Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Classify process and differentiate program, Classify Process, differentiate...

Classify Process, differentiate program, process A process maybe concerned to be a program being run. A program isn't a process of itself; it's a passive Entity while the proce

What is meant by refreshing of the screen, What is meant by refreshing of t...

What is meant by refreshing of the screen?  Some method is required for maintaining the picture on the screen. Refreshing of screen is completed by keeping the phosphorus glowi

Explain serial execution and parallel execution, Serial Execution Exe...

Serial Execution Execution of a program serially, one statement at one instance of time. In the simplest case, that's what takes place on a one processor machine. But even mo

Programming a 64-bit processor, You are to write a C program called big_mul...

You are to write a C program called big_mult.c that multiplies two unsigned 64-bit integers, x and y, read from the command line. The output is a pair of unsigned 64-bit integers r

Explain excess-3 and gray code using four binary digitis, Give the details ...

Give the details of excess 3 codes and gray code using four binary digits. Ans: Table of excess 3 codes and gray code using four binary digits Binary

What is meant by latch, Latch is a D- type flip-flop used as a temporary st...

Latch is a D- type flip-flop used as a temporary storage device controlled by a timing signal, which can kept 0 or 1. The primary function of a Latch is data storage. It is used in

Example of prolog, Example of Prolog: We can say that this is also tru...

Example of Prolog: We can say that this is also true if there are four even numbers. Now we have our first rule: • If there are three or four even numbered cards, such play

Explain about barrier, Q. Explain about Barrier? Barrier: No actual tra...

Q. Explain about Barrier? Barrier: No actual transfer of data takes place in this mode unless all the processors involved in the communication execute a particular block, calle

Find the number of PROM chips & address lines, The capacity of 2K × 16 PROM...

The capacity of 2K × 16 PROM is to be expanded to 16 K × 16.  Find the number of PROM chips required and the number of address lines in the expanded memory. Ans. Capacity requi

Explain the scan code, What is meant by scan code?  When a key is press...

What is meant by scan code?  When a key is pressed on the keyboard, the keyboard controller places a code take to the key pressed into a part of the memory known as the keyboar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd