Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is use case and use case diagram, What is use case and use case diagra...

What is use case and use case diagram? A use case is a coherent piece of functionality that a system can give by interacting with actors. Use case includes one or more actors a

What are the characteristics of sram, What are the characteristics of SRAM?...

What are the characteristics of SRAM? SRAM are fast They are volatile They are of high cost Less density

Pc configuration and troubleshooting, You have been asked to become the con...

You have been asked to become the consulting technician for MobTex, a local auto servicing centre. The general manager (Jo) realises that the IT system has evolved over time with l

Message passing programming, Message passing is possible the most widely us...

Message passing is possible the most widely used parallel programming paradigm these days. It is the most portable, natural and efficient scheme for distributed memory systems. It

Conversion of decimal number 82.67 to its binary equivalent, Conversion of ...

Conversion of Decimal number 82.67 to its Binary Equivalent Ans. Firstly see the integer part 82 and determine its binary equivalent  as The Binary equivalent is (101001

What are the two types of branch prediction techniques, What are the two ty...

What are the two types of branch prediction techniques available?  The two types of branch prediction methods are  1) Static branch prediction  2) Dynamic branch predicti

What is multiple interrupt lines, Q. What is Multiple Interrupt Lines? ...

Q. What is Multiple Interrupt Lines? Multiple Interrupt Lines: Simplest solution to problems above is to provide multiple interrupt lines that will result in immediate recognit

Bus arbitration - computer architecture, Bus arbitration: In single bu...

Bus arbitration: In single bus architecture when more than 1 device requests the bus, a controller known as bus arbiter decides who gets the bus; this is known as the bus arbi

Illustrate working of synchronous counters, Q. Illustrate working of Synchr...

Q. Illustrate working of Synchronous Counters? The main drawback of ripple counter is delay in changing the value. How? To understand this let's take a case when state of rippl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd