Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What happens if acknowledge() is called within a transaction, As per the JM...

As per the JMS specification, when you are in a transaction, the acknowledge Mode is ignored. If acknowledge() is known as within a transaction, it is ignored.

Gather some ram data after system was powered off, (a) When a forensic exa...

(a) When a forensic examiner arrives at a crime scene, the first task done is referred to as "Incident Response". Summarize the different incident response tasks done in 10 steps.

What is arithmetic and logic unit, What is Arithmetic and Logic Unit Ar...

What is Arithmetic and Logic Unit Arithmetic and Logic Unit: The ALU is the 'core' of any processor. It implements all arithmetic operations (addition, multiplication, subtract

Explain dos function call with one illustration, Explain DOS function call ...

Explain DOS function call with one illustration DOS function call In order to use DOS function calls, always place function number into register AH and load all other re

Concept of multithreading, Concept of Multithreading: These troubles incre...

Concept of Multithreading: These troubles increase in the design of large-scale multiprocessors such as MPP as discussed above. Thus, a solution for optimizing this latency should

Average enzyme activity , Activity of a some  enzyme was calculated  in ext...

Activity of a some  enzyme was calculated  in extracts from brain, heart and lung. In every  tissue,  the activity was calculated  various  times, giving the following results (in

How does vb.net achieve polymorphism, How does VB.NET/C# achieve polymorphi...

How does VB.NET/C# achieve polymorphism?  VB.Net / C# provide polymorphism through the following mechanisms: 1. Inheritance - base class gives overridable methods which ar

What is strong-typing versus weak-typing, What is strong-typing versus weak...

What is strong-typing versus weak-typing? Which is preferred? Why? Strong type is checking the types of variables as early as possible, usually at compile time. Whereas weak ty

What is sap luw or update transaction, What is SAP LUW or Update Transactio...

What is SAP LUW or Update Transaction? Update transaction (or "SAP LUW") This is a set of updates terminated by an ABAP/4 commit.  A SAP LUW may last much longer than a data

Function makestk-predicate function emptystk, 1. Create the following ADTs....

1. Create the following ADTs. (a) Write the constructor function makestk, predicate function emptystk and mutator functions pushstk and popstk: i. makestk returns a new stack

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd