Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the methods for handling deadlocks, What are the methods for handl...

What are the methods for handling deadlocks?  The deadlock problem can be dealt with in one of the three ways:  a. Use a protocol to prevent or avoid deadlocks, make sure th

Sequential logic gates - sr flip flop, Sequential Logic Gates SR flip ...

Sequential Logic Gates SR flip flop                                                                                                                    1)

Game playing - artificial intelligence, Game Playing: We have now disp...

Game Playing: We have now dispensed with the necessary background material for AI problem solving techniques, and we just considered to looking at particular types of problems

What is instruction register, Q. What is Instruction Register? Instruct...

Q. What is Instruction Register? Instruction Register (IR): Here instructions are loaded before execution. Comments on figure above are as below: All representations are

How can data and instructions are put into the computers, Q. How can data a...

Q. How can data and instructions are put into the computers? The data and instructions to a computer are provided by external environment. It determines that input devices are

Define the aims of program generation activity, Program generation activity...

Program generation activity aims at? Ans. At automatic generation of program the program generation activity aims.

#, advantages of dda line algoritm

advantages of dda line algoritm

Differentiate memory mapped and isolated i/o, Q. Explain how does CPU perf...

Q. Explain how does CPU perform Read and Write operation on peripheral device taking suitable example in case of Asynchronous Technique. Differentiate Memory mapped and Isolated

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd