Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain clone process, Explain Clone process. A clone process is genera...

Explain Clone process. A clone process is generated using primitive type clone by duplicating its parent process. However unlike traditional processes it might be share its con

Spirit duplicating of information, Spirit Duplicating Equipment Requir...

Spirit Duplicating Equipment Required Spirit Duplicator (also known as hectograph) Thermal copier (optional) Materials Masters Hectographic carbon COPY pa

Create perl scripts, Create Perl scripts as required below: a) Create a ...

Create Perl scripts as required below: a) Create a script named select_by_attribute.pl that accepts the name of a LibML documentand the name of a particular attribute from the c

#chemistry, Please explain the construction and working of calomel electrod...

Please explain the construction and working of calomel electrode..

Define switching element for two stage non-blocking network, A two stage no...

A two stage non-blocking network requires twice the number of switching elements as the single stage non-blocking network. It is true or false. Ans: It is true that a two st

Breakthrough for computer engineering, what is the importance of chemistry ...

what is the importance of chemistry for computer engineering?

How society is affected thorugh internet, How society is affected thorugh I...

How society is affected thorugh Internet Buying goods and services (for example banking) over the internet has both negative and positive aspects on society. These can be expl

List criteria of data structures used in language processing, List the crit...

List the criteria on the basis of which data structures used in language processing can be classified. In language processing the data structures utilization can be classified

What is a process scheduling, What is a Process Scheduling? Scheduling...

What is a Process Scheduling? Scheduling is a key element of the workload management software that usually performs several or all of: Queuing Scheduling Monito

Design a 32:1 multiplexer, Design a 32:1 multiplexer using two 16:1 multipl...

Design a 32:1 multiplexer using two 16:1 multiplexers and a 2:1 multiplexer Ans. Design a 32 X 1 MUX by using two 16 X 1 MUX and one 2 X 1. Now here total 32 input lines

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd