Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How a file can be shared among different users, Discuss the different techn...

Discuss the different techniques with which a file can be shared among different users. Several popular techniques with that a file can be shared among various users are: 1

Explain the power dissipation characteristics for digital ic, Explain the ...

Explain the Power Dissipation characteristics for digital IC's. Ans. Power Dissipation: - It is amount of power dissipated in a digital IC. This is determined through

What will be its digital output of an 8-bit ADC, An 8-bit successive approx...

An 8-bit successive approximation ADC has a resolution of 20mV.  What will be its digital output for an analog input of 2.17V? Ans: Given data Resolution =20mv Analog input =2.

How to create a layout table in dreamweaver, Q. How to Create a Layout Tabl...

Q. How to Create a Layout Table in dreamweaver? In last section you used cells to create a table. Now, you will see how to start with a table and add cells later. 1.  In Obj

What are the uses of interrupts, What are the uses of interrupts?  ...

What are the uses of interrupts?  Recovery from errors Debugging Communication among programs Use of interrupts in operating system

Explain the matlab mathematical function library?, This is a huge collectio...

This is a huge collection of computational algorithms ranging from elementary functions like sum, sine, cosine, and difficult arithmetic, to more sophisticated functions like matri

Explain lexical substitution during macro expansion, Explain Lexical substi...

Explain Lexical substitution during macro expansion ? Lexical substitution is used to produce an assembly statement from a model statement. Model statements have 3 kinds of str

Advantages of using clusters, Q. Advantages of using clusters? Para...

Q. Advantages of using clusters? Parallel and distributed applications Decreased turnaround time Balanced loads Utilization of more powerful hosts Access to

Write a program to perform multiplication of two numbers, Q. Write a progr...

Q. Write a program to perform multiplication of two numbers in specified radix. Check that entered numbers are in specified radix or not else error message should be displayed.

Advantages and drawbacks of mealy and moore machine, What are the advantage...

What are the advantages and drawbacks of mealy and moore machine? Advantages and drawbacks: Into Mealy as the output variable is a function both state and input, changes o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd