Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Parallel virtual machine, Parallel Virtual Machine (PVM): PVM (Parallel...

Parallel Virtual Machine (PVM): PVM (Parallel Virtual Machine) is portable message passing programming system which is designed to link different heterogeneous host machines to

Explain basic working of mainframes, Q. Explain Basic working of Mainframes...

Q. Explain Basic working of Mainframes? Mainframe computers are normally 32-bit machines or higher. These are suited to large organizations, to manage high volume applications.

DBMS, Difference between Paperbase and computer base system?

Difference between Paperbase and computer base system?

Define programmed i/o, Define Programmed I/O. It is the result of input...

Define Programmed I/O. It is the result of input and output instructions written in the computer program. Every data item transfer is initiated by an instruction in the program

Indias parallel computers, Parallel Computers In India, the design and ...

Parallel Computers In India, the design and development of parallel computers in progress in the early 80?s. The Indian Government recognized the Centre for Development of Adva

What is parallel balance point, Q. What is Parallel Balance Point? In ...

Q. What is Parallel Balance Point? In order to execute parallel algorithm on parallel computer K processors are necessary. It should be noted that given input is allocated to

How many octets does smallest possible ipv6 datagram contain, How many Octe...

How many Octets does the smallest possible IPV6 datagram contain? The maximum size of an Ipv6 datagram is 65575 bytes, with the 0 bytes Ipv6 header. Ipv6 also describe a minim

Implicative normal form, Implicative normal form: Thus the sentence is...

Implicative normal form: Thus the sentence is now in CNF. In Fact for simplification can take place by removing duplicate literals and dropping any clause that contains both A

Explain the number unobtainable tone in strowger telephony, Explain the num...

Explain the number unobtainable tone in strowger telephony with waveforms and the timings. In the following figure illustrates the number unobtainable tone that is continuous

State the types of common toes deformities a, Common toes deformities are: ...

Common toes deformities are: 1. Hallux valgus: Deviation of great toe towards the second toe resulting in prominence of first metatarsal head.  Later on there is formation of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd