Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Discuss the classifications of switching systems, Discuss the classificatio...

Discuss the classifications of switching systems. The categorizations of switching systems are specified in the block diagram given below:

How does tcp take of wrapping over of sequence numbers, How does TCP take o...

How does TCP take of wrapping over of sequence numbers? To handle out of instruct deliveries, transport protocols utilize sequencing. The sending side attaches a sequence numbe

What is meant by stacked list, What is meant by stacked list? A stacke...

What is meant by stacked list? A stacked list is nothing but secondary list and is showed on a full-size screen unless you have specified its coordinates using the window comm

Differences between one hot and binary encoding, What are differences betwe...

What are differences between one hot and binary encoding? Common classifications used to explain the state encoding of an FSM is Binary or highly encoded and one hot. A bina

What are the steps followed in testing, What are the steps followed in test...

What are the steps followed in testing? i. Unit testing - The individual components are tested in this method of testing. ii. Module testing - Related collection of independ

Move a layout cell, If you need to line up the cells next to each other you...

If you need to line up the cells next to each other you can resize and move layout cells as you need. You can change size of a layout cell by using one of its resize handles. Yo

Discuss the mount and unmount system calls, Discuss the mount and unmount s...

Discuss the mount and unmount system calls. The privileged mount system call is used to join a file system to a directory of another file system; the unmount system call detach

Explain common control, Explain Common Control. Common Control: Those...

Explain Common Control. Common Control: Those systems wherein the control subsystem is outside the switching network are termed as common control switching system. Therefore,

What is the significance of asp.net routing, ASP.NET MVC uses ASP.NET routi...

ASP.NET MVC uses ASP.NET routing, to map incoming browser requests to controller action process. ASP.NET Routing makes use of route table. Route table is formed when your web appli

What is XML DTD (Document Type Definition), What is XML DTD (Document Type ...

What is XML DTD (Document Type Definition)? DTD is a document which defines legal building blocks of a particular XML document. This defines the document structure along with

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd