Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Btree, What should the size of ''t'' in btree be depending on the hard disk...

What should the size of ''t'' in btree be depending on the hard disk size

Illustrate shift micro-operations, Q. Illustrate Shift Micro-operations? ...

Q. Illustrate Shift Micro-operations? Shift is a valuable operation that can be used for serial transfer of data. These operations can also be used along with other (arithmetic

What is process, What is Process? Process: A process is a program in ...

What is Process? Process: A process is a program in execution. It is an active entity, represented through the value of the program counter and the contents of registers o

What is reification and behaviour, What is reification and behaviour? R...

What is reification and behaviour? Reification is the promotion of something that is not an object into an object. Behavior usually requires this description. It isn't usually

What is a pipeline hazard, What is a pipeline hazard? Any condition tha...

What is a pipeline hazard? Any condition that causes the pipeline to stall is known as hazard. They are also known as stalls or bubbles.

Define grid computing, GRID COMPUTING Grid Computing signifies applying...

GRID COMPUTING Grid Computing signifies applying resources of different computers in a network concurrently to a single problem for solving a scientific or technical problem wh

Example of pruning, Example of Pruning: As an example, we are assume t...

Example of Pruning: As an example, we are assume that the four choices for player one, there we are looking only two moves ahead 1 for player one and 1 for player two such as

Dynamic programing, a ship is loaded with a stock of 3 items each unit of i...

a ship is loaded with a stock of 3 items each unit of item n has a wt wn and vn the max cargo wt the ship can take is the details of 3items are item(n):1 2 3 wt(wn):2 3 1 value(vn)

Differentiate between absolute and relative poverty, Question 1: Using ...

Question 1: Using appropriate diagrams, describe the optimal provision of a private good and a public good. Question 2: Using appropriate diagram, show how there is an

Define miss penalty, Define miss penalty? The extra time required to br...

Define miss penalty? The extra time required to bring the desired information into the cache is known as miss penalty.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd