Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Functional requirements of a control unit, Q. Functional Requirements of a ...

Q. Functional Requirements of a Control Unit? Let's first try to define functions that a control unit should perform in order to get things to happen. However in order to defin

How to join to mwseries from power builder 8.0, Using CICS Transaction Gate...

Using CICS Transaction Gateway we can join MQ Series with Power Builder 8.0

Discuss program testing and debugging in detail, Discuss program testing an...

Discuss program testing and debugging in detail. In program debugging and testing significant steps are as follows: a. For the program, construction of test data b. Analy

Explain arithmetic shift micro-operations, Q. Explain arithmetic shift Micr...

Q. Explain arithmetic shift Micro-operations? In arithmetic shift a signed binary number is shifted to right or to the left. So an arithmetic shift-left causes a number to be m

Explain the input stage of an ADC, Explain the Input Stage of an ADC. ...

Explain the Input Stage of an ADC. Ans. Input Stage- In ADC at the input stage, analog voltage can contain any value in a range although the digital output can contain

Write C++ for following question., We are planning an orienteering game. Th...

We are planning an orienteering game. The aim of this game is to arrive at the goal (G) from the start (S) with the shortest distance. However, the players have to pass all the che

Tightly coupled system- shared memory system, Tightly Coupled System- Share...

Tightly Coupled System- Shared Memory System Shared memory multiprocessorshas has following description: Every processor commune through a shared global memory. For

Explain public switched telephone network, Explain Public Switched Telephon...

Explain Public Switched Telephone Network. PSTN (Public Switched Telephone Network): This is Public Switched Telephone Network (PSTN), which accommodates two types of subscri

Computational study of a spring-mass system, Idealized spring-mass systems ...

Idealized spring-mass systems have numerous applications throughout engineering. Fig.1 shows an arrangement of three masses and four springs which, after is released, is pulled dow

Determine the block diagram of bcd adder, Determine the block diagram of bc...

Determine the block diagram of bcd adder To add 0110 to binary sum, we use a second 4-bit binary adder. The two decimal digits, together with input-carry, are first added in to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd