Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is dialog module, What is dialog Module? A dialog Module is a call...

What is dialog Module? A dialog Module is a callable sequence of screens that does not belong to a certain  transaction. Dialog modules have their module pools, and can be know

How to use an assembler, Q. How to use an Assembler? Symbolic instructi...

Q. How to use an Assembler? Symbolic instructions which we code in assembly language is called as- Source program. An assembler program translates source program in machine

Explain their characteristics and limitations of grammar, Identify the diff...

Identify the different classes of grammar. Explain their characteristics and limitations. As proposed through Noam Chomsky that Chomsky hierarchy contains the subsequent level

Udp, udp connection establishment and termintion

udp connection establishment and termintion

Write a program for comparing two strings, Q. Write a program for comparing...

Q. Write a program for comparing two strings? Let's write a program for comparing two strings. Determine the following piece of code that has been written in C to compare two s

C programming, There is a pebble merchant. He sells the pebbles, that are u...

There is a pebble merchant. He sells the pebbles, that are used for shining the floor. His main duty is to take the length of the room’s sides. But he sometimes mistakes doing that

Computer network, how Hierarchical Routing implement in c or cpp

how Hierarchical Routing implement in c or cpp

Create a web page from which customers can order equipment, Q. Create a Web...

Q. Create a Web page from which customers can order equipment? Suppose your boss wants you to create a Web page from which customers can order computer equipment. You need to c

Write short note on code optimization, Write short note on code optimizatio...

Write short note on code optimization. Code optimization: It is the optional phase designed to enhance the intermediate code therefore the Ultimate object program runs quicke

What is a message in mqseries, A message is a string of bytes that has mean...

A message is a string of bytes that has meaning to the applications that use it Message = Header(s) + Application Data A message having of a header and the attached applicat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd