Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Change to palindrome, given a string S convert it to palindrome by doing ch...

given a string S convert it to palindrome by doing character replacement.convert S to palindrome with minimum character replacements

Scientific applications-image processing, Scientific Applications/Image pro...

Scientific Applications/Image processing Most of parallel processing functions from science and other academic subjects, are mainly have based upon arithmetical simulations whe

Define http, Http Hyper Text Transfer Protocol: The WWW protocol that...

Http Hyper Text Transfer Protocol: The WWW protocol that performs the request and regain functions of a server. Generally seen as the first part of a website address. It is t

State about the directed-test methodology, Directed-Test Methodology Bu...

Directed-Test Methodology Building a directed verification environment with a comprehensive set of directed tests is very time-consuming and difficult. As directed tests only c

The field sy-stepl, The field SY-STEPL refers to The index of the scre...

The field SY-STEPL refers to The index of the screen table row that is presently being processed.  The system variable SY-stepl only has a meaning within the confines of LOOP.

Write a bash-c shell script, Write a BASH/C shell script which takes a name...

Write a BASH/C shell script which takes a name of a directory as a command line argument, and prints unique login name of the users having files in that directory. Your code should

Convert logic circuit in a binary code, The logic circuit given below, conv...

The logic circuit given below, converts a binary code y 1 y 2 y 3 into Ans. Gray code is X1 = Y1,   X2 = Y1 XOR Y2  ,   X3 = Y1 XOR Y2 XOR Y3 For

What is one-way association, What is one-way association? One-way assoc...

What is one-way association? One-way association means association will traverse in only in one direction and implement using the actual implementation. If the multiplicity is

Explain stored program control, Explain Stored Program Control. Stored...

Explain Stored Program Control. Stored Program Control: Modern digital computers utilize the stored programmed idea. Now, a program or a set of instructions to the computer i

What is write-through protocol, What is write-through protocol? For a w...

What is write-through protocol? For a write operation using write-through protocol during write-hit: The cache location and the major memory location are updated concurrently.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd