Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Natural and artificial intelligence, Since the term artificial intelligen...

Since the term artificial intelligence was defined in the 1950s, experts have disagreed about the difference between natural and artificial intelligence. Can computers be pro

What is the use of system.data.dlinq.dll, System.Data.DLinq.dll gives funct...

System.Data.DLinq.dll gives functionality to work with LINQ to SQL.

State about the data glove, State about the Data Glove  Data glove is u...

State about the Data Glove  Data glove is used to grasp a "virtual" object. The glove is constructed with a series of sensors that detect hand and finger motions. Electromagnet

Explain high performance of instruction execution, Q. Explain High performa...

Q. Explain High performance of Instruction execution? High performance of Instruction execution: While mapping of HLL to machine instruction the compiler favours relatively sim

Determine the object oriented features, Object Oriented Analysis  T h...

Object Oriented Analysis  T he basics of object oriented analysis with the help of object oriented features. Analysis  Analysis is not a solution of the problem. We w

Describe COMS inverter, Describe CMOS inverter. Ans: CMOS inverter t...

Describe CMOS inverter. Ans: CMOS inverter that is also called Complementary MOSFET Inverters, are several of the most broadly used and adaptable MOSFET inverters utilized i

State the types of common toes deformities a, Common toes deformities are: ...

Common toes deformities are: 1. Hallux valgus: Deviation of great toe towards the second toe resulting in prominence of first metatarsal head.  Later on there is formation of

Loop statement in both the pbo and pai events, Why do we need to code a LOO...

Why do we need to code a LOOP statement in both the PBO and PAI events for each table in the screen? We require coding a LOOP statement in both PBO and PAI events for every ta

Explain about synchronous dram, Q. Explain about Synchronous DRAM? One ...

Q. Explain about Synchronous DRAM? One of the most broadly used forms of DRAM is synchronous DRAM (SDRAM). Unlike the conventional DRAM that is asynchronous SDRAM exchanges dat

Differentiate between protected and real modes of an intel, Differentiate b...

Differentiate between protected and real modes of an Intel microprocessor Operation of Real mode interrupt: When microprocessor completes executing the current instruction, it

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd