Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Genetic algorithms - artificial intelligence, Genetic Algorithms: In s...

Genetic Algorithms: In such a scenario the evolutionary approach to "Artificial Intelligence" is one of the neatest ideas of all. Whether we have tried to mimic the functionin

What is process control block, What is process control block?  Each pro...

What is process control block?  Each process is shown in the OS by a process control block. It having many pieces of information associated with a specific process.

Address fields and phone fields , Make a nested struct to store a person's ...

Make a nested struct to store a person's name, address, and phone numbers.  The struct should have 3 fields for the name, address, and phone. The address fields and phone fields wi

Types of validation controls provided by asp.net, Types of validation contr...

Types of validation controls provided by ASP.Net There are following types of validation controls provided by ASP.Net: 1. Required Field Validator 2. Compare Validator

What is the role of ir and pc, What is the role of IR and PC?  Instruct...

What is the role of IR and PC?  Instruction Register (IR) having the instruction being implemented. Its output is available to the control circuits, which make the timing signa

What is an advantage of executing a process in background, What is an advan...

What is an advantage of executing a process in background? The most common reason to put a process in the background is to permit you to do something else interactively without

How to develop an object model, How to develop an object model To deve...

How to develop an object model To develop an object model firstly identify classes and their associations, as they affect overall problem structure and approach. Then prepare

What is uml, ? UML is called as Unified Modeling Language. ? it is used...

? UML is called as Unified Modeling Language. ? it is used to Graphical language for visualizing artifacts of the system. ? It Allow to make a blue print of all the aspects

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd