Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Skip to line line number, The "SKIP TO LINE line number" is dependent on wh...

The "SKIP TO LINE line number" is dependent on which statement included in the report statement of the program. The "SKIP TO LINE line number" is dependent on "LINE-COUNT" stat

Explain the differences between macros and subroutines, Explain the differe...

Explain the differences between macros and subroutines. Macros Vs Subroutines (i) Macros are pre-processor directives which are processed before the source program is pass

Give the example of spreadsheet, Give the example of Spreadsheet By sel...

Give the example of Spreadsheet By selecting cell C1 and dragging the formula down to C5 the below formulae will be replicated in C2 to C5: (A2*B2), (A3*B3), (A4*B4) and (A5*B5

Show the advantages of joint application development, Q. Show the advantage...

Q. Show the advantages of Joint Application Development? The following are the numerous advantages of Joint Application Development: Actively includes management and use

What is the meaning of aliasing, a. What is the meaning of aliasing? What a...

a. What is the meaning of aliasing? What are its drawbacks? Describe a method to remove aliasing, using post filtering. b. How can you copy a Pixmap from one place to another

Explain the difference between ram and rom, RAM: Read / Write memory, High ...

RAM: Read / Write memory, High Speed, Volatile Memory. ROM: Read only memory, Low Speed, Non Voliate Memory.   RAM- Random Access memory it is a Volatile Memory.  volatil

How can we use ordered lists, Q. How can we use Ordered Lists? Lists ha...

Q. How can we use Ordered Lists? Lists having numbered items are termed as ordered lists. They are used when items in the list have a natural order. They can also be used when

Asp.net, how work for asp.net

how work for asp.net

Page translation table, Make a page translation table the meets the require...

Make a page translation table the meets the requirements of the virtual memory system given below.  Suppose page (and frame) sizes of 20 with pages 0 by 3 in logical memory and fra

What is mqseries cluster, Cluster is said to be collection of queue manager...

Cluster is said to be collection of queue manager's logically linked together to balance the load on the remote machine (i.e if it is remote queue managers which processes your mes

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd