Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Drawbacks of specifying parameter assignments using defparam, The disadvant...

The disadvantages of specifying parameter assignments using defparam are: -  Parameter  is  essentially specified  by  the  scope  of  hierarchies  underneath  which  it exists

Show the fundamental process of instruction execution, Q. Show the fundamen...

Q. Show the fundamental process of instruction execution? The fundamental process of instruction execution is:  1. Instruction is fetched from memory to CPU registers (calle

Explain function of dual slope analogue to digital converter, Draw and expl...

Draw and explain the function of dual slope analogue to digital converter. Derive the equations used. Ans.               Dual slope A/D converter : This has 4 main blocks.

Set up a standard population model structure, Set up a standard population ...

Set up a standard population model structure. The population will begin with 24 people. We do not have actual data to support a birth rate, but we could calculate a reasona

Problems.., what are the different types of tablets?

what are the different types of tablets?

Explain about synchronous dram, Q. Explain about Synchronous DRAM? One ...

Q. Explain about Synchronous DRAM? One of the most broadly used forms of DRAM is synchronous DRAM (SDRAM). Unlike the conventional DRAM that is asynchronous SDRAM exchanges dat

Differentiate between the message and method in c++, Message in C++ : *...

Message in C++ : * Objects converse by sending messages to each other. * A message is sent to invoke a method in C++.   Method in C++: * Gives response to a message

Main features of TCP, The main features of TCP are: Reliability: TCP...

The main features of TCP are: Reliability: TCP makes sure that any data sent by a sender arrives at destination as it was sent. There can't be any data loss or change in the

Differentiate between adaptive and non-adaptive routing, Differentiate betw...

Differentiate between adaptive and non-adaptive routing. Adaptive routing defines the ability of a system, by which routes are characterised through their destination, to cha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd