Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Advantages and disadvantages of public-key cryptography, Advantages and Dis...

Advantages and Disadvantages of Public-key cryptography Advantages (i) Enhanced security and convenience  (ii) Electronic records may be authenticated by affixing

Explain the different page replacement policies, Explain the different page...

Explain the different page replacement policies. Various page replacement algorithms are briefly explained below: 1. First-in, first-out FIFO page replacement algorith

What is the difference among save and save as, Use SAVE when you are revisi...

Use SAVE when you are revising an existing document. Use SAVE AS when you are making a new document from scratch or an existing document. This will remain the original document

How do you detect if two 8-bit signals are same, By using XNOR gate if the ...

By using XNOR gate if the signals are similar then only the output will be one otherwise not.

Explain working of bit serial associative processor, Q. Explain working of ...

Q. Explain working of Bit Serial Associative Processor? When associative processor accepts bit serial memory organization subsequently it is known as bit serial associative pr

Object oriented and structured oriented programming, What is the difference...

What is the difference among object oriented and structured oriented programming? Ans) ? Object Oriented means programme will be there in terms of Class and Object connection w

Determine the use of loop instruction, Q. Determine the use of LOOP instruc...

Q. Determine the use of LOOP instruction? Program: This program prints the alphabets (A-Z) ; Register used: AX, CX, DX CODE SEGMENT ASSUME: CS: CODE.     MAINP:

Grid security, i just want the experiment to be taken , on Grid Security......

i just want the experiment to be taken , on Grid Security........

Explain the life cycle of java server pages, Discuss the life cycle of JSP....

Discuss the life cycle of JSP. A JSP (JavaServer Pages) page services requests like a servlet. Therefore, the life cycle and many of the abilities of JSP pages (particular in t

Backpropagation, Backpropagation: However Backpropagation can be seen ...

Backpropagation: However Backpropagation can be seen as utilising searching a space of network configurations as weights in order to find a configuration with the least error,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd