Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain classification based on grain size, Explain Classification Based On...

Explain Classification Based On Grain Size This categorization is based on distinguishing the parallelism in a program to be executed on a multiprocessor system. The concept is

Why a linked list is called a dynamic data structure, Why a linked list is ...

Why a linked list is called a dynamic data structure? What are the advantages of using linked list over arrays?    A linked list is known as a dynamic data structure because it

What are the disadvantages of linux, What are the disadvantages of Linux? ...

What are the disadvantages of Linux? Learning Lack of comparable programs More technical skill required

Intelligent retrieval from database, Intelligent Retrieval from Database: D...

Intelligent Retrieval from Database: Database system are large bodies of facts about some subjects, which are used to answer users queries about that subject. The design of d

Executing a parallel algorithm, Q. Executing a parallel algorithm? Mult...

Q. Executing a parallel algorithm? Multiple processors need synchronization with one another when executing a parallel algorithm. So task which is running on processor X may ha

How do you recognize the performance bottlenecks, Performance Bottlenecks c...

Performance Bottlenecks can be identified by using monitors. These monitors might be application server monitors, database server monitors, web server monitors and network monitors

Pros and cons of general purpose register architecture, Q. Pros and Cons of...

Q. Pros and Cons of general purpose register architecture? General Purpose Register Architecture: Pros and Cons Registers can be employed to store variables as it decrea

Give an example of shortest job next scheduling, Consider the following set...

Consider the following set of jobs with their arrival  times, execution time (in minutes), and deadlines. Job Ids Ar r ival Time E xecuti

Example of the horizon problem, Example of the horizon problem: It is ...

Example of the horizon problem: It is also worth bearing in mind the horizon problem, however a game-playing agent cannot see much far satisfactory into the search space. Now

Ip fragmentation of user datagarm, IP specified that datagram can arrive in...

IP specified that datagram can arrive in a different order than they were sent. If a fragment from one datagram arrives at a destination before all the segments from a previous dat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd