Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Minimization of the logic function using k-maps, Minimize the logic functio...

Minimize the logic function F(A, B, C, D) = ∑ m(1,3,5,8,9,11,15) + d(2,13) using K-maps Ans. The logic function minimization of F(A, B, C, D) = ∑ m(1,3,5,8,9,11.15) + d(2,13) by

What is cgi, CGI stands for Common Gateway Interface, and is a mechanism by...

CGI stands for Common Gateway Interface, and is a mechanism by which a browser is permitted to communicate with programs running on a server. If you look at every word in turn it m

What is a flip-flop, What is a flip-flop? Ans. Flip-flop is particu...

What is a flip-flop? Ans. Flip-flop is particular bit memory cell. This stores individual bit information in its true and compliment form. It is the basic block of any sequ

Logic calculations are done in which type of registers, Accumulator is the ...

Accumulator is the register in which Arithmetic and Logic calculations are completed.

What is a structure, What is a structure? A structure is a collection o...

What is a structure? A structure is a collection of variables under a single name. These variables can be of different types, and each has a name which is used to select it fro

Creating a contacts application, Creating a contacts application: Firs...

Creating a contacts application: First, a contact is defined as the tuple: firstName, lastName, phoneNumber and email. You will create a class Contact that allows getting a

Illustrate 16-bit isa, Illustrate 16-bit ISA?  Compare it with 8-bit ISA bu...

Illustrate 16-bit ISA?  Compare it with 8-bit ISA bus.  The only difference between 8 and 16-bit ISA bus is that an extra connector is attached behind the 8-bit connector. 16-b

History of e-commerce, In 1960: The purpose of e-commerce was to exchange t...

In 1960: The purpose of e-commerce was to exchange the electronic data. In 1970s: Electronic Fund Transfers or EFT was developed which considered as huge impact in the emerging

Explain the concept of process, The Concept of Process Unofficially a p...

The Concept of Process Unofficially a process is a program in execution subsequent to the program has been loaded in the main memory. Though a process is more than just a progr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd