Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is dom, DOM is the Document Object Model (DOM) which is an interface s...

DOM is the Document Object Model (DOM) which is an interface specification handled by the W3C DOM Workgroup that explains an application independent mechanism to access, parse, or

Define colgroup tag, COLGROUP defines a group of columns in table and...

COLGROUP defines a group of columns in table and allows you to set properties of those columns. goes immediately after tag and before an

Explain the term recursion, Explain the term recursion A recursive functi...

Explain the term recursion A recursive function is one which calls itself. Recursive functions are useful in evaluating certain types of mathematical function. Here is a recursiv

What do you mean by synchronization principles, In multiprocessing several ...

In multiprocessing several processors require to communicate with one another. So synchronisation is needed between them. The correctness and performance of parallel execution reli

Multi-layer network architectures, Multi-Layer Network Architectures: ...

Multi-Layer Network Architectures: As we considered we saw in the previous lecture that perceptrons have limited scope in the type of concepts that they can learn - but they c

Convert the octal number 7401 to binary, Convert the octal number 7401 to B...

Convert the octal number 7401 to Binary. Ans. Octal number 7401 to Binary conversion: Every octal digit represents 3 binary digits. To change an octal number to binary number,

Determine the simplified sop boolean expression, Reduce the following equat...

Reduce the following equation using k-map Y = BC‾D‾ + A‾BC‾D + ABC‾D + A‾BCD + ABCD Ans. Multiplying the first term with (A+A') Y = A'BC'D' + ABC'D' + A'BC'D + ABC'D + A'BCD + A

What is reentrant tasks and functions, What is reentrant tasks and function...

What is reentrant tasks and functions Tasks and functions without optional keyword automatic are static , with all declared items being statically allocated. These items will b

Pc cross assembler, 1.0 By working throughthe first time guide this will ga...

1.0 By working throughthe first time guide this will gain familiarity with the on board monitor and the PC cross assembler  After connecting the system to the terminal program,

Develop the multi agent system, The new season of AFL, and the excited comi...

The new season of AFL, and the excited coming FIFA World Cup in South Africa this June, many sports fans are willing to find the latest results of their beloved sports teams. In th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd