Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain basic cpu structure, A computer manipulates data consistent with in...

A computer manipulates data consistent with instructions of a stored program. Stored program means that the data and program are stored in same memory unit. Central processing unit

Explain the high level Language - computer programming, Explain the High Le...

Explain the High Level Language? The programming language such as FORTRAN, C, or Pascal that enables a programmer to write programs those are more or less independent of a parti

Kirchoff''s voltage law , Kirc hoff's Voltage Law   The sum ...

Kirc hoff's Voltage Law   The sum of all the voltage drops around a closed circuit loop will add to zero  V1+(-V2)+(-V3)+(-V4)= 0

Explain the compiler - computer programming, Explain the Compiler - Compute...

Explain the Compiler - Computer Programming? The Compiler is a program that translates source code into object code. The compiler derives its name from the means it works looki

Explain sample instruction format of mips instruction, Q. Explain Sample In...

Q. Explain Sample Instruction Format of MIPS instruction? All MIPS instructions are of same size and are 32 bits long. MIPS designers chose to keep all instructions of same len

Continuous or discrete - artificial intelligence, Continuous or Discrete - ...

Continuous or Discrete - artificial intelligence: The behaviour of the coming data in from the environment will change how the agent should be programming. In particular, the

Cross bar-various interconnection networks-fully connected, Cross Bar ...

Cross Bar The crossbar network is the easiest interconnection network. It has a two dimensional grid of switches.  It is a non-blocking network and give connectivity among inp

Message passing programming, Message passing is possible the most widely us...

Message passing is possible the most widely used parallel programming paradigm these days. It is the most portable, natural and efficient scheme for distributed memory systems. It

Explain about computer architecture, Explain about Computer architecture ...

Explain about Computer architecture Computer architecture is the conceptual design and fundamental operational structure of a computer system. It is a blueprint and functional

Define user space, Define user space? The system space is divided from ...

Define user space? The system space is divided from virtual address space in which the user application programs reside. The letter space is known as user space.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd