Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Which device consume minimum power, Which device consume minimum power ? ...

Which device consume minimum power ? Ans. Minimum power consume by CMOS as in its one p-MOS and one n-MOS transistors are connected in complimentary mode, so one device is ON a

Software engineering, specialization,ggeneralization and aggregation of rai...

specialization,ggeneralization and aggregation of railway reservation system?

What is central processing unit, What is Central Processing Unit Centra...

What is Central Processing Unit Central Processing Unit (CPU) performs all the arithmetic and logical calculations in a computer. The CPU is said to be the brain of the compute

IEEE802.4 Token Bus Network, en a five station token bus LAN with station a...

en a five station token bus LAN with station addresses of 3000, 500, 100, 70, and 50. Stations with addresses of 5000, 4000, 400, 90, and 60 are waiting to enter the ring. Assume a

.image forgery detection, what is the code to detect image forgery using Ma...

what is the code to detect image forgery using Matlab..??

Show the connection between different networks, Q. Show the Connection betw...

Q. Show the Connection between different networks? The connection between different stages is made in following manner:  all outputs of 1 st crossbar switch of first stage a

List out the features of computer memory, List Out the Features of Computer...

List Out the Features of Computer Memory? Features of each type of memory   Type Volatile? Write able? Erase Size

Name the approaches used for generating the control signals, What are the t...

What are the two approaches used for generating the control signals in proper sequence? Hardwired control Micro programmed control

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd