Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define the half duplex transmission, Define the Half Duplex Transmission ...

Define the Half Duplex Transmission A half-duplex channel can receive andsend, but not at the same time. It's like a one-lane bridge where two-way traffic should give way in

Variable-partition multiprogramming, Choose the descriptions below with the...

Choose the descriptions below with the most appropriate memory management scheme (A through D).  Solutions may be used once, more than once, or not at all. A.     Fixed-partitio

State about agp, State about AGP The latest addition to many computer s...

State about AGP The latest addition to many computer systems is the inclusion of accelerated graphics port (AGP). AGP operates at the bus clock frequency of the microprocessor.

Explain system software with system programming, Explain the evolution of s...

Explain the evolution of system software with system programming. System-software is collection of system programs which perform a variety of functions, name are: file editing,

Probabilistic hough transformation, The probabilistic Hough transform uses ...

The probabilistic Hough transform uses random sampling instead of an accumulator array. In this approach the number of random samples r, is not specified in the OpenCV call, but

What is the necessity of an interface, What is the necessity of an interfac...

What is the necessity of an interface?  Any device that has to be linked to a CPU requires an interface. This takes care of the mismatch in speed, data and electrical character

What is called static and dynamic branch prediction, What is called static ...

What is called static and dynamic branch prediction? The branch prediction decision is always the similar every time a given instruction is implemented. Any approach that has t

Parallel edge or self loop of the total number of edges, A graph with n ver...

A graph with n vertices will definitely have a parallel edge or self loop of the total number of edges are More than n(n-1)/2

Breakthrough for computer engineering, what is the importance of chemistry ...

what is the importance of chemistry for computer engineering?

Bootstrap, The device is packaged in a 80 pin PLCC device as shown.The main...

The device is packaged in a 80 pin PLCC device as shown.The main groupings of the pins are as follows Port A PA0 - PA7 Parallel Port or Timer Port B PB0 - PB7 Parallel Port or High

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd