Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain the boolean equations for logic circuits, Explain The Boolean Equat...

Explain The Boolean Equations for Logic Circuits? A Boolean equation is the mathematical representation of a logic circuit using standard Boolean terms. All the logic gates (AND,

What is the conclude of the force of gravity on an object, Q. What is the...

Q. What is the conclude of the force of gravity on an object? Answer:- Force is the vector product of mass as well as acceleration F = ma. Weight is an unusual case of t

C programming, write a program to find the area under the curve y=f(x) betw...

write a program to find the area under the curve y=f(x) between x=a and x=b,integrate y=f(x) between the limits a and b

Explain briefly the generic framework for e-commerce, Explain briefly the g...

Explain briefly the generic framework for e-commerce.  Generic framework of e-commerce contains the Applications of EC   (like as banking, shopping in online stores and malls,

Illustration of parallel programming environments, Q. Illustration of paral...

Q. Illustration of parallel programming environments? Let's discuss illustrations of parallel programming environments of Intel paragaon XP/S and Cray Y-MP software. The Cra

Generic techniques developed - artificial intelligence, Generic Techniques ...

Generic Techniques Developed: In the pursuit of solutions to various problems in the above categories, various individual fundamental techniques have sprung up which have been

Pre-os and runtime sub-os functionality, In a raw Itanium, a "Processor Abs...

In a raw Itanium, a "Processor Abstraction Layer" (PAL) is integrated into the system. When it is booted the PAL is loaded into the CPU and gives a low-level interface that abstrac

Explain about zip drive, Q. Explain about Zip Drive? Zip Drive: Loads...

Q. Explain about Zip Drive? Zip Drive: Loads of files, Volumes of data have definitely increased onus on today's computer user and protection of this data is what bugs every

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd