Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Fixed arithmetic pipelines, Fixed Arithmetic pipelines  We obtain the e...

Fixed Arithmetic pipelines  We obtain the example of multiplication of fixed numbers. The Two fixed-point numbers are added by the ALU using shift and add operations. This sequ

the monte carlo simulation technique, The demand placed on a system is exp...

The demand placed on a system is explained by a lognormally distributed random variable with mean 50 and standard deviation of 10. The capacity of the system is modeled by a Weibul

What is the purpose of the enableevents() method, The enableEvents() method...

The enableEvents() method is used to enable an event for a certain object. Normally, an event is enabled when a listener is added to an object for a certain event. The enableEvents

NETWORK ADMIN, Discuss the risks of having a single root user and how more ...

Discuss the risks of having a single root user and how more limited management abilities can be given to others users on Linux/UNIX systems.uestion #Minimum 100 words accepted#

Define the system analysis of object oriented modelling, Define the System ...

Define the System Analysis of Object oriented modelling System Analysis: In this stage a statement of the queries is formulated and a model is designed by the analyst in enc

The source to the current version, How do I update an existing copy of the ...

How do I update an existing copy of the source to the current version? Ans) As the common code changes, you might need to update your copy to have the lastest version. To do tha

Why array index starts from zero, This boils down to the concept of Binary ...

This boils down to the concept of Binary digits. Take an array size of 64 for example. We begin from 0 and end at 63. We need 6 bits.But, if we were to begin from 1 and end at 64,

Explain about system deadlock, Q. Explain about System Deadlock? A dead...

Q. Explain about System Deadlock? A deadlock denotes to the condition when simultaneous processes are holding resources and putting off each other from finishing their executio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd