Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Structure tensor, what is structure tensor?how we calculate for image pixel...

what is structure tensor?how we calculate for image pixel?

How to reduce the maximum quantization error, In successive-approximation A...

In successive-approximation A/D converter, offset voltage equal to 1/2 LSB is added to the D/A converter's output. This is done to ? Ans. It is done to reduce the maximum quantiz

System programming, concurrentisation and vectorisation of program

concurrentisation and vectorisation of program

Prove using boolean algebra, Q.Prove using Boolean Algebra 1. X (X+Y) = ...

Q.Prove using Boolean Algebra 1. X (X+Y) = X 2. AB + AC + BC' = AC + BC' 3. (A+B+C) (A+B'+C') (A+B+C') (A+B'+C)=A 4. (A+B'+C) (AB+A'C) = (A+C) (A'+B) 5. XY + XZ + YZ

Perceptrons of artificial neural networks, Perceptrons: However the we...

Perceptrons: However the weights in any ANN are usually just real numbers and the learning problem boils down to choosing the best value for each weight in the network. Becaus

Artificial neural networks, Artificial Neural Networks: However imagin...

Artificial Neural Networks: However imagine now in this example as the inputs to our function were arrays of pixels and there actually taken from photographs of vehicles such

Recent parallel programming models, A model for parallel programming is an ...

A model for parallel programming is an abstraction in addition its machine architecture is independent. A model is able to be implemented on different hardware and memory architect

Name the software required to run video conferencing, Name The software req...

Name The software required to run video conferencing The software and hardware required to run video conferencing is very sophisticated. Apart from obvious items (that is large

Human computer interaction, Preamble The owner of the local shopping mal...

Preamble The owner of the local shopping mall, MaxiMart, has contracted you to assist in the design of an interactive directory. The interactive directory is to be permanently l

New execution of listpermutations, Update the permutation algorithm from th...

Update the permutation algorithm from the text to obtainthe correct list of permutations even if the string haves repeated letters. For example, if you call ListPermutations on the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd