Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Name some popular internet browsers, Name some Popular Internet Browsers ...

Name some Popular Internet Browsers There are many internet browers are available on internet. Some Popular Internet Browsers are: Internet Explorer, Netscape Navigato

For what an append query be used, For what an append query be used? It ...

For what an append query be used? It is simple to append records from one table to another using an append query. There is no requirement for the tables to have the similar num

Why is TCP called end-to-end protocol, Why is TCP called end-to-end protoco...

Why is TCP called end-to-end protocol? TCP is termed as an end-to-end protocol as this provides a connection directly by an application in one computer to an application on a r

Difference between data warehousing and data mining, Difference between dat...

Difference between data warehousing and data mining The difference between data warehousing and data mining is that data warehousing shows to the data storage while data mining

What is called when a star connected intermediate exchange, A star connecte...

A star connected intermediate exchange is known as a? A star connected intermediate exchange is termed as a Hub exchange.

Manipulate the presentation and attributes interactive list, How can you m...

How can you manipulate the presentation and attributes of interactive lists? ---Scrolling by Interactive Lists. ---Setting the Cursor from within the Program. ---Changing

Determine the importance of computer hardware, Determine the importance of ...

Determine the importance of computer Hardware Hardware forms the greatest asset of the company, but it reaches obsolescence very quickly. Normally, it is said that every six mo

Determine the maximum amplitude of delta modulator, (a) Consider a sinusoid...

(a) Consider a sinusoidal signal m(t) = A cos(2πfmt) applied to a delta modulator with step size Δ. Determine the range of the step size so that slope overload will be avoided. Ass

Catch output from child tasks, Q. Catch output from child tasks? ...

Q. Catch output from child tasks? int pvm_catchout( FILE *ff ) Catch output from child tasks. ff is file descriptor on which we write collected output. The defau

Determine the output of SR flip flop when S=1 and R=0, The output of SR fli...

The output of SR flip flop when S=1, R=0 is ? Ans. When for the SR flip-flop S=set i/p R=reset i/p, as S=1, R=0, Flip-flop will be set means output will be one.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd