Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Adding momentum - sigmoid units, Adding Momentum - Sigmoid units: Howe...

Adding Momentum - Sigmoid units: However imagine a ball rolling down a hill as it does so then it gains momentum in which its speed increases and it becomes more difficult to

Describe about the protection features present in ms access, If a programme...

If a programmer doesn't wish to make modifies to the document he can lock the document data and its code from more changes by changing the extension of the file system to .MDE. Cha

Explain time sharing operating system, Explain Time sharing operating syste...

Explain Time sharing operating system. Time sharing: It is also called as multi tasking, is a logical execution of multiprogramming. Multiple jobs are executed through the C

gui component handle its own events, A component can handle its own events...

A component can handle its own events by executing the needed event-listener interface and adding itself as its own event listener.

How to calculate register indirect addressing, Q. How to calculate register...

Q. How to calculate register indirect addressing? The effective address of operand in this technique is calculated as: EA= (R) and D = (EA)  Address capability of regi

Visibility, hidden edge/surface removal

hidden edge/surface removal

Difference between vertical and horizontal organization, Difference between...

Difference between Vertical and Horizontal Organization Vertical Organizations  It is a usual approach which is typified by a functional approach to work in which departme

Resource dependence , Resource Dependence The parallelism among the ...

Resource Dependence The parallelism among the instructions may also be affected because of  the shared resources. If two instructions are using the related shared resource t

What do you mean by drive cache, Q. What do you mean by Drive Cache? Di...

Q. What do you mean by Drive Cache? Disk cache may be a part of RAM sometimes known as soft disk cache which is used to speed up access time on a disk. In latest technologies s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd