Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain about double error detection bit, Q. Explain about Double Error Det...

Q. Explain about Double Error Detection bit? Let's presume now that two bit errors take place in data. Data received: So on -matching we conclude P3-D3 pair doesn't

What are the advantages of inheritance in c++, It allows code reusability. ...

It allows code reusability. Reusability saves time in program development. It encourages the reuse of proven and debugged high-quality software, thus decreasing problem after a sys

Constructor, what is meant by private copy constructor

what is meant by private copy constructor

Explian service topologies, Explian Service Topologies Service Topolog...

Explian Service Topologies Service Topologies In a service-based architecture there increase dependencies between services resulting from cooperation

What is error detection code, What is Error detection code? It is a bin...

What is Error detection code? It is a binary code that notice digital errors during transmission. The detected errors cannot be correct but the presence is shown.

Develop website for my party venue- hall rental website, Project Descriptio...

Project Description: I want to prepare website for my party venue where i can post the photos and detail of place along with availability calendar. In future, I buy some more ha

Logical database reads the data from the database, Is it true that the Logi...

Is it true that the Logical Database reads the data from the database tables using Select Statements. Yes. We are coding that in Database part of LDB.

What are the measures to be taken in the design, What are the measures or p...

What are the measures or precautions to be taken in the Design when the chip has both analog and digital portions? As today's IC has analog components also inbuilt, some design

Categorize the cpu scheduling algorithms, Categorize the CPU scheduling alg...

Categorize the CPU scheduling algorithms? The various CPU scheduling algorithms are categorized as given below:

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd