Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is dispatch unit, What is dispatch unit? A separate unit which we ...

What is dispatch unit? A separate unit which we call the dispatch unit fetch instructions from the front of the queue and sends them to the execution unit. The dispatch unit al

Write a subroutine in c for toggling the cursor, Write a subroutine in C fo...

Write a subroutine in C for toggling the cursor using old directives. ; ; use small memory model for C - near code segment _DATA SEGMENT WORD   'DATA'   CURVAL EQU   [B

Name the software required to run video conferencing, Name The software req...

Name The software required to run video conferencing The software and hardware required to run video conferencing is very sophisticated. Apart from obvious items (that is large

Positive logic nand gate is equivalent to negative logic nor, Show that a p...

Show that a positive logic NAND gate is equivalent to negative logic NOR gate. Ans:  Positive logic denotes True or 1 with a high voltage and False or 0 with a low volt

What is analysis iteration, Analysis Iteration   To understand any prob...

Analysis Iteration   To understand any problem completely you have to repeat task which implies that analysis requires repetition. First, just get overview of problem, make a r

Explain about iframe, Q. Explain about IFRAME? is an HTML 4.0 addition...

Q. Explain about IFRAME? is an HTML 4.0 addition to frames toolbox. Presently only MSIE supports . Unlike frames created employing and

Implement or, Q. Write a program to implement OR, NOR, AND and NAND gates ...

Q. Write a program to implement OR, NOR, AND and NAND gates using and without using Bit wise operator. The menu should be as follows: I. Using Bit Wise operator II. Withou

Name the approaches used for generating the control signals, What are the t...

What are the two approaches used for generating the control signals in proper sequence? Hardwired control Micro programmed control

Fundamental types of flash memory, Q. Fundamental types of flash memory? ...

Q. Fundamental types of flash memory? Code Storage Flash which is made by Intel, AMD, Atmel. It stores programming algorithms and it is largely found in cell phones. Data

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd