Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Task of the computer systems consultant, You are required to carry out the ...

You are required to carry out the task of the Computer Systems Consultant mentioned above. Your quotation/recommendations, which must be justified, should include information wi

Assignment, zero, one, two three address instructions

zero, one, two three address instructions

Give introduction to object oriented analysis and design, Introduction to o...

Introduction to object oriented Analysis & design: tools In case of OOAD, Unified Modelling Language (UML) is a well accepted language. It is used for constructing, visualizin

Explain frequency-division multiplexing, Q. Explain Frequency-division mult...

Q. Explain Frequency-division multiplexing? Frequency-division multiplexing (FDM) is a technique for data transmission widely used in telephone, radio, and cable TV systems in

Explain the concepts and definitions of e-commerce, The Internet has emerge...

The Internet has emerged as a major worldwide distribution channel for goods, managerial, services, and professional jobs. It has impacted market economics and industry structure,

Project on adaptive concept map, to develop an adaptive concept map providi...

to develop an adaptive concept map providing personalized learning for Operating System subject with text file(in any form like html,ppt,txt,doc,pdf)as input

Predicate logic - artificial intelligence, Translate the following sentence...

Translate the following sentences into predicate logic, using Russell's theory of definite descriptions to represent the article the. a. The wizzard of Oz fell. b. Everyone a

Compute the positive integer and square root, Question: Q1) Write a cod...

Question: Q1) Write a code that asks the user for a positive integer, computes the square root of that integer, and return the result to the user. The computational error needs

Unix for multiprocessor system, The UNIX operating system for a multiproces...

The UNIX operating system for a multiprocessor system has a number of extra features as compared to normal UNIX operating system.  Let's first consider the design objectives of mul

What is the syntax of the assembler directive equ, The syntax of the assemb...

The syntax of the assembler directive EQU is ? Ans. The syntax of the assembler directive EQU is as given below: EQU

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd