Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What do you mean by drive cache, Q. What do you mean by Drive Cache? Di...

Q. What do you mean by Drive Cache? Disk cache may be a part of RAM sometimes known as soft disk cache which is used to speed up access time on a disk. In latest technologies s

Define seek time and latency time, Define seek time and latency time. ...

Define seek time and latency time.  The time taken by the head to move to the appropriate cylinder or track is known as seek time. Once the head is at right track, it must wai

Find out the decimal equivalent of binary number, The decimal equivalent of...

The decimal equivalent of Binary number 10101 is ? Ans. 1x2 4 + 0x2 3 +1x2 2 +0x2 1 + 1x2 0 = 16 + 0 + 4 + 0 + 1 = 21.

Define electronic data interchange, Define Electronic Data Interchange. ...

Define Electronic Data Interchange. An EDI stand for Electronic Data Interchange is used by organizations for transactions which occur on regular basis to a pre-determined for

Describe about the desk top publishing, Desk Top Publishing (DTP) As wo...

Desk Top Publishing (DTP) As word processors develop increasingly more sophisticated features, differences with desk top publishing (DTP) packages becomes more and more blurred

The variables that are declared outside all functions, The variable that ar...

The variable that are declared outside all the functions are called The variables that are declared outside every functions are known as global variable.

Additions of two numbers by using 2’s complement, Add -20 to +26 by using 2...

Add -20 to +26 by using 2's complement ? Ans. Firstly convert the both numbers 20 and 26 in its 8-bit binary equivalent and determine the 2's complement of 20, after that add -

Different edi components and services, Different EDI components and service...

Different EDI components and services  Three main components containing services in EDI System are as follows:  •  Application Service: Gives the means of integrating existi

Give the solutions for critical section problem, Give the solutions for cri...

Give the solutions for critical section problem? A solution to the critical section problem must specify the subsequent requirements. (a) Mutual exclusion (b) Progress (c)

Average number of instructions, Consider a processor with a 4-stage pipelin...

Consider a processor with a 4-stage pipeline. Each  time a conditional branch is encountered, the pipeline must be flushed (3 partially completed instructions are lost). Determine

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd