Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Operations of a scientific calculator, A program is to be developed to simu...

A program is to be developed to simulate the operations of a scientific calculator. List the facilities to be provided by this calculator. Analyze this using a DFD 0- level and 1-

History, #what is the history of computer science

#what is the history of computer science

Explain the working of broad band isdn, Explain the working of broad band I...

Explain the working of broad band ISDN. BISDN Configuration: Figure shows how access to the BISDN network is accomplished. All peripheral devices are interfaced to the acces

Explain criteria for choosing type of file organization, What criteria shou...

What criteria should be adopted for choosing type of file organization. Selecting a file organization is a design decision; therefore it must be done having in mind the achieve

Non-repudiation achieved in designing e-cash based system, How can non-repu...

How can non-repudiation be achieved into designing e-cash based system? E-cash is fundamentally an online solution. The buyer should validate the coins by the issuer so as to g

Explain the working of a demultiplexer, Explain the working of a demultiple...

Explain the working of a demultiplexer with the help of an example. Ans: 1:4 Demultiplexer: Fig.(a) demonstrates the logic circuit of a 1:4 demultiplexer. This has two NOT

What is mini computer, Q. What is Mini computer? The term minicomputer ...

Q. What is Mini computer? The term minicomputer introduced in 1960's when it was realized that numerous computing tasks don't need an expensive modern mainframe computers howev

Logical database reads the data from the database, Is it true that the Logi...

Is it true that the Logical Database reads the data from the database tables using Select Statements. Yes. We are coding that in Database part of LDB.

Explain csmsginterface() function with predefined protocol, Explain CSMsgIn...

Explain CSMsgInterface() Function with Predefined Protocol  A REQUEST structure is created for each message sent to the server. Messages passed to CSMsgInterface() as *dataMSG

Hardware interrupts - computer architecture, Hardware interrupts: Har...

Hardware interrupts: Hardware interrupts -from I/O devices, processor, memory Software interrupts-produced by a program. Direct Memory Access (DMA)  Interrupt or Poll

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd