Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is redefines clause, Redefines clause is used to permit the similar st...

Redefines clause is used to permit the similar storage allocation to be referenced by dissimilar data names.

Explain the boolean equations for logic circuits, Explain The Boolean Equat...

Explain The Boolean Equations for Logic Circuits? A Boolean equation is the mathematical representation of a logic circuit using standard Boolean terms. All the logic gates (AND,

Determine about the information centres, Determine about the Information ce...

Determine about the Information centres Airports, supermarkets and any application where information needs to be relayed to customers, gain advantage from having automatic inf

Different types of addressing modes, Described different types of addressin...

Described different types of addressing modes available? Ans: The various types of addressing modes available are following:   Register addressing mode   Immediate ad

Datastructure, deque insertion and deletion ..

deque insertion and deletion ..

Interaction goals, Most interactive products aim to satisfy a variety of us...

Most interactive products aim to satisfy a variety of usability and user experience goals. Fully satisfying all of these goals is rarely, if ever, feasible, either because of pract

How do stubs work in a weblogic server cluster, Clients that join to a WebL...

Clients that join to a WebLogic Server cluster and look up a clustered object get a replica-aware stub for the object. This stub haves the list of available server instances that h

Determine the types of sensors, Determine the types of Sensors Differe...

Determine the types of Sensors Different types of sensors are used to give real time information to computers. Frequently, an analogue to digital converter (ADC) is required a

What are difference between mealy and moore state machine, What are differe...

What are difference between Mealy and Moore state machine? Difference between Mealy and Moore state machine: 1) Mealy and Moore models are the fundamental models of state ma

Define the actions a process take upon receiving a signal, Define the vario...

Define the various actions a process might be take upon receiving a signal? There are various actions a process might be take upon receiving a signal here are three different d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd