Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How does the dialog handle user requests, How does the Dialog handle user r...

How does the Dialog handle user requests? when an action is performed ,the system triggers the PROCESS AFTER INPUT event. The data passed contains field screen data data enter

What is stack addressing, Q. What is Stack Addressing? In this addressi...

Q. What is Stack Addressing? In this addressing technique operand is implied as top of stack. It isn't explicit however implied. It employs a CPU Register known as Stack Pointe

Explain about transmission media, Q. Explain about Transmission Media? ...

Q. Explain about Transmission Media? These, also known as physical channels, can be either bounded or unbounded. Bounded media, in which signals representing data are confined

Set up to use parallel virtual machine, Q. Set up to Use parallel virtual m...

Q. Set up to Use parallel virtual machine? PVM employs two environment variables when starting and running. Each and every PVM user needs to set these two variables to employ P

What are the logic micro-operations, Q. What are the Logic Micro-operations...

Q. What are the Logic Micro-operations? Logic operations are fundamentally binary operations that are performed on string of bits stored in the registers. For a logic micro-ope

Seven segment decoder, A design for the seven segment decoder is required. ...

A design for the seven segment decoder is required. The decoder has four inputs which represent a number from 0 to 9 in binary and seven outputs which are connected to the seven

Define seek time and latency time, Define seek time and latency time. ...

Define seek time and latency time.  The time taken by the head to move to the appropriate cylinder or track is known as seek time. Once the head is at right track, it must wai

De moiver theorem, application of de moiver theorem in software engineering...

application of de moiver theorem in software engineering

What do you meant by a storage device, Question : (a) What do you me...

Question : (a) What do you meant by a storage device? (b) List 5 examples of storage devices and give their uses (c) What are the differences between backup and ar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd