Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Draw a schematic for managing dynamic storage allocation, Draw a simple sch...

Draw a simple schematic for managing dynamic storage allocation. A simple schematic for managing dynamic storage allocation is as follows: Block size pointe

Describing Random Algorithm, Suppose you''re given n numbers and asked to f...

Suppose you''re given n numbers and asked to find a number that is greater than or equal to the median a) What is the lower bound for the worst case complexity of this problem?

Time complexity in the worst case, Speicified the following piece of code: ...

Speicified the following piece of code: int i = 1; int j = 4; while (i     {      if (i%3 == 0) i+=3;      else i+=4;        if (j%2 == 0) j*=4;      els

Explain the daa instruction, Explain the DAA DAA instruction follows th...

Explain the DAA DAA instruction follows the ADC or ADD instruction to adjust the result into a BCD result. DAA instruction functions only with the AL register, this addition sh

Texture - elements of composition, Texture Texture is how artists show...

Texture Texture is how artists show what an object would feel like to touch. This can have a dramatic effect on how an image is perceived. Imagine for instance an image that h

Amdahl law to measure speed up performance, Q. Amdahl Law to measure speed ...

Q. Amdahl Law to measure speed up performance? Remember that speed up factor assists us in knowing relative gain attained in shifting execution of a task from sequential comput

Static memories - computer architecture, Static memories Circuits c...

Static memories Circuits capable of receiving their state as long as power is applied volatile Static RAM(SRAM)

Two ways for restricting the value range for a domain, What are the two way...

What are the two ways for restricting the value range for a domain? By specifying fixed values. By stipulating a value table.

Which of the logic gates are known as universal gates, Which of the logic g...

Which of the logic gates are known as universal gates ? Ans. NAND and NOR are termed as universal gates, since any digital circuit can be realized completely by using either of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd