Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Reduce minimum literals and derive their complements, Q. Reduce following t...

Q. Reduce following to minimum literals and derive their complements. 1. [(AB)'A][(AB)'B] 2. ABC(ABC' + AB'C + A'BC) 3. (A+C+D) (A+C+D') (A+C'+D)(A+D')

Name the modes of 8255 programmable peripheral interface, What are the diff...

What are the different modes in that 8255 Programmable Peripheral Interface (PPI) can operate?  24 I/O lines in 3-8-bit port groups - A, B, C A, B can be 8-bit input

What are kinds of models, What are kinds of models? Class model - Objec...

What are kinds of models? Class model - Objects in the system and their relationships. State model - Life history of the objects. Interaction model - Interactions between

Explain the term- variables, Explain the term- Variables - Variables ar...

Explain the term- Variables - Variables are used for local storage of data -  Variables are usually not available to multiple processes and components. -  Variables would

What is the length of function code at user-command, What is the length of ...

What is the length of function code at user-command? Every menu function, push button, or function key has an associated function code of length FOUR (for example, FREE), which

Explain parallel overhead, Parallel Overhead The amount of time needed ...

Parallel Overhead The amount of time needed to organize parallel tasks, as opposed to undertaking useful work. Parallel overhead may comprise factors like:   1) Task start-u

Operations from events, Operations from events During analysis, events...

Operations from events During analysis, events which are sent to target objects. An operation on these object are presented as labels on transitions and should not be explicit

Information distribution, INFORMATION DISTRIBUTION: The organization and m...

INFORMATION DISTRIBUTION: The organization and management of any institution, be it an isolated lab or a large site with many labs, requires that information is managed. Methods o

Illustrate memory read operation, Q. Illustrate Memory Read operation? ...

Q. Illustrate Memory Read operation? Memory unit receives the address from a register known as the memory address register designated by MAR. Data is transferred to another re

What is reducibility, What is reducibility?  The primary method of prov...

What is reducibility?  The primary method of proving some problems are computationally unsolvable.       It is known as reducibility. Reducibility always includes two problems

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd