Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain switching system of a finite state machine model, Show how finite s...

Show how finite state machine model helps in designing a switching system and give a typical example. Switching system fundamentally belongs to the class of finite state machi

Explain normans execution-evaluation cycle model, Question 1: (a) How ...

Question 1: (a) How would you explain human reasoning? (b) Explain the different types of human reasoning? Question 2: (a) What are the computational factors affec

DBMS, what is dbms goal?

what is dbms goal?

Why are high-speed memories required, Q. Why are high-speed memories requir...

Q. Why are high-speed memories required? Is the main memory not a high-speed memory? The answer to second question is absolutely 'No' though why so? Then if memories are slowe

What is software quality assuranc, Software QA includes the whole software ...

Software QA includes the whole software development PROCESS - improving and monitoring the process, making sure that any agreed-upon standards and processes are followed, and ensur

Define congestion, Define Congestion. Congestion: This is uneconomic ...

Define Congestion. Congestion: This is uneconomic to give sufficient equipment to carry all the traffic which could possibly be offered to a telecommunication system. Inside

Explain clearly the difference between j-cuts and l-cuts, Question: (a)...

Question: (a) Explain clearly the difference between J-cuts and L-Cuts. (b) What is the function of the rate stretch tool? (c) What's the difference between an Image Matt

What is scsi, What is SCSI? Ans: It is the acronym for small computer s...

What is SCSI? Ans: It is the acronym for small computer system interface. It refers to a standard bus explained ANSI. Devices such as disks are linked to a computer via 50-wire

What is the use of system.data.dlinq.dll, System.Data.DLinq.dll gives funct...

System.Data.DLinq.dll gives functionality to work with LINQ to SQL.

Difference between char a[] = "string", What is the difference between char...

What is the difference between char a[] = "string"; and char *p = "string";? Ans) In the first case 6 bytes are assigned to the variable a which is fixed, where as in the secon

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd