Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

General registers in a processor, In this segment, we will give very brief ...

In this segment, we will give very brief details of registers of a RISC system known as MIPS. MIPS is a register-to-register or load/store architecture and employs three address

#title.calomel electrode, explain the construction and working of calomel e...

explain the construction and working of calomel electrode

Convert the following decimal numbers into octal, Q. Convert the following ...

Q. Convert the following DECIMAL numbers into OCTAL, double check by converting the result OCTAL to DECIMAL. a) 932 b) 4429.625 c) 19

Describe the importance of micro-programming, Question: (a) Describe t...

Question: (a) Describe the importance of Micro-Programming and point out one area where Micro-Programming is extensively used. (b) Below is a diagram of an 8086 processor.

Area under curve , Write a program to find the area under the curve y = f(x...

Write a program to find the area under the curve y = f(x) between x = a and x = b, integrate y = f(x) between the limits of a and b. The area under a curve between two points can b

Evaluate speed of disk drive, Q. Evaluate Speed of disk drive? Drive S...

Q. Evaluate Speed of disk drive? Drive Speed: Amount of information which can be transferred in or out of memory in a second is called as disk drive speed or data transfer ra

Detrmine pure paging, Which is not a key piece of information, stored in si...

Which is not a key piece of information, stored in single page table entry, assuming pure paging and virtual memory Ans. A reference for the disk block which stores the page is

What is process, What is Process? Process: A process is a program in ...

What is Process? Process: A process is a program in execution. It is an active entity, represented through the value of the program counter and the contents of registers o

Explain SR latch using nor gates, Q. Explain SR Latch using NOR gates? ...

Q. Explain SR Latch using NOR gates? Let's inspect the latch more closely.   i. Suppose initially 1 is applied to S leaving R to 0 at this instance. The instant S=1 output o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd