Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Characteristics of decision support system, Q. Characteristics of decision ...

Q. Characteristics of decision support system? Characteristics of DSS- The qualities of the DSS are as follows: - 1. DSS focus on towards providing assistance in analyzing s

Non-repudiation achieved in designing e-cash based system, How can non-repu...

How can non-repudiation be achieved into designing e-cash based system? E-cash is fundamentally an online solution. The buyer should validate the coins by the issuer so as to g

The concept of electronic cash, The concept of electronic cash is to implem...

The concept of electronic cash is to implement payment by Using computers over network

Determine the ad hoc testing, Determine the Ad hoc testing - It is a ty...

Determine the Ad hoc testing - It is a type of testing which is performed without the use of planning or/and documentation. - These tests are run only one time unless a defe

Scoreboards- constrained-random verification methodology, Scoreboards- Cons...

Scoreboards- Constrained-Random Verification Methodology Scoreboards are used to verify that data has successfully reached its destination whereas monitors snoop the interfaces

Determine the uses of smart cards, Determine the uses of Smart cards  ...

Determine the uses of Smart cards  These comprise embedded microchips and receive power from the card readers; Microchip is made up of RAM, ROM and 16-bit processor and the st

How to detect a sequence of 1101, Use 4 D-bascules connected in serial all ...

Use 4 D-bascules connected in serial all synchronized with the similar CLK. Then connect all 4 outputs, & 2nd output must reverse, of the D-bascule to an AND logic. The output of t

What are the engineering applications in parallel computing, Engineering Ap...

Engineering Applications A number of the engineering applications are: 1. Simulations of artificial ecosystems  2. Airflow circulation over aircraft components Airflow

How does computer know that overflow has happened, Q. How does computer kno...

Q. How does computer know that overflow has happened? Illustration: Add numbers 65 and 75 in 8 bit register in signed 2's complement notation.  Here expected result is

Architecture of artificial neural networks, Architecture of Artificial neur...

Architecture of Artificial neural networks: Presumably "Artificial Neural Networks" consist of a number of units that are mini calculation devices. But they take in real-value

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd