Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate what is universal law of universal gravitation, Q. Illustrate wh...

Q. Illustrate what is the universal law of universal gravitation? Answer:- Declaration that any particle of matter in the universe attracts any other with a force varying

Gantt chart, The Gantt chart shows the several activities of each processor...

The Gantt chart shows the several activities of each processor with respect to progress in time in idle-overhead -busy modes with respect to each processor. Kiviat diagram:  Th

What is the advantage of dividing an email address, What is the advantage o...

What is the advantage of dividing an email address into two parts? The division of an e-mail address in two parts is significant since it achieve two objectives. First, the div

Give an example of problem statement, Give an example of Problem Statem...

Give an example of Problem Statement You should understand here that you are looking for a statement of requirements, not a proposal for the solution. OOA specifies structu

Example of shared programming using library routines, Q. Example of shared ...

Q. Example of shared programming using library routines? Think about subsequent set of statements  Process A                                  Process B                  :

Classified the vlsi technology, The VLSI technology is still developing. Mo...

The VLSI technology is still developing. More and more powerful microprocessors and more storage space now are being put in single chip. One question that we have still not conside

Determine about the authoring software, Determine about the Authoring Softw...

Determine about the Authoring Software Also termed as author ware; this is a program which helps in the writing of hypertext or multimedia applications. Authoring tools general

What is basic working of modem, Q. What is basic working of Modem? A mo...

Q. What is basic working of Modem? A modem (modulator/demodulator) is an electronic device that takes digital data as a serial stream of bits and produces a modulated carrier s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd