Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Designing e-cash based system, How can it be achieved in designing e-cash b...

How can it be achieved in designing e-cash based system? E-cash is essentially an online solution.  The buyer must validate the coins by the issuer in order to get the purchase

What is called when network address prefixed by 1110, Network address prefi...

Network address prefixed by 1110 is a? Network address prefixed through 1110 is a multicast address.

Evaluate expression by using convention , Evaluate x = A ‾.B + C ( ) usin...

Evaluate x = A ‾.B + C ( ) using the convention A = True and B = False. Ans. Simplify given expression x = A ‾ .B + C ( ) as = A ‾ B + C (A ‾ + D ‾ ) (As = A ‾ +D ‾ usin

Bit pair recoding and 2’s complement, Explain bit pair recoding with an exa...

Explain bit pair recoding with an example? Ans: Bit pair recoding halves the maximum number of summands. Group the Booth-recoded multiplier bits in pairs and see the following

Subtraction of 01100-00011 using 2's complement method, Subtraction of 0110...

Subtraction of 01100-00011 using 2's complement method Ans. Firstly 1's complement of 00011 is 11100 and 2's complement is 11100 + 1 = 11101. Thus If a last carry is

What specifies by environment variable in cgi script, The Environment varia...

The Environment variable SCRIPT_NAME in CGI script specifies? In CGI script gives the path of URL after server name.

Interval b/w time of submission and completion of the job, Interval between...

Interval between the time of submission and completion of the job is? Ans. Turnaround time is the interval in between the time of submission and completion  of the job.

Expalin the history of parallel computers, Expalin the History Of Parallel ...

Expalin the History Of Parallel Computers The researches with and implementations of use of the parallelism started long back in the 1950's by IBM Corporation. The IBM STRETCH

Solve the assignment of finite automata, Solve the assignment of NFA-- Fini...

Solve the assignment of NFA-- Finite Automata and Formal Language Project Description: I have an assignment on Finite Automata and Formal Languages ( Nondeterministic Fini

Features of an expert system, The heart of an experts systems is the ...

The heart of an experts systems is the powerful corups of knowledge that accumulates during system building. The knowledge is explicit and organized to simplify decisio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd