Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is arithmetic and logic unit, What is Arithmetic and Logic Unit Ar...

What is Arithmetic and Logic Unit Arithmetic and Logic Unit: The ALU is the 'core' of any processor. It implements all arithmetic operations (addition, multiplication, subtract

Define the term grade of service, Define the term Grade of Service. Gr...

Define the term Grade of Service. Grade of Service: In loss systems, the traffic carried through the network is usually lower than the actual traffic offered to the network t

Analysis of sort bitonic, Analysis of Sort_Bitonic(X) The bitonic sorti...

Analysis of Sort_Bitonic(X) The bitonic sorting network needs log n number of phases for performing task of sorting the numbers. The first n-1 phases of circuit can sort two n/

Explain proces of defining the document page title, Q. Explain proces of de...

Q. Explain proces of defining the Document Page Title? Though the document has a file name, notice it's still labelled Untitled Document; that is because it needs an HTML docum

Differences between flexgrid control and dbgrid control, Normal 0 ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Nand gate, The NAND gate. The NAND gate is equivalent to an AND gate fo...

The NAND gate. The NAND gate is equivalent to an AND gate followed by a NOT gate so that the output is 0 when all of the inputs are high, otherwise the output is 1. There may

Address phase - computer architecture, Address phase: A PCI bus transa...

Address phase: A PCI bus transaction starts having an address phase. The initiator,  after seeing that it has GNT# and the bus is inactive, drives the target address onto the

Write a program using linq to find the sum of first 5 prime , Class Program...

Class Program { static void Main() { int[] MyPrimeNumbers = {1,2,3,5,7}; // Use the Count() and Sum() Standard Query Operators to // compute the count an whole su

Array, list advantages of array

list advantages of array

DoDAF OV-2 for a green datacenter, How do I create a DoDAF OV-2 for the con...

How do I create a DoDAF OV-2 for the construction of a green data center?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd