Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is store program control, What is store program control (SPC)?  I...

What is store program control (SPC)?  In  stored  program  control  systems,  a  set  of  instructions  or  program  to  the computer  is  stored  in  its  memory  and  instru

Limitation of software engineering, i want to get answer about this topic w...

i want to get answer about this topic what is software engineering and what is its limitation

What are the type of internet connection, What are the type of Internet con...

What are the type of Internet connection When determining requirements for a VPN, carefully estimate the number of systems to be put behind the VPN, the number of concurrent u

Origin of RISC, Q. Origin of RISC? In the 1980s a new philosophy develo...

Q. Origin of RISC? In the 1980s a new philosophy developed having optimizing compilers which could be used to compile 'normal' programming languages down to instructions which

Example of perceptrons, Example of perceptrons: Here as an example fun...

Example of perceptrons: Here as an example function in which the AND boolean function outputs a 1 only but if both inputs are 1 and where the OR function only outputs a 1 then

Explain the concept behind pre-compositing adobe, Question 1: (a) Expl...

Question 1: (a) Explain the concept behind Pre-Compositing Adobe After Effects. (b) Briefly describe the Wiggler function in Animation help in Adobe After Effects. (c)

Classify process and differentiate program, Classify Process, differentiate...

Classify Process, differentiate program, process A process maybe concerned to be a program being run. A program isn't a process of itself; it's a passive Entity while the proce

Explain about the term- reports, Explain about the term- Reports Repor...

Explain about the term- Reports Reports are produced as a result of questions like "how many times has a type of car broken down" or "which cities have the highest house price

What is machine language, What is Machine Language? To write program fo...

What is Machine Language? To write program for a computer we need to specify, directly or indirectly the sequence of machine instructions.  These instructions  inside  computer

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd