Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Pushbutton switches, Use the input capture to control the digital clock.  I...

Use the input capture to control the digital clock.  In this part, there will be two switches to control the clock, one is for starting the clock and one is for stopping the clock.

Different industries which use this marketing tool, What are the different ...

What are the different industries which use this marketing tool? Ans) Many dissimilar companies can use this tool for developing their business plan but it is often three main

Define stack segment, Q. Define Stack segment ? 8086 Microprocessor su...

Q. Define Stack segment ? 8086 Microprocessor supports Word stack. Stack segment parameters tell the assembler to alert linker that this segment statement states the program s

C program, Write a program to find the area under the curve y = f(x) betwee...

Write a program to find the area under the curve y = f(x) between x = a and x = b, integrate y = f(x) between the limits of a and b. The area under a curve between two points can b

Selection - artificial intelligence, Selection - artificial intelligence: ...

Selection - artificial intelligence: However the first step is to choose the individuals that will have a shot at becoming the parents of the next generation. Hence this is kn

Describe the modes of wave propagation, Question : a) Describe the foll...

Question : a) Describe the following modes of wave propagation: - Line of sight - Ground waves - Skywaves b) Why can waves with a very low frequency be used for submar

Explain the message passing interface, Q. Explain the Message Passing Inter...

Q. Explain the Message Passing Interface? The Message Passing Interface (MPI) is a universal benchmark for providing communication among multiple simultaneous processes on a di

?????, c program??????????

c program??????????

Explain the working of interpreter, Explain the working of Interpreter? ...

Explain the working of Interpreter? The Interpreter is a program that executes instructions written in a high-level language. There are two manners to run programs written in a

Can you tell me some of system tasks and their purpose, Can you tell me som...

Can you tell me some of system tasks and their purpose? $display, $displayb, $displayh, $displayo, $write, $writeb, $writeh, $writeo. The most useful of these is $display. T

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd