Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is use case and use case diagram, What is use case and use case diagra...

What is use case and use case diagram? A use case is a coherent piece of functionality that a system can give by interacting with actors. Use case includes one or more actors a

Why object oriented development not only allows reuse, Why object oriented ...

Why object oriented development not only allows reuse In a wider way we can say that object oriented development not only allows reuse and information sharing within an applica

Explain cache organisation, Q. Explain Cache Organisation? Cache memori...

Q. Explain Cache Organisation? Cache memories are found in nearly all latest computers.  They are very helpful for increasing speed of access of information from memory.  Let's

Write heterogeneous functions, Write "heterogeneous" functions If a pro...

Write "heterogeneous" functions If a program uses simulated, dynamically allocated multidimensional arrays, it becomes possible to write "heterogeneous" functions which don't h

Expression for boolean function in standard POSform, Write the expression f...

Write the expression for Boolean function for F (A, B, C) = ∑m (1,4,5,6,7) in standard POS form.                                   Ans: f (A,B,C )= ΣM (1,4,5,6,7) in standard POS

Illustrate about direct addressing mode, Q. Illustrate about Direct Address...

Q. Illustrate about Direct Addressing mode? In this technique operand field of instruction specifies direct address of intended operand for example if instruction LOAD 500 uses

Why gateways are used during mail transfer, Why Gateways are used during ma...

Why Gateways are used during mail transfer? Email using SMTP effort best while both the sender and the receiver are on the internet and can hold TCP connections in between send

Crafting an isa - computer architecture, Crafting an ISA: We will l...

Crafting an ISA: We will look at some decisions facing an instruction set architect, and In the design of the MIPS instruction set how those decisions were made. MIPS

Develop a menu-driven application, In assignment you are required extend th...

In assignment you are required extend the Patient class to implement an  Inpatient  class,  representing a patient who is admitted to the hospital for a longer term and who may req

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd