yes, you have to have some form of X server (unless you're running Windows, of course). It requires an X server for image processing, and for font manipulation. Though, if you wish

What is called checking CRC in cyclic redundancy, In cyclic redundancy chec...

In cyclic redundancy checking CRC is the? Checking CRC, in cyclic redundancy is the remainder. Normal 0 false false false EN-IN X-NONE X-NONE

Classes of experts system, 1. The Consultant : A consultant is an experts...

1. The Consultant : A consultant is an experts person who possesses a high level of expertise in the area. He guide and educate the executives regarding establishing the e

Register organisation, The number and nature of registers is a major factor...

The number and nature of registers is a major factor which distinguishes among computers. For illustration, Intel Pentium has about 32 registers. A number of these registers are sp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd