Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Determine a sample rate required for telephone conversation, A sample rate ...

A sample rate of            is required for a good quality representation of telephone conversation. A sample rate of 50 times/second /mile of distance travelled are needed fo

Control flow diagram, creating a control flow question for atm system

creating a control flow question for atm system

Which approaches not require knowledge of the system state, Which approache...

Which approaches do not require knowledge of the system state? Ans. Deadlock detection, deadlock prevention and deadlock avoidance; none of the given require knowledge of the s

What is the difference between awt and swt, SWT (Standard Widget Toolkit) i...

SWT (Standard Widget Toolkit) is a totally independent Graphical User Interface (GUI) toolkit from IBM. They formed it for the creation of Eclipse Integrated Development Environmen

How call processing takes place, How call processing takes place? Fund...

How call processing takes place? Fundamental Call Procedure: Fig. demonstrates a simplification diagram exemplifying how two telephone sets (as subscribers) are interconnecte

Explain about quine mckluskey method, Q. Explain about Quine McKluskey Meth...

Q. Explain about Quine McKluskey Method? A tabular method was proposed to deal with increasing number of variables called Quine McKluskey Method. This method is appropriate for

Prove, state and prove distributive law?

state and prove distributive law?

Flowchart, How to calculate the flowchart

How to calculate the flowchart

What is interrupt and function of color graphics adopter, Q. What is inter...

Q. What is interrupt? How it is useful in controlling I/O operations. Q. Explain function of Color Graphics Adopter card and Diskette Drive Adopter Card.

How many words can be acquired by the word universal, How many words can be...

How many words can be acquired by arranging the letters of the word 'UNIVERSAL' in different way? In how many of them  (i)  E, R, S takes place together (ii)  No two of the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd