Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Technical Support Engineer, I''m seeking a challenging professional working...

I''m seeking a challenging professional working position in the field of Information Technology,where I’ll be given the chance to enhance & expand the skills & experience

Explain about the postpurchase interaction briefly, Explain about the postp...

Explain about the postpurchase interaction briefly. Postpurchase Interaction: Customer support and service: The considerations at such can be explained by the followin

Components of a 3-tier client server, What are the essential components of ...

What are the essential components of a 3-tier client server In a three-tier or multi-tier environment, the client executes the presentation logic (the client). The business log

What do you mean by shopping bots, Q. What do you mean by shopping bots? ...

Q. What do you mean by shopping bots? ANSWER: A shopping bot or buyer agent is an intelligent agent on a Web site that assists you, the customer, search the products and servic

Define program counter, Define Program Counter(PC) The Program Counter ...

Define Program Counter(PC) The Program Counter holds the address of the next instruction to be read from memory after the current instruction is implemented.

Introduction to information distribution, INTRODUCTION : Like any other of...

INTRODUCTION : Like any other office we need equipment to provide for information distribution in the laboratory office also. For information distribution we require multiple copi

Area under curve, Write a program to find the area under the curve y = f(x)...

Write a program to find the area under the curve y = f(x) between x = a and x = b, integrate y = f(x) between the limits of a and b. The area under a curve betw   #includ

Data structure, what are the fundamental data structures

what are the fundamental data structures

Nmknl''knl, Ask question bhjjnjnnjnjm#Minimum 100 words accepted#

Ask question bhjjnjnnjnjm#Minimum 100 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd