Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the logic micro-operations, Q. What are the Logic Micro-operations...

Q. What are the Logic Micro-operations? Logic operations are fundamentally binary operations that are performed on string of bits stored in the registers. For a logic micro-ope

What is flag, Flag is a flip-flop used to kept the information about the st...

Flag is a flip-flop used to kept the information about the status of a processor and the status of the instruction implemented most recently A software or hardware mark that si

Example on distribution of data, Q. Example on Distribution of Data? !H...

Q. Example on Distribution of Data? !HPF$ PROCESSORS P1(4) !HPF$ TEMPLATE T1(18) !HPF$ DISTRIBUTE T1(BLOCK) ONTO P1  Consequently of these instructions distribution of

Find the average of two values, Q. Find the average of two values? Find...

Q. Find the average of two values? Find the average of two values which are stored in  ; Memory locations named FIRST and SECOND  ; And puts result in memory location AVG

Define the term grade of service, Define the term Grade of Service. Gr...

Define the term Grade of Service. Grade of Service: In loss systems, the traffic carried through the network is usually lower than the actual traffic offered to the network t

Critical capabilities for superior firm performance, What are the critical ...

What are the critical capabilities for superior firm performance in e-commerce? Three firm capabilities which are critical for superior firm performance within e-commerce are:

Explain booth''s multiplication algorithm, Computer Organization 1. Dr...

Computer Organization 1. Draw a flowchart of a Booth's multiplication algorithm and explain it. 2. What is the concept of memory interleaving? 3. Explain virtual memory? Expla

Automatic typewriter in information distribution, Automatic typewriter : I...

Automatic typewriter : It is a power-driven machine, which automatically types a standard pro forma from a previously punched or stencilled master. When the master is placed on th

Basic working of semiconductors, Q. Basic working of Semiconductors? Se...

Q. Basic working of Semiconductors? Semiconductors are crystalline solid materials whose resistivities have values between those of conductors and insulators. Conductivity rang

Analysis of amdahls law, Q. Analysis of Amdahls law? The conclusions of...

Q. Analysis of Amdahls law? The conclusions of analysis of Amdahl's law are: 1) To optimize performance of parallel computers modified compilers should be developed that sho

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd