Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is a file, What is a file? A file is a named collection of relate...

What is a file? A file is a named collection of related information that is recorded on secondary storage. A file having either programs or data. A file has sure "structure" b

Explain the general model for the translation process, Write down the gener...

Write down the general model for the translation process. For the translation process the general model can be represented as given here:

history of databases , Write a four-page paper how relational data solutio...

Write a four-page paper how relational data solution is applied to presnt Video Store business. 1.       Describe Relational Databases   2.       Write History of databases

Describe type library and what is its purpose, Type libraries are files tha...

Type libraries are files that explicitly explain some or all of the contents of components. This haves information about the methods, properties, constants, and other members expos

Assembler directives, Assembler directives: An assembler directive is ...

Assembler directives: An assembler directive is a statement to give direction to the assembler to perform the task of assembly process. Assembler directives control organizati

What is immediate addressing, What is Immediate addressing The  data  i...

What is Immediate addressing The  data  itself,  beside  the address,  is  given  as  the  operand or operands  of  the instruction.

The values 15 and 11 can also be defined by variable, In the statement Writ...

In the statement Write:/15(10) lfa1-lifnr. The values 15 and 11 can also be defined by variable. No, the value of 11 nad 15 is not described by variable.

Multiple program multiple data, Like SPMD, MPMD is actually a "high level" ...

Like SPMD, MPMD is actually a "high level" programming model that can be built upon any combination of the previously mentioned parallel programming models. MPMD applications ty

Which of the memories stores the most number of bits, Which of the memories...

Which of the memories stores the most number of bits ? Ans. most number of bits stores in 32M x 8 As 2 5 x 2 20   = 2 25 Therefore 1M = 2 20 = 1K x 1K = 2 10 x 2 10

Obstacles to is implementation - information system, Obstacles to IS implem...

Obstacles to IS implementation While information systems are now becoming the norm in most organisations the journey to this point has been a difficult one. Even in the 21st c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd