Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is external modems, Q. What is External Modems? External Modems: M...

Q. What is External Modems? External Modems: Modems externally associated to PC via a parallel or serial port and into a telephone line at the other end.  They can generally co

Career after BSc CS, Sir,wish to receive guidance from you how to join in A...

Sir,wish to receive guidance from you how to join in Aeronautical Engineering after Bsc Computer Science. I am a Girl.Interested to work in AE field, it will be better to use in co

How many instructions in a computer, Q. How many instructions in a Computer...

Q. How many instructions in a Computer? A computer can have a vast number of instructions and addressing modes. Older computers with the growth of Integrated circuit technolog

What is the use of buffer register, What is the use of buffer register? ...

What is the use of buffer register? The buffer register is used to avoid speed mismatch among the I/O device and the processor.

What is focussed ion beam fix, What is Focussed Ion Beam Fix? A FIB Fix...

What is Focussed Ion Beam Fix? A FIB Fix (Focussed Ion Beam) Fix is simply performed onto a terminated chip. FIB is a somewhat exotic process where a particle beam is capable t

Implementing recursive function the data structure, For executing recursive...

For executing recursive function the data structure used is: For executing recursive function, stack is used as a data structure.

Why echo suppressor is detrimental to full duplex operation, Echo suppresso...

Echo suppressor is detrimental to full duplex operation because? This disables one of the two pairs in a four-wire trunk line while a signal is detected upon another pair.

Describe the term- macros, Describe the term- Macros A macro is a key o...

Describe the term- Macros A macro is a key or name which signifies a series of commands or key strokes. Many applications allow single nominated key or single word on a keyboar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd