Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Translating from english to first-order logic, Translating from English to ...

Translating from English to First-Order Logic: Still we have now seen some of examples of first order sentences, than you should practice writing down English sentences in fir

Estate agency application, Build U Like are a building company specialising...

Build U Like are a building company specialising in hard landscaping. They lay patios, build walls, lay drives etc. for their customers. A customer will remain in the system even t

What are the objectives of usb, What are the objectives of USB? a) Simp...

What are the objectives of USB? a) Simple b) Low cost c) Easy to use d) Supports wide range of data transfer characteristics e) Plug and play mode of operation

Capacity and performance of storage - computer architecture, Capacity: ...

Capacity: Raw capacity Total amount of stored information that a medium or storage device can hold is expressed as a quantity of bytes and bits (for example 10.4 megabyte

Cross bar-various interconnection networks-fully connected, Cross Bar ...

Cross Bar The crossbar network is the easiest interconnection network. It has a two dimensional grid of switches.  It is a non-blocking network and give connectivity among inp

Project, the project database is avilable?

the project database is avilable?

Define a console-program to make an array of integers, Define a console-pro...

Define a console-program to make an array of integers. Initialize the array and assign the values in array. Describe a method to pass the array and alter array elements. show array

Define bidirectional bus, Define bidirectional bus? A bidirectional bus...

Define bidirectional bus? A bidirectional bus is that which permits the transfer of data either from memory to CPU during a read operation or from CPU to memory during write op

Cemistry, Discuss scales and sludge

Discuss scales and sludge

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd