Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is the type of process identifiers, What is the type of Process Identi...

What is the type of Process Identifiers? Identification of the real user Identification of the effective user Identification of the real group Identification

State the web server security through ssl, Web server security through SSL ...

Web server security through SSL (Secure Socket Layer) As it is well known that the Intranets and internet are purely based on use of powerful web servers to deliver information

Data analysis and results in e-commerce, There were 50 respondents to our s...

There were 50 respondents to our survey. The first component of the data examined here focuses on student's preference (ecommerce or traditional commerce). The Second compone

Explain about floating-executive model, Q. Explain about Floating-Executive...

Q. Explain about Floating-Executive model? Floating-Executive model: The master-slave kernel model is too restrictive in sense that only one of processors viz designated master

Assignment for statical natural language processing, Hi I study master of ...

Hi I study master of computer science I have assignment for subject statical natural language processing . I need solved due date on 6 May2014 at 11 pm Australia time I need yo

Discuss the 5-level switching hierarchy recommended by ccitt, Discuss the 5...

Discuss the 5-level switching hierarchy recommended by CCITT. Hierarchical networks are able of handling heavy traffic where needed, and at similar time use minimal number of t

Why a computer expect to receive responses, Why a computer expect to receiv...

Why a computer expect to receive responses when it broadcast an ARP request? Response will be acquired only from the machine for that request is being sent not for the other ma

What is a serial port, What is a serial port?  A serial port transfers...

What is a serial port?  A serial port transfers and receives data single bit at a time.

Explain implementation of circuits from boolean expression, Explain Impleme...

Explain Implementation of the Circuits From the Boolean Expression? If the operation of the circuit is defined by a Boolean expression, a logic-circuit diagram can he implement

Explain the multiple bus organization structure, Explain the multiple bus o...

Explain the multiple bus organization structure with neat diagram. The multiple bus organization is using more buses instead of one bus to decrease the number of steps needed an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd