Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Differentiate between time sharing & batch operating system, Differentiate ...

Differentiate between Batch Operating System and Time Sharing Operating System? Batch operating systems : A batch is a sequence of jobs. Such batch is submitted to batch proce

What is insert module and goal seek functions there in vba, Visual basic ap...

Visual basic applications have very rich and flexible applications but there is single limitation when using pointer function. Windows API has limited support for function pointers

What is byte addressable memory, What is byte addressable memory? The a...

What is byte addressable memory? The assignment of successive addresses to successive byte locations in the memory is known as byte addressable memory.

What is batch processing, What is Batch processing In this process, a n...

What is Batch processing In this process, a number of tasks (or jobs) are all collected together over a set period of time. They are then all loaded into the computer system (i

Explain parallelism conditions, Parallelism Conditions As discussed ear...

Parallelism Conditions As discussed earlier, parallel computing needs the segments to be executed in parallel should be independent of each other. So before executing paralleli

How do we synthesize verilog into gates with synopsys, How do we synthesize...

How do we synthesize Verilog into gates with Synopsys?  The answer can, of course, occupy various lifetimes to completely answer.. BUT.. a straight-forward Verilog module can b

Sap security audit log, You are required to use software of your choice (sp...

You are required to use software of your choice (spreadsheet, database, statistical package etc) to analyze the provided SAP security audit log data ( Userdata.xls ), generate appr

Explain busy hour calling rate in telephone traffic, With reference to tele...

With reference to telephone traffic, explain the terms BHCR. BHCR: Busy hour calling rate is explained as the average number of calls originated through a subscriber througho

Explain about the client/server computing, Explain about the Client/Server ...

Explain about the Client/Server Computing? Although there are different various configurations, various hardware and software platforms and even various network protocols into

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd