Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is the difference between thread and process, What is the difference b...

What is the difference between thread and process?  Thread - is used to execute more than one program at a time. process - executes single program A thread is a path of e

Episodes - artificial intelligence , Episodes - artificial intelligence: ...

Episodes - artificial intelligence: If an agent's current choice of action not based on its past reactions, then the environment is known as episodic. In the non-episodic envi

Explain message switching, Explain Message switching. Recourse computer...

Explain Message switching. Recourse computer sends data to switching office that stores the data into buffer and seems for a free link. Sends link to other switching office, if

Explain three-way handshake mechanism, Explain Three-Way Handshake Mechanis...

Explain Three-Way Handshake Mechanism used by TCP to terminate a Session reliably. Just to guarantee that connection is sets up or terminated reliably, transfer control protoco

Explain the program translation model, Explain the program translation mode...

Explain the program translation model The program translation model makes the execution gap through translating a program written in a programming language, termed as the sou

Explain about micro-instruction formats, Q. Explain about Micro-instruction...

Q. Explain about Micro-instruction Formats? Now let's focus on format of a micro-instruction. The two widely used formats employed for micro-instructions are vertical and horiz

What is a deadlock, What is a Deadlock? Deadlock is a situation, in th...

What is a Deadlock? Deadlock is a situation, in that processes never complete executing and system resources are tied-up, preventing another job form starting. If the resou

Determine about selective set- logic micro operations, Selective set Th...

Selective set The selective-set operation sets to 1 bits in register A where there can corresponding 1's  in  register  B.  It  does  not  affect  bit  positions  which  have

What is artificial intelligence robotics, Artificial Intelligence Robotics ...

Artificial Intelligence Robotics covers all the material required to understand the principles behind the AI approach to robotics and to program an artificially intelligent robot f

Define memory utilization factor, Memory utilization factor shall be comput...

Memory utilization factor shall be computed as? Ans. memory in use/total memory connected.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd