Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Final implementation of object oriented modelling, Final Implementation of ...

Final Implementation of Object oriented modelling Final Implementation: At this phase, the final execution of classes and  relationships developed while object design takes

Determine the operations from functions, Operations from Functions As ...

Operations from Functions As we know, function is actually operations on object. These   functions could be simple and summarized on object model. Organise functions into oper

Tree strucred directory, what is the operations in atree structured directo...

what is the operations in atree structured directory.

Can we call reports from interactive reporting lists, Can we call reports ...

Can we call reports and transactions from interactive reporting lists? Yes.  It also permits you to call transactions or other reports from lists.  These programs then use val

Define input-output interface, Define Input-Output Interface. I/O inter...

Define Input-Output Interface. I/O interface gives a method for transferring information among internal storage and external I/O devices

Control hazard and delayed branching, Described Instruction or control haza...

Described Instruction or control hazard? Ans: The pipeline can be stalled due to delay in the availability of an instruction. For instance, this may be a result of a miss in t

Determine the function of dynamic model, Determine the function of Dynamic ...

Determine the function of Dynamic model Dynamic model: Dynamic model describes how system responds to external events. The implementation of the control flow in a program must

How many input ANDand OR gates are required, How many two input AND gates a...

How many two input AND gates and two input OR gates are required to realize Y = BD+CE+AB ? Ans. Here three product terms, therefore three AND gates of two inputs are needed.

Working of fully parallel associative processor, Q. Working of Fully Parall...

Q. Working of Fully Parallel Associative Processor? Fully Parallel Associative Processor: This processor accepts the bit parallel memory organisation. There are 2 kinds of this

Difference among using a filter and a query to find records, What is the di...

What is the difference among using a filter and a query to find records? Filter is used to quickly limit the records as we are already viewing in a Datasheet or a form to those

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd