Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How semaphores implement mutual exclusion, How semaphores implement mutual ...

How semaphores implement mutual exclusion? Mutual-exclusion implementation along with semaphores: Assume that there are n-processes and they share a semaphore, mutex (stan

Knowledge representation in artificial intelligence , Knowledge Representat...

Knowledge Representation: To recap, now we have some characterizations of Artificial Intelligence, so  when an Artificial Intelligence problem arises, you will enable  to put i

Define the operand data types, Operand is that part of an instruction which...

Operand is that part of an instruction which specifies the address of source or result or the data itself on which the processor is to operate. Operand types typically give operand

What is assembler directive, What is assembler directive? SUM EQU 200 ...

What is assembler directive? SUM EQU 200 Assembler directives are not instructions that will be implemented. It easily informs the assembler that the name SUM should be chan

Compare single bus structure and multiple bus structure, Compare single bus...

Compare single bus structure and multiple bus structure? A system that having only one bus(i.e only one transfer at a time) is known as a single bus structure. A system is know

How to creating a key pair, How to Creating a Key Pair You can make a...

How to Creating a Key Pair You can make a key pair using the Strong Name tool (Sn.exe). Key pair files usually have an .snk extension. To create a key pair at the command

What is Video Card Interfaces, Q. What is Video Card Interfaces? A video i...

Q. What is Video Card Interfaces? A video interface is the link of video system to rest of the PC. To improve video performance there is required to be an intimate connection betw

Determine about the the difference engine - pascaline, THE DIFFERENCE ENGIN...

THE DIFFERENCE ENGINE - Pascaline The difference enigne was based on the mathematical principle of finite differences and was used to solve calculations based on large numbers

Determine the term - artisan software and bridgepoint, Determine the term ...

Determine the term - ARTiSAN Software and  BridgePoint ARTiSAN Software : This provides a variety of UML based CASE tools, which also includes a real time modeling tool.

Task information displays in search-based tools, Q. Task Information Displa...

Q. Task Information Displays in Search-based tools? Task Information Displays principally give visualization of different locations in parallel program where bottlenecks have o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd