Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What do you mean by true complement method, Q. What do you mean by True Com...

Q. What do you mean by True Complement Method? Explain in detail. Q. Show IEEE format for (12.75)10. Q. What are the various ways to represent Negative Numbers in computer sy

What is the difference between proc. sent by val and by ref, What is the di...

What is the difference between proc. sent BY VAL and By Ref? BY VAL: Alters will not be reflected back to the variable. By REF: Alters will be reflected back to that variab

The constructed datatype of c, The constructed datatype of C is known as ...

The constructed datatype of C is known as Structure is a constructed datatype of C.

Why we need parallel programming languages, Q. Why we need parallel program...

Q. Why we need parallel programming languages? The parallel programming languages are created for parallel computer environments.  These are developed either by creating new la

Explain a multiprocessing operating system, Explain a multiprocessing opera...

Explain a multiprocessing operating system? A multiprocessing system is a computer hardware configuration which contains more than one independent processing unit. Multiprocess

Anti reflection coating, expression for thickness and refractive index of c...

expression for thickness and refractive index of coating material to act as anti reflection coating

What is microcomputer system, Q. What is microcomputer system? The micr...

Q. What is microcomputer system? The microcomputer has a single microprocessor and a number of RAM and ROM chips as well as an interface unit which communicates with several ex

How to modify or delete a custom class name, 1. Click Tools > General Optio...

1. Click Tools > General Options, and then click the Object Mapping tab. 2. From the Object type list, select the standard object type that is associated with the object class

Explain auto increment and auto decrement mode, Explain Auto increment and ...

Explain Auto increment and Auto decrement mode  The register is incremented or decremented after (or before) its value is used to access memory.  The address stored in the regi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd