Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Features of mpi-1, Features of MPI-1 Binding for FORTRAN and C ...

Features of MPI-1 Binding for FORTRAN and C Collective communication Communication domains and Process groups Point-to-point communication Virtual process

Storage devices, Logic manufactures have produced 'large scale' logic (LSI)...

Logic manufactures have produced 'large scale' logic (LSI) blocks to achieve complex functions; a typical set of logic functions is that of data storage. There are two main types o

Special theory of relativty, michelson-morley experiment-motivation and exp...

michelson-morley experiment-motivation and experimental setup

Harvard mark-I and the bug, The next important effort in the direction of d...

The next important effort in the direction of devising an electromechanical computer was made at Harvard University mutually sponsored by IBM and Department of UN Navy, Howard Aike

How will you prepare problem statement, How will you prepare problem statem...

How will you prepare problem statement? Problem statement should state what is to be completed and not how it is to be executed. It should be a statement of requirements not a

Explain the resolution of an ADC, Explain the Resolution of an ADC. ...

Explain the Resolution of an ADC. Ans. Resolution- It  is  the  smallest  possible  change  in  input  voltage  the same as  the  fraction  of percentage of the full s

What is meant by inter process communication, What is meant by inter proces...

What is meant by inter process communication? Inter process Communication: The OS give the means for cooperating processes to communicate with each other through an inter pro

Describe the interpretation features of vba, VBA is licensed to Microsoft a...

VBA is licensed to Microsoft and this compatible with and only Microsoft products. Code written is compiled by an intermediate language known as P-code and this is stored in hostin

Interpolation algorithm, Design two matlab algorithms for enlarging the 256...

Design two matlab algorithms for enlarging the 256x256 images into 512x512 images by using bilinear and bicubic interpolations   a)  Evaluate the interpolated images with the

How control functions help in signalling and control, How different control...

How different control function categories help in signalling and control. Events happening outside the exchange on the line units, trunk junctions and inter exchange signalin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd