Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain that datagram cannot be larger than mtu of a network, "A datagram c...

"A datagram cannot be larger than the MTU of a network over which it is sent." Is the statement true or false? Explain with the help of a suitable example. All hardware technol

What is difference between hold time and setup, What is difference between ...

What is difference between hold time and setup? The interviewer was looking for one exact reason, and it’s really a good answer as well..The hint is hold time doesn't depend onto c

Operator, write algorithm and draw flowchart for exchange the values of two...

write algorithm and draw flowchart for exchange the values of two variables.

Write the html code to web page to insert an image, Write the HTML code to ...

Write the HTML code to accomplish the web page to insert an image onto a page using good.gif as image and having "welcome" as the ALT text. The HTML code to accomplish the web

Accessing the operands - assembly language, Accessing the Operands: ...

Accessing the Operands: operands are usually place in one of two places: -registers (32 int, 32 fp) -memory (232locations) registers are -simple to spe

Dbms, what is cascading rolback?

what is cascading rolback?

Draw a circuit of TTL gates with Wired-AND connection, Draw a circuit of TT...

Draw a circuit of TTL gates with Wired-AND connection and explain its operation. Wired - AND Connection In digital IC's NAND and NOR gates are most frequently used. For th

Projects on cluster computing, Some famous projects on cluster computing ar...

Some famous projects on cluster computing are as follows: High Net Worth Project: (developed by: Bill McMillan, JISC NTI/65 - The HNW Project, University of Glasgow, The prim

Explain in detail about register transfer language, We have multiple instan...

We have multiple instances in RTL (Register Transfer Language), do you do anything special during synthesis stage? Whereas writing RTL(Register Transfer language),say in Verilo

Addressability of memory - computer architecture, Addressability: Loc...

Addressability: Location-addressable Each alone accessible unit of information in storage is chosen with its numerical memory address. In the modern computers, location-a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd