Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Name some pure object oriented languages, Some pure object oriented languag...

Some pure object oriented languages are Smalltalk, Eiffel,  Java, Sather.

Implement a priority queue, 1. Insert the following characters with their r...

1. Insert the following characters with their respective priorities (shown as ordered pairs) into an empty treap: (K, 17), (F, 22), (P, 29), (M, 10), (N, 15), (L, 26), (G, 13),

Processor technology , Processor Technology: Computers consist of elec...

Processor Technology: Computers consist of electronic components assembled in a design or "architecture" that will perform necessary functions of input, output, computation an

Why we need linker, Q. Why we need linker?  The linker: Joins as...

Q. Why we need linker?  The linker: Joins assembled module in one executable program, Produces an .EXE module and initializes with special instructions to facilitate

Pebble merchant, There is a pebble merchant.He sells the pebbles,that are u...

There is a pebble merchant.He sells the pebbles,that are used for shining the floor.His main duty is to take length of the room''s sides. program 1 : package test.padovanstring

Write program to simulate conversation with an old and deaf, You are going ...

You are going to write a program to simulate a conversation with an old, deaf relative. You can type your statements, and whatever you say, the relative will reply randomly with on

Add another layout cell, Next add a layout cell for the Learn More About gr...

Next add a layout cell for the Learn More About graphic. 1.  In Objects panel, click the Draw Layout Cell icon. 2.  In Document window, draw a new cell in the space below nav

Example application - canonical genetic algorithm, Example Application: ...

Example Application: There are many fantastic applications of genetic algorithms. Conceivably my favorite is their usage in evaluating Jazz melodies done as part of a PhD proj

Natural and artificial intelligence, Since the term artificial intelligen...

Since the term artificial intelligence was defined in the 1950s, experts have disagreed about the difference between natural and artificial intelligence. Can computers be pro

Explain the term - strong typing and weak typing, Explain the term - Strong...

Explain the term - Strong Typing and  Weak Typing Strong Typing : When any operation upon an object can be checked during compile time, when type is confirmed forcefully.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd