Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Displays a format of floating-point number, Q. Displays a format of floatin...

Q. Displays a format of floating-point number? A floating binary number +1010.001 in a 16-bit register is able to be represented in normalised form (presuming 6 bits for expone

What is fish bone diagram, What is Fish Bone Diagram? Or Explain Ishikawa D...

What is Fish Bone Diagram? Or Explain Ishikawa Diagram. Fish Bone Diagram is also known as Ishikawa Diagram or Cause and Effect Diagram. It is known as Fish Bone Diagram be

Hazard, how to calculate delay for hazard?

how to calculate delay for hazard?

Drag and drop state numbers and functions in vb, State 0 Source control is ...

State 0 Source control is being dragged with the variety of a target. 1 Out of the variety of a target. 2 One position in the target to one another.

Explain in detail about the dynamic timing, Explain in detail about the Dyn...

Explain in detail about the Dynamic timing a. Design is simulated in full timing mode. b. Not all possibilities tested, as it is dependent on input test vectors. c. Simul

Dynamic configuration of parallel virtual machine, Q. Dynamic Configuration...

Q. Dynamic Configuration of parallel virtual machine? int pvm_addhosts( char **hosts, int nhost, int *infos ) Add hosts to virtual machine. hosts is an arra

Artificial neural networks - artificial intelligence, Artificial Neural Net...

Artificial Neural Networks - Artificial intelligence: Decision trees, while strong, are a easy representation method. While graphical on the surface, they may be seen as disjun

Elaborate state space search briefly, Artificial Intelligence 1. Explai...

Artificial Intelligence 1. Explain about artificial intelligence? What are the achievements of AI? 2. Elaborate state space search briefly. 3. Prove that A* is optimal.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd