Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain about control memory organization, Q. Explain about Control Memory ...

Q. Explain about Control Memory Organization? One of the simplest ways to organize control memory is to organize micro-instructions for different sub cycles of machine instruct

Database, what are the Database designs to avoid?

what are the Database designs to avoid?

What are spa/gpa parameters (sap memory), What are SPA/GPA parameters (SAP ...

What are SPA/GPA parameters (SAP memory) SPA/GPA parameters are field values saved globally in memory.  There are two ways to use SPA/GPA parmeters: By setting field attrib

Design the counter using sequential logic, Q. Design the counter using sequ...

Q. Design the counter using sequential logic with following counting sequence using RS- flip-flops. 000, 100, 101, 111, 010, ... ... ... ... ... ... ... ... ... ...

Explain indirect cycle in control unit, Q. Explain Indirect Cycle in contro...

Q. Explain Indirect Cycle in control unit? Once an instruction is fetched the subsequent step is to fetch the operands. The instruction may have indirect and direct addressing

Explain the concept of process, The Concept of Process Unofficially a p...

The Concept of Process Unofficially a process is a program in execution subsequent to the program has been loaded in the main memory. Though a process is more than just a progr

Define about anchor tag, Q. Define about Anchor Tag? Anchor tag is used...

Q. Define about Anchor Tag? Anchor tag is used to create links between various objects such as HTML pages, web sites, files etc. It is introduced by characters and termi

What is an identification method, An identification method notifies Robot h...

An identification method notifies Robot how to recognize the values to compare during record and playback.

Assembly 8086 program that computes the minimum and maximum, Write a progra...

Write a program that computes the minimum and maximum of elements in an array in Assembly 8086.

Set up the site structure, Structuring the Web site is first step towards b...

Structuring the Web site is first step towards building the corporate Web site. Structuring includes creating a folder that includes all our picture files, text files and database

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd