Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Research methods, Building on their knowledge of research methods and their...

Building on their knowledge of research methods and their interest in a particular aspect of information technology this assessment enables students to put this knowledge into prac

How do you create special files like named pipes, How do you create special...

How do you create special files like named pipes and device files? The system call method forms special files in the following sequence. Kernel assigns new inode,

Operating system, explain network operating system and design issues?

explain network operating system and design issues?

Interrupt signal interconnection network (isin), Interrupt Signal Interconn...

Interrupt Signal Interconnection Network (ISIN) When a processor needs to send an interruption to another processor, then this interrupt initial goes to ISIN, through which it

Network properties, Network Properties There are many properties are as...

Network Properties There are many properties are associated with interconnection networks:- 1) Topology: It signify how the nodes a network are organised. A variety of top

VLSI implementation of control unit, Q. VLSI Implementation of Control Unit...

Q. VLSI Implementation of Control Unit? A main potential advantage of RISC is VLSI implementation of microprocessor. VLSI Technology has decreased the delays of transfer of inf

What are vectored interrupts, What are vectored interrupts? To decrease...

What are vectored interrupts? To decrease the time involved in the polling process, a device requesting an interrupt may recognize itself directly to the processor. Then the pr

Define memory cell, Define memory cell? A memory cell is capable of sto...

Define memory cell? A memory cell is capable of storing single bit of information. It is usually organized in the form of an array

File structures, Write in brief about UNIX process structure.

Write in brief about UNIX process structure.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd