Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is interrupt and function of color graphics adopter, Q. What is inter...

Q. What is interrupt? How it is useful in controlling I/O operations. Q. Explain function of Color Graphics Adopter card and Diskette Drive Adopter Card.

Describe about the layered computer design, Describe about the Layered comp...

Describe about the Layered computer design Introduction Layered computer design focuses on computer design. It uses top-down, layered approach to design and also to improve

Explain about workstations, Q. Explain about Workstations? The workstat...

Q. Explain about Workstations? The workstations are used for engineering applications like CAD/CAM or other types of applications which need a moderate computing power and rela

Reduce minimum literals and derive their complements, Q. Reduce following t...

Q. Reduce following to minimum literals and derive their complements. 1. [(AB)'A][(AB)'B] 2. ABC(ABC' + AB'C + A'BC) 3. (A+C+D) (A+C+D') (A+C'+D)(A+D')

Associative array processing, Associative Array Processing Consider tha...

Associative Array Processing Consider that a list of record or a table is stored in the memory and you want to search some information in that list. For example, the list havin

What is the functionality of remote login, What is the functionality of Rem...

What is the functionality of Remote Login? Remote Login gives similar functionality of telnet, along with the added functionality of not involving a password from trusted cli

Describe the lists used in html, Q. Describe the LISTS used in html? Li...

Q. Describe the LISTS used in html? Lists are used when data are to be mentioned in form of points such as: causes of a particular issue, list of items etc. Lists break up mono

Arbitrary categorisation - learning decision trees, Arbitrary categorisatio...

Arbitrary categorisation - learning decision trees: Through visualising  a set of boxes with some balls in. There if all the balls were in a single box so this would be nicely

Explain message switching, Explain Message switching. Recourse computer...

Explain Message switching. Recourse computer sends data to switching office that stores the data into buffer and seems for a free link. Sends link to other switching office, if

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd