Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain the term - rational rose and visio 2000 enterprise, Explain the ter...

Explain the term - Rational Rose and Visio 2000 Enterprise Rational Rose: IBM Rational RequisitePro is a powerful and easy-to-use tool for use case management and requirement

Advantages & disadvantages of public-key cryptography, Advantages & Disadva...

Advantages & Disadvantages Enhanced security and convenience: private keys never require be transmitting or revealing to anyone.  They can givce a method for digital signatu

What is independent process, What is independent process? A process is ...

What is independent process? A process is independent it cannot affect or be affected by the other processes implementing in the system. Any process does not share data with ot

What is a parallel port, What is a parallel port? A parallel port trans...

What is a parallel port? A parallel port transfers data in the form a number of bits, typically 8 to 16, concurrently to or from the device.

Computer grphics, Advantages of DDa algorithms for line drawimg

Advantages of DDa algorithms for line drawimg

What are the features common in most of the websites, What are the features...

What are the features common in most of the websites Following general features must be found on most web sites in one form or another (this list is by no means exhaustive):

Microcomputer - controlled breadmaking machine, Q. Microcomputer - Controll...

Q. Microcomputer - Controlled Breadmaking Machine? Figure shows a simplified schematic diagram of a microcomputer-controlled breadmaking machine. A microcomputer along with its

#project, how to build PVR set-top box using raspberry

how to build PVR set-top box using raspberry

Rdbms relational database system, RDBMS relational database system - Re...

RDBMS relational database system - Relational databases are composed of relations and managed through relational operations, and governed through data integrity constraints.

What is the maximum number of fragments, What is the maximum number of frag...

What is the maximum number of fragments that can result from a single IP Datagram? Explain. To fragment a datagram for transmission across a network, a router utilizes the netw

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd