Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Interpolation search, Interpolation Search The next task is to implemen...

Interpolation Search The next task is to implement a variable size decrease-and-conquer solution to search. See Levitin [2007] pp 190 for a detailed description of the interpol

Is it possible to pass data and include program explicitly, Is it possible ...

Is it possible to pass data to and from include programs explicitly? No.  If it is needed to pass data to and from modules it is needed to use subroutines or function modules.

Chemistry, what are the applications of photochemistry?

what are the applications of photochemistry?

Re:- exam help, Hello there i have 4 exams of ICT and i am after a tutor wh...

Hello there i have 4 exams of ICT and i am after a tutor who can help me in those 4 subjects. One hour for each subjects will be good for me as i have sample papers ready for all s

Explain briefly how firewalls protect network, Explain briefly how firewall...

Explain briefly how firewalls protect network.       A firewall is simply a program or hardware device that filters the information coming by the Internet connection into your

Convert following decimal numbers into 9s & 10s complement, Q. Convert the ...

Q. Convert the following decimal numbers into 9s & 10s complement: 1) 3654 2) 99 3) 18.293 Q. Convert the following binary numbers into 1s& 2s complement: 1) 1101

Explain load sharing processor configuration of spc, Explain how a centrali...

Explain how a centralized SPC organization works under load sharing operation. Under load sharing operation, an incoming call is allocated randomly or in a predetermined sequen

What are advantages and disadvantages of using eeprom, What are advantages ...

What are advantages and disadvantages of using EEPROM? The benefits are that EEPROM do not have to be removed for erasure. Also it is possible to delete the cell contents selec

Discuss the general procedure of booting process, Question 1 What are t...

Question 1 What are the different schemes in power management? Explain 2 Explain the functions of parallel port in detail 3 (a) List and explain the functions of keyboard

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd