Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Why java is called machine independent, Why Java is called Machine Independ...

Why Java is called Machine Independent? While a java program is compiled this is not converted in an executable code. Rather, this is converted in a byte code. Byte code is hig

Interconnection network in-array processing, Interconnection Network (IN): ...

Interconnection Network (IN):  IN performs data exchange between the PEs, manipulation functions and data routing. This IN is under the control of CU.

No. of decimal places for output within a write statement, The no of decima...

The no of decimal places for output can be describes within a write statement. This statement is right. Write:/ decimals 2.

8259 PIC, plz expalain interfacing of 8259 with 8085 step wise

plz expalain interfacing of 8259 with 8085 step wise

What are digital signatures and its uses, What are Digital Signatures and i...

What are Digital Signatures and its uses? A digital signature is an electronic quite than a written signature which can be used through someone to authenticate the identity of

Is it possible to decrease clock skew to zero, Is it possible to decrease c...

Is it possible to decrease clock skew to zero? Describe your answer? Even if there are clock layout strategies (H-tree) which can into theory reduce clock skew to zero by havi

List the major components of the keyboard, List the major components of the...

List the major components of the keyboard/Display interface. a. Keyboard section b. CPU interface section c. Display section d. Scan section

Advanced microprocessor, Write a program to mask bits D3D2D1D0 and to set ...

Write a program to mask bits D3D2D1D0 and to set bits D5D4 and to invert bits D7D6 of the AX register.

Explain client server model, Explain Client Server Model. In the client...

Explain Client Server Model. In the client- server model, communication usually takes the form of a request message from the client to the server asking for several works to be

Why we use addressing schemes, Q Why we use addressing schemes? An ope...

Q Why we use addressing schemes? An operation code of an instruction tells the operation to be performed. This operation is executed on some data stored in memory or register.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd