Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Asp.net, in asp project is i have to crate database every time when i move ...

in asp project is i have to crate database every time when i move my project on different server

Where the grade of service is measured, The grade of service is measured in...

The grade of service is measured in (A) Percentage                                  (B)  Number (C)  Fractional Number                    (D)  Logarithmic Number  Ans

Explain about floating point representation, Q. Explain about Floating Poin...

Q. Explain about Floating Point Representation? Floating-point number representation includes two parts. The first part of number is a signed fixed-point number which is called

When do you do load and performance testing, We perform load testing once w...

We perform load testing once we are completed with interface (GUI) testing. Modern system architectures are large and difficult. Whereas one user testing primarily on functionality

What are kinds of models, What are kinds of models? Class model - Objec...

What are kinds of models? Class model - Objects in the system and their relationships. State model - Life history of the objects. Interaction model - Interactions between

Show buffered mode for point-to-point message passing, Q. Show Buffered mod...

Q. Show Buffered mode for Point-to-point Message Passing? Buffered mode: Transmitting can be started whether or not matching receives has been started and transmitting may comp

In order to concatenate strings only for output purposes, In order to conca...

In order to concatenate strings only for output purposes which command can be used in conjunction with the 'Write' statement. NO-GAP command.

Classify computer systems according to capacity, Classify computer systems ...

Classify computer systems according to capacity. How they are different from computers according to the classification of technology. Provide comparative study also

Explain about fat - inode, Q. Explain about FAT - Inode? Today modern P...

Q. Explain about FAT - Inode? Today modern PC comprises total capacity of nearly 40GB for storage of program and data Due to this huge capacity in place of having just one oper

Displacement addressing mode - computer architecture, Displacement and  Sta...

Displacement and  Stack Addressing  mode - computer architecture: Displacement Addressing: In displacement addressing mode there are three types of addressing mode. They

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd