Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How to apply color and style, Q. How to Apply Color and Style? 1.  In f...

Q. How to Apply Color and Style? 1.  In first text description layout cell, select heading text from the word "Fly" through the word "Mountains." 2.  In Property inspector,

What is bea weblogic?, Ans) BEA Web Logic is a J2EE application server and ...

Ans) BEA Web Logic is a J2EE application server and also an HTTP web server by BEA Systems of San Jose, California, for UNIX, Linux, Microsoft Windows, and other platforms. Web Log

Displacement addressing mode - computer architecture, Displacement and  Sta...

Displacement and  Stack Addressing  mode - computer architecture: Displacement Addressing: In displacement addressing mode there are three types of addressing mode. They

Explain about RISC pipelining, Q. Explain about RISC PIPELINING? Instru...

Q. Explain about RISC PIPELINING? Instruction pipelining is frequently used to increase performance. Let's consider this in context of RISC architecture. In case of RISC machin

Fuzzy logic - artificial intelligence, Fuzzy Logic: In the logics we a...

Fuzzy Logic: In the logics we are here described above, what we have been concerned with truth: whether propositions and sentences are true. Moreover, with some natural langua

Period and space tradeoffs - artificial intelligence, Period and Space Trad...

Period and Space Tradeoffs - artificial intelligence: In practice, you are going to stop your agent for long term using in searching goal at some stage if it has not found a s

Computer networks, distributed & centralized system in computer network

distributed & centralized system in computer network

Contraposition, Contraposition : The contraposition equivalence is as ...

Contraposition : The contraposition equivalence is as follows:  So it may seem a small strange at first, this means that it appears which we have said nothing in the f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd