Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Initial considerations in problem solving, Initial considerations in proble...

Initial considerations in problem solving: Three initial considerations in problem solving for easiest(as described in Russell and Norvig):  Initial State  First

Define memory cycle time, Define memory cycle time? It is the time dela...

Define memory cycle time? It is the time delay needed between the initiations of two successive memory operations. Eg. The time among two successive read operations.

Micro programmed control and hardwired control, Explain micro programmed co...

Explain micro programmed control. Ans: A micro programmed control unit is made around storage till is called a control store where all the control signals are stored in a prog

Explain erasable programmable rom (eprom) - computer memory, Explain Erasab...

Explain Erasable Programmable ROM (EPROM) - Computer Memory? An EPROM is a ROM that can be reprogrammed and erased. A little glass window is installed at the top of the ROM pac

Rational schema, write the rational schema and draw it’s dependency diagram...

write the rational schema and draw it’s dependency diagram. Identify all dependencies.

Define process, Define Process Process is a program in execution; proc...

Define Process Process is a program in execution; process execution should progress in sequential fashion. A process involves: a) Program counter  b) Stack c) Data se

Determine the importance of computer hardware, Determine the importance of ...

Determine the importance of computer Hardware Hardware forms the greatest asset of the company, but it reaches obsolescence very quickly. Normally, it is said that every six mo

Define parameters used in program annotation, Q. Define Parameters used in ...

Q. Define Parameters used in Program Annotation? Parameters: A parameter refines and extends the meaning that assembler attributes to keyword in a statement.  Number of param

Find the number of PROM chips & address lines, The capacity of 2K × 16 PROM...

The capacity of 2K × 16 PROM is to be expanded to 16 K × 16.  Find the number of PROM chips required and the number of address lines in the expanded memory. Ans. Capacity requi

Enumerate in brief about the intranet security policy, Enumerate in brief a...

Enumerate in brief about the Intranet security policy An Intranet security policy is a very broad topic and it cannot be covered easily in few pages since it differs from situa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd