Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How the at-user command serves mainly in lists, How the at-user command ser...

How the at-user command serves mainly in lists? The AT USER-COMMAND event serves mostly to handle own function codes.  In this case, you should make an individual interface wit

What is the meaning of aliasing, a. What is the meaning of aliasing? What a...

a. What is the meaning of aliasing? What are its drawbacks? Describe a method to remove aliasing, using post filtering. b. How can you copy a Pixmap from one place to another

Including the titles, Your company is planning a party for employees, and y...

Your company is planning a party for employees, and you have been asked to set up a spreadsheet to track the attendees and to measure the associated cost. Every employee is permitt

Concurrently read concurrently write, Q. Concurrently read concurrently wri...

Q. Concurrently read concurrently write? It is one of the models derived from PRAM. In this model the processors access the memory locations simultaneously for reading and writ

Can you list out some of enhancements in verilog 2001, Can you list out som...

Can you list out some of enhancements in Verilog 2001? In  earlier  version  of  Verilog,  we  use  'or'  to  specify  more  than  one  element  in  sensitivity  list.  In Veri

What is collection objects in vb, Likewise to arrays but is preferred over ...

Likewise to arrays but is preferred over an array due to of the following reasons. 1. A collection objects uses less Memory than an array. 2. It gives methods to add and dele

Explain difference between a constant and variable, What is the difference ...

What is the difference between a constant and variable? Explain with example.  A C constant is usually just the written version of a number. For example 1, 0, 5.73, 12.5e9. We

Explain the message passing interface, Q. Explain the Message Passing Inter...

Q. Explain the Message Passing Interface? The Message Passing Interface (MPI) is a universal benchmark for providing communication among multiple simultaneous processes on a di

Cascade delete options, Create a relationship among Employee and Sales tabl...

Create a relationship among Employee and Sales tables using Emp No. Enforce referential integrity and select both cascade update and cascade delete options. Save the relationship.

Find the width of a time division space switch, I n a time division space s...

I n a time division space switch the size of the control memory is N and its Width:  (A) Log 10 M  (B) Log e M  (C) Log N M  (D) Log 2 M Where N are the ou

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd