Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Specify the default alignment, Specify the default alignment for the follow...

Specify the default alignment for the following field types: 'D' - Left, 'F'-Right, 'N'-Left, 'I'-Right, 'T'-Left.

Local minima - sigmoid units, Local minima - sigmoid units: Alternativ...

Local minima - sigmoid units: Alternatively in addition to getting over some local minima where the gradient is constant in one direction or adding momentum will increase the

Positive logic nand gate is equivalent to negative logic nor, Show that a p...

Show that a positive logic NAND gate is equivalent to negative logic NOR gate. Ans:  Positive logic denotes True or 1 with a high voltage and False or 0 with a low volt

Carry save addition and generated and propagate function, Explain carry sav...

Explain carry save addition (CSA) process. Ans: Instead of allowing the carries ripple along the rows, they can be saved and then introduced into the next roe at the right wei

What is a linked list, What is a linked list? Linked list: A linked l...

What is a linked list? Linked list: A linked list is a self referential structure which having a member field that point to the similar structure type. In simple term, a link

What is reification, What is reification? It is the promotion of someth...

What is reification? It is the promotion of something that is not an object into an object. Helpful method for Meta applications. It shifts the level of abstraction. Promote

Bus arbitration - computer architecture, Bus arbitration: In single bu...

Bus arbitration: In single bus architecture when more than 1 device requests the bus, a controller known as bus arbiter decides who gets the bus; this is known as the bus arbi

Explain quadratic probing with respect to hashing technique, Quadratic prob...

Quadratic probing: In the above case when the first insertion is made the probability of latest element being inserted in a certain position is 1/n    where n is the size of the a

Difference between top-down and bottom-up programming, What is the differen...

What is the difference between top-down and bottom-up, programming? Ans: Top-down and Bottom-up Approaches In Top-down programming approach, we begin by identifying the main

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd