Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define the types of software life cycle, Define the types of software life ...

Define the types of software life cycle Any system progress refers to the initial part of the software life cycle: analysis, design, and implementation. During object oriented

Example of perceptrons, Example of perceptrons: Here as an example fun...

Example of perceptrons: Here as an example function in which the AND boolean function outputs a 1 only but if both inputs are 1 and where the OR function only outputs a 1 then

What is an "on request field" statement, What is an "on request Field" stat...

What is an "on request Field" statement? ON REQUEST The ABAP/4 Module is known as only if the user has entered the value in the field value as the last screen display .Th

.master-slave flip flop, JK, SR, D master FF 1)draw block diagram 2) combin...

JK, SR, D master FF 1)draw block diagram 2) combinational circuits using NOR & NAND gate thank you

What is meant by a field, What is meant by a field The consecutive nonw...

What is meant by a field The consecutive nonwhite space characters that define a data item collectively define a field. It is possible  to limit the number of such characters b

When is a memory unit called as ram, When is a memory unit called as RAM? ...

When is a memory unit called as RAM? A memory unit is called as RAM if any location can be accessed for a read or writes operation in some fixed quantity of time that is indepe

Multithreaded architecture, Q. Multithreaded Architecture? It is clear ...

Q. Multithreaded Architecture? It is clear at the moment if we provide a lot of contexts to multiple threads then processors with numerous contexts are known as multithreaded s

By which except ions of type error in java are handled, Except ions of type...

Except ions of type error in JAVA are handled by? Except ions of type error in the JAVA are handled through JAVA run time environment.

Explain about olap, OLAP is called as online analytical processing which gi...

OLAP is called as online analytical processing which gives answers to queries which are multi dimensional in nature. It composes relational reporting and data mining for giving sol

Define rules for reducing karnaugh maps, Define Rules for Reducing Karnaugh...

Define Rules for Reducing Karnaugh Maps? The rules for reducing Karnaugh Maps (k- maps) are as follows: All of the 1's in the Karnaugh Map are called as minterms. The

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd