Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Entrepreneurship, explain succession planning and strategies for harvesting...

explain succession planning and strategies for harvesting and ending the venture

Differentiate between qa and testing, Differentiate between QA and testing....

Differentiate between QA and testing. - Quality Assurance is more a stop thing, ensuring quality in the company and thus the product rather than just testing the product for so

Reference table and a reference field, A field containing currency amounts ...

A field containing currency amounts (data type CURR) must be assigned to a reference table and a reference field. Explain. As a reference table, a system having all the valid

What is virtual memory, What is virtual memory? Method that automatical...

What is virtual memory? Method that automatically move program and datablocks into the physical main memory when they are needed for execution are known as virtual memory.

What is serial mouse, Q. What is Serial Mouse? Mice that use standard s...

Q. What is Serial Mouse? Mice that use standard serial port are known as 'serial'. Because Serial ports 1 and 4 (COM1, COM4 under DOS, /dev/ttyS0 and /dev/ttyS3 under Unix/GNU-

DATA DICTIONARY, DATA DICTIONARY ON ONLINE QUIZ SYSTEM

DATA DICTIONARY ON ONLINE QUIZ SYSTEM

Discuss the advantages of store program control, Discuss the advantages of ...

Discuss the advantages of store program control (SPC) automation in telephone switching. Advantages of SPC: (i) Simple to control (ii) Simple to maintain (iii) Fine-

Communication process, 1)    Describe challenges involved for both the send...

1)    Describe challenges involved for both the sender and the receiver in the communication process. 2)    Describe the purpose of a subject line in an email message and give gui

What is the linkage section, The linkage section is part of a known as prog...

The linkage section is part of a known as program that 'links' or maps to data items in the calling program are working storage. It is the part of the called program where these sh

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd