Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Can we change the color of the worksheet tabs in my workbook, In a word,you...

In a word,you can't. It would certainly be helpful to be able to color-code your worksheet tabs. For some reason, Microsoft hasn't executed this feature, which has been available i

What is segment directive, Q. What is SEGMENT Directive? Segment direct...

Q. What is SEGMENT Directive? Segment directive defines logical segment to which following instructions or data allocations statement belong.  It also provides a segment name t

Explain the role of a bus arbiter in a multiprocessor, Explain the role of ...

Explain the role of a bus arbiter in a multiprocessor configuration. Bus arbiter: Which functions to resolve priority between bus masters and allows only one device at a time t

Atom-collider, Many physicists believe that the universe is governed by a s...

Many physicists believe that the universe is governed by a single system. A system which is capable of describing the behaviour of the very large (stars and planets) and the very s

What is a scope resolution operator, A scope resolution operator (::), can ...

A scope resolution operator (::), can be used to describe the member functions of a class outside the class.

How can you show only selected records with a form, How can you show only s...

How can you show only selected records with a form? There are dissimilar ways in which you can limit the records that you will see with a form, you can: Open a form and app

What are the central interfaces of the r/3 system, What are the central int...

What are the central interfaces of the R/3 system? There are three central interfaces:- Presentation Interface. Database Interface. Operating system Interface.

Recombination and mutation, Recombination and Mutation: In such a scen...

Recombination and Mutation: In such a scenario the point of GAs is to generate population after population of individuals that represent possible solutions to the problem at h

Flowchart, draw the flowchart for operator overloading in c++

draw the flowchart for operator overloading in c++

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd