Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Create the website home page, Now when a site structure is set up for stori...

Now when a site structure is set up for storing pages and assets for Compass site, you'll create the first page-a home page for the site. As you build this page, you will add text,

Show the bus and memory transfers, Q. Show the Bus and Memory Transfers? ...

Q. Show the Bus and Memory Transfers? A digital computer has many registers and rather than connecting wires amid all registers to transfer information between them a common bu

What is electronic payment system, What is electronic payment system? E...

What is electronic payment system? Electronic payment systems are alternative cash credit payment methods using various electronic technologies to pay for products and services

Write a program to find the area and perimeter of a circle, Write a program...

Write a program to find the area and perimeter of a circle of given radius # include void main() { float radius, area, perimeter, pi=3.14; printf("\nEnter the rad

Survey of advanced applications, 1. Conduct a literature survey of advanced...

1. Conduct a literature survey of advanced applications of the finite element method for engineering design and analysis. 2. Identify at least one application, which interests y

Interconnection network, Interconnection Network Introduction Th...

Interconnection Network Introduction This unit discusses the types and properties of interconnection networks.  In multiprocessor systems, there are multiple I/O modules

Explain the working of any one of centralized spc, Explain the working of a...

Explain the working of any one of centralized SPC? Standby mode of operation is the easiest of dual processor configuration operations. Usually, one processor is active and

Software estimation, Software Estimation The statement of scope helps t...

Software Estimation The statement of scope helps the planner to established estimates using one or more method which fail into two wide categories: empirical modeling and decom

Explain lexical substitution during macro expansion, Explain Lexical substi...

Explain Lexical substitution during macro expansion ? Lexical substitution is used to produce an assembly statement from a model statement. Model statements have 3 kinds of str

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd