Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

A universal shift register can shift in both the lef, #question.A universal...

#question.A universal shift register can shift in both the left-to-right and right-to-left directions, and it has parallel-load capability. Draw a circuit for such a shift register

Define busy waiting and spinlock, Define busy waiting and spinlock.  Wh...

Define busy waiting and spinlock.  When a process is in its critical section, any other process that tries to enter its critical section must loop continuously in the entry cod

What are the objectives of usb, What are the objectives of USB? a) Simp...

What are the objectives of USB? a) Simple b) Low cost c) Easy to use d) Supports wide range of data transfer characteristics e) Plug and play mode of operation

Develop a calculator in masm, Assignment:  develop a calculator in MASM. ...

Assignment:  develop a calculator in MASM. Text chapters covered:  1 through 4, 5.4, 5.5, 6.3, 7.4 You will develop a "calculator" algorithm in MASM using reverse-polish nota

Inspirations of artificial intelligence, Inspirations of artificial intelli...

Inspirations of artificial intelligence: Artificial Intelligence research can be easily understood by following example in terms of how the following question has been answere

How many types of keys used to encrypt and decrypt data, How many types of ...

How many types of keys used to encrypt and decrypt data in Secure Sockets Layer? Two forms of keys are used as ciphers to decrypt and encrypt data. Private keys are referred to

What are the two primary models of supply chain management, What are the tw...

What are the two primary models of Supply Chain Management? The Two Primary models of Supply Chain Management are:- 1.  Porter's Value Chain Model 2. Supply Chain Model

Differentiate between raid 0 and raid 1, Problem 1 a) Give three reaso...

Problem 1 a) Give three reasons why connecting peripherals directly to the system bus are not a good practice. b) Name five categories in which the major functions on requ

Explain about microcomputers, Q. Explain about Microcomputers? Microco...

Q. Explain about Microcomputers? Microcomputers: A microcomputer's CPU is a microprocessor. They are characteristically used as single usercomputer though present day microco

Define rules for reducing karnaugh maps, Define Rules for Reducing Karnaugh...

Define Rules for Reducing Karnaugh Maps? The rules for reducing Karnaugh Maps (k- maps) are as follows: All of the 1's in the Karnaugh Map are called as minterms. The

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd