Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

..binary tree, draw a binary tree from its inorder and preorder traversal s...

draw a binary tree from its inorder and preorder traversal sequences given as follows: inorder: d b g e h a c n f preorder: a b d e g h c f n

Explain about algebraic simplification, Q. Explain about Algebraic Simplifi...

Q. Explain about Algebraic Simplification? We have already determined algebraic simplification of logic circuit. An algebraic expression can exist in SOP or POS forms.  Let's i

What is the conclude of the force of gravity on an object, Q. What is the...

Q. What is the conclude of the force of gravity on an object? Answer:- Force is the vector product of mass as well as acceleration F = ma. Weight is an unusual case of t

Where do you set automatic correlation options, Automatic correlation from ...

Automatic correlation from web point of sight can be set in recording options and correlation tab. Here we can enable correlation for the whole script and choose either issue onlin

PADOVAN STRING, write a program that counts the number of occurrences of th...

write a program that counts the number of occurrences of the string in the n-th Padovan string P(n)

Explain the need for user-defined functions, Explain the need for user-defi...

Explain the need for user-defined functions. The need for user-defined function: 1.  A programmer might be having a block of code that he has repeated forty times all over t

What are pooled tables, Normal 0 false false false EN-I...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Appropriate problems for ann learning, Appropriate Problems for ANN learnin...

Appropriate Problems for ANN learning: Conversely as we did for decision trees there it's important to know where ANNs are the right representation scheme for such job. Howeve

Determine the bandwidth required for transmission, A PCM system uses 8 bits...

A PCM system uses 8 bits per sample and the analog signal is limited to 4.3 kHz. The PCM data is transmitted using (a) BFSK and (b) ASK. Determine the bandwidth required for transm

Which process is used for page reference, Locality of reference implies tha...

Locality of reference implies that the page reference being made by a process is Ans. Locality of reference means that the page reference being made through a process is proba

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd