Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Different ways in which a thread can be cancelled, What are the different w...

What are the different ways in which a thread can be cancelled?  Cancellation of a target thread may occur in two different scenarios: Asynchronous cancellation: One thre

What is collective message passing, Q. What is Collective Message Passing? ...

Q. What is Collective Message Passing? In collective message passing all the processes of a group take part in communication. MPI offers a number of functions to apply the coll

What are the objectives of usb, What are the objectives of USB? a) Simp...

What are the objectives of USB? a) Simple b) Low cost c) Easy to use d) Supports wide range of data transfer characteristics e) Plug and play mode of operation

Multi tasking environment, Q. Explain about Multi tasking environment? ...

Q. Explain about Multi tasking environment? Multi tasking uses parallelism by: 1) Pipelining functional units are pipe line mutually 2) Simultaneously employing multiple

Arbitrary categorisation - learning decision trees, Arbitrary categorisatio...

Arbitrary categorisation - learning decision trees: Through visualising  a set of boxes with some balls in. There if all the balls were in a single box so this would be nicely

Logical representations, Logical Representations: If all human beings ...

Logical Representations: If all human beings spoke the same language, there would be a much more less misunderstanding in the world. The problem regarding with software engine

Depth - basic characteristics of an experts system, An expert system has d...

An expert system has death that is it operate effectively in a narrow domain containing difficult challenging problems. Thus the rules in an experts systems are necessarily co

What is the resolution of this DAC, A 5-bit DAC produces an output voltage ...

A 5-bit DAC produces an output voltage of 0.2V for a digital input of 00001. Find the value of the output voltage for an input of 11111. What is the resolution of this DAC? Ans

Not dragged and dropped onto the form, I have to make a quiz machine progra...

I have to make a quiz machine program in in Visual Basic with the following: A menu strip that must be formed programmatically (ie NOT dragged and dropped onto the form). There

Engineering phyics, what is interference of light explain the nessicity of ...

what is interference of light explain the nessicity of coharent source for obtaining sustain interference pattern

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd