Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Configure port to send logic, Configure port A for the lower 4 bits to be i...

Configure port A for the lower 4 bits to be inputs and the upper 4 bits to be outputs. The program should chase a logic one from Pa4 -> Pa7, depending upon the condition of Pa0-Pa3

Show the process of message passing, Q. Show the process of message passing...

Q. Show the process of message passing? The subsequent issues are determined by system in process of message passing: 1)  Whether receiver is prepared to receive message

Automated reasoning - first-order logic, Automated Reasoning - first-order ...

Automated Reasoning - first-order logic: The topic known as "Automated Reasoning" in "AI"concentrates mostly on deductive reasoning, here new facts are logically deduced from

Illustrate the logical view of a system, Illustrate the Logical view of a s...

Illustrate the Logical view of a system The Logical view of a system serves to describe existence and meaning of key abstractions and mechanism which form problem space, or wh

Explain isdn address structure and its working, Draw the ISDN address struc...

Draw the ISDN address structure and explain how the addressing works? Address Structure: The ISDN address structure is demonstrated in figure. ISDN number part has a maximum

Differentiate between gateways and bridges, Differentiate between Gateways ...

Differentiate between Gateways and Bridges. A machine that connects a LAN to the Internet is termed as a gateway. The gateway machine is responsible for routing packets that ar

Difference between shadow and override in programming, Overriding tell us o...

Overriding tell us only the methods, but shadowing tells us the entire element.

Instruction per cycle in RISC, Q. Instruction per cycle in RISC? One in...

Q. Instruction per cycle in RISC? One instruction per cycle: A machine cycle is total time taken to fetch two operands from registers perform ALU operation on them and store re

Define http, Http Hyper Text Transfer Protocol: The WWW protocol that...

Http Hyper Text Transfer Protocol: The WWW protocol that performs the request and regain functions of a server. Generally seen as the first part of a website address. It is t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd