Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the different layers in r/3 system, What are the different layers ...

What are the different layers in R/3 system? There are three layer:- Presentation Layer. Application Layer. Database Layer.

Significance of having less memory references, Q. What is the significance ...

Q. What is the significance of having less memory references? As the time needed for memory reference is more than that of a register reference so increased number of memory r

Dynamic programming problem, KK manufacturing company is faced with demand ...

KK manufacturing company is faced with demand for its product in each of the next four periods as shown in Table 1.  It must decide upon a production schedule to meet these demands

What is delegation, What is Delegation? A delegate acts like a strongly...

What is Delegation? A delegate acts like a strongly type function pointer. Delegates can raise the methods that they reference without making explicit calls to those methods. D

Explain about layout cells, Q. Explain about Layout Cells? In Layout vi...

Q. Explain about Layout Cells? In Layout view you can draw layout cells and layout tables to define design areas of a document. This task is easier to accomplish if you prepare

Design a mod-6 synchronous counter, Design a MOD-6 synchronous counter usin...

Design a MOD-6 synchronous counter using J-K Flip-Flops. Ans: Design of Mod-6 Counter:   To design the Mod-6 synchronous counter, contain six counter states (that is, from

Explain briefly the function of layers, Explain briefly the function of dif...

Explain briefly the function of different layers which are covered under end to end layer connectivity. Different layer are as follows: 1. Transport Layer:  This is res

Which TTL logic gate is used for wired anding, Which TTL logic gate is used...

Which TTL logic gate is used for wired ANDing ? Ans. Open collector output, TTL logic gate is used.

Modified digital clock, can you deign the schematic of a modified digital c...

can you deign the schematic of a modified digital clock at the gate as well as the IC level and then construct the circuit, lab spec and industral spec?

Subprogram, create a stored procedure to debit a bank account user must ent...

create a stored procedure to debit a bank account user must enter account no. and amount to debited from account .the minimum balance in account should be 500. if the debited amoun

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd