Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is reduction, What is reduction?  A reduction is a way of changing...

What is reduction?  A reduction is a way of changing one problem into another in such a way that a solution to the second problem can be used to explain the first problem.

Single instruction and multiple data stream (simd), Single Instruction and ...

Single Instruction and Multiple Data stream (SIMD) In this organisation, multiple processing elements are working under the control of a one control unit. It has multiple data

The concept of parallel execution and concurrent , The Concept of Parallel ...

The Concept of Parallel Execution and Concurrent Real world systems are obviously concurrent, and computer science is about modelling the actual world. Examples of actual worl

What is presentation layer, Q. What is Presentation layer? Presentatio...

Q. What is Presentation layer? Presentation layer: When two hosts are communicating with each other they might use different coding standards and character sets for represent

Integrated services digital network service, Whole idea of ISDN is to digit...

Whole idea of ISDN is to digitize the telephone network to permit transmission of video, audio and text over existing telephone lines. The purpose of ISDN is to provide fully integ

Explain jk flip-flop using sr flip-flop, Q. Explain 4 bit Ripple counter wi...

Q. Explain 4 bit Ripple counter with necessary diagram. Q. Explain JK Master-slave Flip-flop with block diagram and logic design. Q. Explain JK flip-flop using SR flip-flop

Block format and disk layout on cd-rom, Q. Block Format and Disk Layout on ...

Q. Block Format and Disk Layout on CD-ROM? A typical block format is displayed in Figure (a). It comprises the subsequent fields: Sync: Sync field identifies beginning o

What is the use of object factories, Factory methods that will be used to m...

Factory methods that will be used to make objects just like in a static way.

Explain stored program control, Explain Stored Program Control. Stored...

Explain Stored Program Control. Stored Program Control: Modern digital computers utilize the stored programmed idea. Now, a program or a set of instructions to the computer i

Returns and procedures definitions in 8086, Q. Returns and Procedures defin...

Q. Returns and Procedures definitions in 8086? 8086 microprocessor supports RET and CALL instructions for procedure call. CALL instruction not only branches to indicate address

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd