Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

is risc always fast, It is fast because it has got separate program and da...

It is fast because it has got separate program and data memory(highly pipelined architecture)

Define object oriented and structured development, How object oriented deve...

How object oriented development is dissimilar from structured development object oriented development is dissimilar from structured development of the system. In the structure

Computer based accounting systems, For the purposes of this assignment, you...

For the purposes of this assignment, you are the accountant for an industrial property development company, Devprop Leasing Co., that typically develops warehouse and industrial co

What is self reference, What is self reference?  The Turing machine tha...

What is self reference?  The Turing machine that ignores its input and prints out a copy of its own description,   we call this as SELF. There is a computable function q: €*€*,

How many flip flops are required to construct decade countr, How many flip ...

How many flip flops are required to construct a decade counter ? Ans. 4 FlipFlop's are required because decade counter counts 10 states from 0 to 9 (that is from 0000 to 1001).

What are overlays, What are overlays? To enable a process to be larger ...

What are overlays? To enable a process to be larger than the amount of memory allocated to it, overlays are used. The idea of overlays is to keep in memory only those instructi

Control-centered virtual manufacturing, Control-Centered Virtual Manufactur...

Control-Centered Virtual Manufacturing This is the addition of simulations to control actual processes and models, permitting for seamless simulation for optimization throughou

By which finders are connected, In step by step switching line finders are ...

In step by step switching line finders are connected to the (A) Calling subscriber.                   (B) Switching network. (C) Called subscriber.                    (

How can data and instructions are put into the computers, Q. How can data a...

Q. How can data and instructions are put into the computers? The data and instructions to a computer are provided by external environment. It determines that input devices are

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd