Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Find cross points and primary no. in 3-tage satge switching, A three stage ...

A three stage switching structure supports 100 inlets and 400 outlets. Find the number of cross points, and the number of primary and secondary switches used in the design. We

Development of a successful system, The success of a system relies on the a...

The success of a system relies on the approach of building it. If development approach is right then system will work successfully. Figure below portrays a System Development Life

What is dispatch unit, What is dispatch unit? A separate unit which we ...

What is dispatch unit? A separate unit which we call the dispatch unit fetch instructions from the front of the queue and sends them to the execution unit. The dispatch unit al

Show the main drawback of cav disk, Q. Show the main drawback of CAV disk? ...

Q. Show the main drawback of CAV disk? The main drawback of CAV disk is that a lot of storage space is wasted because longer outer tracks are storing data only equal to the sho

Illustrate master-slave flip-flop, Q. Illustrate Master-Slave Flip-Flop? ...

Q. Illustrate Master-Slave Flip-Flop? Master slave flip-flop comprise two flip-flops. One is master flip-flop and other one is known as slave flip-flop. Fig below shows impleme

Explain ps-2 connector, PS/2 connector (PS/2 keyboards): These were int...

PS/2 connector (PS/2 keyboards): These were introduced with IBM's PS/2 computers and therefore are known as PS/2 connectors.  They have 6-pins but actually their wiring is just

State the concept of multiplicity, Multiplicity Multiplicity in an ass...

Multiplicity Multiplicity in an association specifies tells us about number of objects participate in a relationship. It decides the number of related objects. Multiplicity is

Comparator, 6 bit magnitude comparator

6 bit magnitude comparator

What are the different phases of consumer mercantile model, What are the di...

What are the different phases of consumer mercantile model? There are three different phase of consumer mercantile model like listed as in below: • Pre-purchase interaction

Ethernet 10 base 2 is an example of which topology, Ethernet 10 Base 2 is a...

Ethernet 10 Base 2 is an example of               network topology. (A)  Bus                                           (B)  Ring (C)  Star

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd