Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What do you mean by loader, Q. What do you mean by Loader? Loader is a ...

Q. What do you mean by Loader? Loader is a program that assigns absolute addresses to program. These addresses are produced by adding the address from where program is loaded i

Define class p, Define class P  The class of all sets L that can be kno...

Define class P  The class of all sets L that can be known in polynomial time by deterministic TM. The class of all decision problems that can be decided in polynomial time.

Dbms, Find a 3NF decomposition of the following relation scheme: University...

Find a 3NF decomposition of the following relation scheme: University (Faculty, Dean, Department, Chair, Professor, Rank, Student}. The University relation satisfies the following

What are the reasons behind using intranet, Reason behind using Intranet ...

Reason behind using Intranet The major reasons for doing this include: -  Safer as there is less chance of external viruses or hacking -  It's possible to prevent employe

What is visualisation - search based tools, Q. What is Visualisation - sear...

Q. What is Visualisation - search based tools? Visualization is a common method in contract to search based tools. In this scheme visual aids are supplied as pictures to help p

IA-32 support, In order to support IA-32 Itanium can switch in 32-bit mode ...

In order to support IA-32 Itanium can switch in 32-bit mode with special jump escape instructions. IA-32 instructions have been mapped to Itanium's functional units. But as Itanium

What are the lists of signal available, What are the lists of signal availa...

What are the lists of signal available? Terminating and suspending method Physical circumstances Available for the Programmer Fault in power supply

Explain parsing, What is parsing? The target of parsing is to find out...

What is parsing? The target of parsing is to find out the syntactic validity of a source string. A tree is built for use through subsequent phase of compiler, if the string is

Computer Graphics , What do you mean by ‘Bresenham’s him Algorithm?

What do you mean by ‘Bresenham’s him Algorithm?

Role of bitmap indexes to solve aggregation problems, Describe about the ro...

Describe about the role of bitmap indexes to solve aggregation problems? Ans) Bitmaps are very useful in begin schema to join large databases to small databases. Answer queries

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd