Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Full adder, design a FULL adder with two half adders and an or gate

design a FULL adder with two half adders and an or gate

Conversion of bcd number to binary using a procedure, Q. Conversion of BCD ...

Q. Conversion of BCD number to binary using a procedure? Conversion of BCD number to binary using a procedure. Algorithm for conversion procedure: Take a packed BCD digit

Sort, quick sort working

quick sort working

Why are interrupt masks provided in any processor, Why are interrupt masks ...

Why are interrupt masks provided in any processor? Interrupt mask enable the higher priority devices comes first and there for lower priority devices comes last. The interrupt

What is presentation layer, Q. What is Presentation layer? Presentatio...

Q. What is Presentation layer? Presentation layer: When two hosts are communicating with each other they might use different coding standards and character sets for represent

ANS, Smugglers are becoming very smart day by day. Now they have developed ...

Smugglers are becoming very smart day by day. Now they have developed a new technique of sending their messages from one smuggler to another. In their new technology, they are send

Find the boolean expression for boolean algebra, Find the Boolean expressio...

Find the Boolean expression for logic circuit shown in Figure below and reduce it using Boolean algebra. Ans. Y = (AB)' + (A' + B)' = A' + B' + AB' by using Demorgan's Theorem. =

Determine the indicator variables in a random forest, Given a dataset with ...

Given a dataset with 1000 rows and 25 predictors labeled x1, x2, ...,x25 to classify into two classes {a, b}. Consider the small random forest with 3 trees and one split in each tr

What is the purpose of linq providers in linq, LINQ Providers are a set of ...

LINQ Providers are a set of classes that takes a LINQ query and dynamically produces a method that implements an equivalent query against an exact data source.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd