Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is library, What is library? A library is a collection of classes ...

What is library? A library is a collection of classes that are useful in most of the contexts. Classes must have accurate and thorough explanations to help users.

What is bea weblogic?, Ans) BEA Web Logic is a J2EE application server and ...

Ans) BEA Web Logic is a J2EE application server and also an HTTP web server by BEA Systems of San Jose, California, for UNIX, Linux, Microsoft Windows, and other platforms. Web Log

Logic calculations are done in which type of registers, Accumulator is the ...

Accumulator is the register in which Arithmetic and Logic calculations are completed.

Operating system, define request edge and assignment edge

define request edge and assignment edge

Classification of systems, Classification of Systems Systems may be cat...

Classification of Systems Systems may be categorized as follows: a)  Formal or Informal b)  Abstract or Physical c)  Closed or Open d)  Automated orManual.

Which electro mechanical switch had fewer moving parts, The             el...

The             electro mechanical switch (developed in 1938) had fewer moving parts than earlier switches. (A)  No. 1ESS                                 (B)  Strowger (

Build and evaluate a GAN based model using KERAS, I did not see an option r...

I did not see an option related to machine learning. so i selected computer engineering. Use different datasets such as: paintings by Picasso, Van Gogh, DaVinci

What are the advantages of segmentation, What are its advantages? How is se...

What are its advantages? How is segmentation implemented in typical microprocessors? The first benefit that memory segmentation has is that only 16 bit registers are necessary

What is the use of urgent pointer in tcp segment, What is the use of urgent...

What is the use of urgent pointer in TCP segment? For accommodation out of band signaling, TCP permits the sender to identify data as urgent, implies that the receiving program

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd