Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How can we set the table spaces and extent sizes, How can we set the table ...

How can we set the table spaces and extent sizes? You can state the extent sizes and the table space (physical storage area in the database) in which a transparent table is to

Define is a personality, Define is a Personality. In order to allow pro...

Define is a Personality. In order to allow programs coming other operating system to be run in Linux, Linux supports the idea of personalities. Every method is assign to an imp

List the key notions concerning macro expansion, List the key notions conce...

List the key notions concerning macro expansion. Two key notions relating to macro expansion is: 1. Expansion time control flow- Determines the order of model statements tha

Appropriate name for the superclass, Suppose that your team is then asked t...

Suppose that your team is then asked to expand the system. The publisher now wishes to make other computer science publications. As a team member, you are asked to make a class tha

Explain block diagram for 4 bit parallel adder, What is parallel adder? Dra...

What is parallel adder? Draw and explain block diagram for 4 bit parallel adder. Ans: By using full adder circuit, any two bits can be added along with third input like a ca

Validate the xml document , As an XML expert you are needed to model a syst...

As an XML expert you are needed to model a system for an online furniture shop. After an interview with the shop manager you have the certain information: The detail of th

External links to files, Somehow, the worksheet has external links to files...

Somehow, the worksheet has external links to files that are no longer around. How can we delete the links? Ans) This happens all of the time to MrExcel. I downloaded a little

Differentiate between hardware and software, Differentiate between Hardware...

Differentiate between Hardware and Software Another classification is software vs. hardware. Hardware is the collection of physical components, like chips, wires, PCBs, connect

How swapping increase overheads of the operating systems, Does swapping inc...

Does swapping increase the Operating Systems' overheads? Justify your answer. A process can be swapped out temporarily of memory to a backing store and after that brought back

Explain logical shift micro-operations, Q. Explain logical shift Micro-oper...

Q. Explain logical shift Micro-operations? In logical shift data entering by serial input to left most or right most flip-flop (which depends on right or left shift operations

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd