Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the types of parallel programming, Q. What are the types of parall...

Q. What are the types of parallel programming? There are various parallel programming models in general use. A few of them are:  Data Parallel programming Message P

Describe about immediate addressing mode, Q. Describe about Immediate Addre...

Q. Describe about Immediate Addressing mode? When an operand is interpreted as an immediate value for example LOAD IMMEDIATE 7 it is actual value 7 which is put in CPU register

Data structure, what are the fundamental data structures

what are the fundamental data structures

Explain the features of major scheduling algorithms, Explain the Features o...

Explain the Features of Major scheduling algorithms. The Features of Major scheduling algorithms is given below: FCFS - i.e. First come first served scheduli

What are the disadvantages of fcfs scheduling algorithm, What are the disad...

What are the disadvantages of FCFS scheduling algorithm as compared to shortest job first (SJF) scheduling? Disadvantages: (i) Waiting time can be huge if short requests w

Determine by which digits are represented in dtmf phone, In a DTMF phone, d...

In a DTMF phone, digits are represented by: (A)  Orthogonal frequencies. (B)  Orthogonal Phases. (C)  Orthogonal codes. (D)  Orthogonal pulses. Ans: Di

What is the concept of lock, Q. What is the Concept of Lock? Locks are ...

Q. What is the Concept of Lock? Locks are used for protected access of data in a shared variable system.  There are numerous kinds of locks:  1)  Binary Locks: These locks a

Explain in detail about real time processing, Explain in detail about Real ...

Explain in detail about Real time (transaction) processing When booking seats on a flight, for illustration, real time (transaction) processing would be used. Response to a que

How do we synthesize verilog into gates with synopsys, How do we synthesize...

How do we synthesize Verilog into gates with Synopsys?  The answer can, of course, occupy various lifetimes to completely answer.. BUT.. a straight-forward Verilog module can b

Ip fragmentation of user datagarm, IP specified that datagram can arrive in...

IP specified that datagram can arrive in a different order than they were sent. If a fragment from one datagram arrives at a destination before all the segments from a previous dat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd