Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Cookies, basic purpose of cookies

basic purpose of cookies

Explain optimizing transformations, Explain optimizing transformations? ...

Explain optimizing transformations? Optimizing transformations: It is a rule for rewriting a segment of a program to enhance its execution efficiency without influencing i

Explain about butterfly permutation, Q. Explain about Butterfly permutation...

Q. Explain about Butterfly permutation? Butterfly permutation:  This kind of permutation is attained by interchanging the most significant bit in address with least significant

Fully parallel associative processor (fpap), Fully Parallel Associative Pro...

Fully Parallel Associative Processor (FPAP):  This processor accepts the bit parallel memory organisation. FPAP has two type of this associative processor named as: Word Org

Show a string in assembly language, Q. Show a string in assembly language? ...

Q. Show a string in assembly language? MOV AH, 09H MOV DX, OFFSET   BUFF INT    21H Here data in input buffer stored in data segment is intended to be displayed on mo

Define service (within r/3), Define service (within R/3)? A service is...

Define service (within R/3)? A service is a process or group of processes that perform a exact system function and often give an application-programming interface for other pr

What are limitations of assembly language, What are limitations of assembly...

What are limitations of assembly language? i. It is changed to machine language using assembler which is time consuming when compared with machine language. ii. It is comple

Definitions of the procedures cons, Show that we can represent pairs of non...

Show that we can represent pairs of nonnegative integers using only numbers and arithmetic operations if we represent the pair a and b as the integer that is the product 2a3b. Give

What is the maximum number of fragments, What is the maximum number of frag...

What is the maximum number of fragments that can result from a single IP Datagram? Explain. To fragment a datagram for transmission across a network, a router utilizes the netw

Is the basic list deleted when the new list is created, Is the basic list d...

Is the basic list deleted when the new list is created? No.  It is not removed and you can return back to it using one of the standard navigation functions like clicking on th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd