Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Pre order given find post order ?, The preorder traversal sequence of a bin...

The preorder traversal sequence of a binary search tree is 30, 20, 10, 15, 25, 23, 39, 35, 42. Which one of the following is the postorder traversal sequence of the same tree?

Expand cpi-c, Expand CPI-C. CPI-C= Common Program Interface Communica...

Expand CPI-C. CPI-C= Common Program Interface Communication.

Sap system configuration, SAP system configuration includes It include...

SAP system configuration includes It includes :- a) Dialog tasks b) Update tasks.

Compare pre-emptive and non-preemptive scheduling policies, Compare pre-emp...

Compare pre-emptive and non-preemptive scheduling policies. We preempt the currently executing process in preemptive scheduling. In non-preemptive we permit the current process

Give difference between compiler and interpreter, Give difference between c...

Give difference between compiler and interpreter. Compiler: It is a translator for machine independent HLL as FORTRAN and COBOL etc. Interpreter: It analysis the source

Explain the difference between a subroutine and macro, Explain the differen...

Explain the difference between a subroutine & macro. It is inefficient to have to write code for standard routines.  For instance reading a character form the keyboard or savin

Explain working of d flip -flop, Q. Explain working of D Flip -Flop? D ...

Q. Explain working of D Flip -Flop? D (data) flip-flop is modification of RS flip-flop. Problem of undefined output in SR flip-flop when both R and S become 1 gets avoided in D

Instruction cycle-flynn’s classification, Instruction Cycle The instruc...

Instruction Cycle The instruction cycle consists of a series of steps needed for the implementation of an instruction in a program. A typical instruction in a program is descri

First-order models, First-Order Models: Here if we proposed first-orde...

First-Order Models: Here if we proposed first-order logic as a good knowledge representation language than propositional logic is just because there is more expressive than we

How 2-domain name servers contain exactly same set of names, Does it makes ...

Does it makes sense for two domain name servers to contain exactly the same set of names? Why? Yes. This is very advantageous for two domain servers having similar set of names

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd