Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Method of spirit duplicating, Method : The master from which the copies wi...

Method : The master from which the copies will be taken is first prepared from a special non-absorbent glazed sheet of paper and special carbon paper which acts as the reproducing

Explain the passive matrix in lcd technology, Q. Explain the Passive Matrix...

Q. Explain the Passive Matrix in lcd technology? In a passive matrix arrangement LCD panel has a grid of vertical and horizontal conductors and every pixel is positioned at an

Seven segment decoder, A design for the seven segment decoder is required. ...

A design for the seven segment decoder is required. The decoder has four inputs which represent a number from 0 to 9 in binary and seven outputs which are connected to the seven

Algorithm to have a good best case running time, How can we change almost a...

How can we change almost any algorithm to have a good best case running time? Check whether the input constitutes an input at the very starting Or else run the original algo

What is laser printers, Q. What is Laser Printers? Laser Printers are p...

Q. What is Laser Printers? Laser Printers are page printers. For print quality they also face same addressability issues as DMP/InkJet Printers. Though some other methods are p

Explain the main characteristics of semiconductor memory, Explain the Main ...

Explain the Main characteristics of semiconductor memory Memory, with regard to computers, most commonly signifies to semiconductor devices whose contents can be accessed (whic

How to transmits data in the active message buffer, Q. How to Transmits dat...

Q. How to Transmits data in the active message buffer? int pvm_bcast( char *group, int msgtag ) Transmits data in the active message buffer to a group of processes. msgt

What are the two ways in which the system using cache, What are the two way...

What are the two ways in which the system using cache can proceed for a write operation? Write by protocol technique Write-back or Copy-back protocol method

What is an interrupt, What is an interrupt?  An interrupt is an event t...

What is an interrupt?  An interrupt is an event that causes the implementation of one program to be suspended and another program to be implemented.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd