Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How can arithmetic processor be associated to the CPU, Q. How can this arit...

Q. How can this arithmetic processor be associated to the CPU?  Two mechanisms are used for connecting arithmetic processor to CPU.   If an arithmetic processor is treated a

Discussion., Functionality first and then Security?

Functionality first and then Security?

Serial execution and parallel execution, Serial Execution Execution of ...

Serial Execution Execution of a program consecutively, one statement at a time. In the easiest sense, this is what occurs on a one processor machine. However, even many of the

Show the frames inside other frames, Q. Show the Frames inside other frames...

Q. Show the Frames inside other frames? Here we would discuss how to divide frames into different frames that is how to put horizontal frames in a vertical one and vice-versa.

Conversion of data types done between abap/4 & db layer, How is conversion ...

How is conversion of data types done between ABAP/4 & DB layer? Conversion among ABAP/4 data types and the database layer is complete within the database interface

Input-output techniques, After going through details of device interfaces n...

After going through details of device interfaces next point to be discussed is how the interface can be used to support I/O from devices. Binary information received from an extern

Predicates in propositional model, Predicates in propositional model: ...

Predicates in propositional model: The predicates take a number of arguments in which for now we assume are ground terms and represent a relationship between those arguments t

Local variables and global variables in lingo programming, Question: (a...

Question: (a) Differentiate between local variables and global variables in Lingo programming. (b) Using examples differentiate between deleteProp() and deleteAt() function

Give detail explanation about arithmetic micro-operations, Give detail expl...

Give detail explanation about Arithmetic Micro-operations These micro-operations perform some essential arithmetic operations on numeric data stored in the registers. These bas

What is throughput of a system, Throughput of a system is? Ans. "Throug...

Throughput of a system is? Ans. "Throughput" of a system is no. of programs processed by this per unit time.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd