Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Adding server-side include to the page, Step 1: Click on the icon in the ob...

Step 1: Click on the icon in the object tool bar Or Insert -> SSI Step 2: Select the file Step 3: Add the file Step 4: Provide the URL (where to be attached) Step

Determine the use of loop instruction, Q. Determine the use of LOOP instruc...

Q. Determine the use of LOOP instruction? Program: This program prints the alphabets (A-Z) ; Register used: AX, CX, DX CODE SEGMENT ASSUME: CS: CODE.     MAINP:

Prepare a decision tree, A part of an aircraft engine can be given a test b...

A part of an aircraft engine can be given a test before installation.  The test has a 75% chance of revealing a defect if it is present, and the same chance of passing a sound part

Define is a personality, Define is a Personality. In order to allow pro...

Define is a Personality. In order to allow programs coming other operating system to be run in Linux, Linux supports the idea of personalities. Every method is assign to an imp

Enumerate the history of computers, Enumerate the History of computers ...

Enumerate the History of computers Basic information about technological development trends in computer in past and its projections in future. If you want to know about compute

History of e-commerce, In 1960: The purpose of e-commerce was to exchange t...

In 1960: The purpose of e-commerce was to exchange the electronic data. In 1970s: Electronic Fund Transfers or EFT was developed which considered as huge impact in the emerging

State about the data glove, State about the Data Glove  Data glove is u...

State about the Data Glove  Data glove is used to grasp a "virtual" object. The glove is constructed with a series of sensors that detect hand and finger motions. Electromagnet

Maximum number of nodes in a binary tree, The maximum number of nodes in a ...

The maximum number of nodes in a binary tree of depth 5 is 31 is the maximum number of nodes in a binary tree

Explain time complexity in parallel algorithms, Q. Explain Time Complexity ...

Q. Explain Time Complexity in Parallel algorithms? As it takes place nearly everyone who implement algorithms wish to know how much of an individual resource (for example time

Determine the process of kernel, What are the events done by the Kernel aft...

What are the events done by the Kernel after a process is being swapped out from the main memory? When Kernel changes the process out of the primary memory, it performs the fol

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd