Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Combinational logic circuits, A circuit can be designed to perform manydiff...

A circuit can be designed to perform manydifferent functions e.g.a circuit has 3 inputs A, B and C and 3 outputs:Output X is logic level 1 (or 'high') if one or moreinputs are at l

What is access latency and rotation speed, Q. What is Access latency and Ro...

Q. What is Access latency and Rotation Speed? Access latency: A disk access basically moves the arm to selected cylinder and waits for rotational latency that may take less t

Explain redundant array of independent disks levels, Q. Explain Redundant A...

Q. Explain Redundant Array of Independent Disks levels? One such industrial standard that exists for multiple-disk database schemes is called as RAID which implies Redundant Ar

Explain about hexadecimal numbers system, Q. Explain about Hexadecimal Numb...

Q. Explain about Hexadecimal Numbers system? Hexadecimal system has 16 digits that are represented as 0,1,2,3,4,5,6,7,8,9,A,B,C,D,E,F. A number (F2) H is equivalent to

What are the use of job queues and ready queues, What are the use of job qu...

What are the use of job queues, ready queues and device queues? As a process enters a system they are put in to a job queue. These queues having of all jobs in the system. The

Show the bus and memory transfers, Q. Show the Bus and Memory Transfers? ...

Q. Show the Bus and Memory Transfers? A digital computer has many registers and rather than connecting wires amid all registers to transfer information between them a common bu

Plot2fnhand, Write a function "plot2fnhand" that will receive 2 function ha...

Write a function "plot2fnhand" that will receive 2 function handles as input arguments, and will show in two Figure Windows plots of these functions, with the function names in the

Backward chaining - artificial intelligence, Backward Chaining - Artificial...

Backward Chaining - Artificial intelligence Given that we are just interested in constructing the path, we may set our initial state to be the theorem statement and search backw

Gui status in a program from the object browser, Can we create a gui status...

Can we create a gui status in a program from the object browser? Yes.  You can make a GUI STATUS in a program using SET PF-STATUS.

what is polymorphism in c++, Polymorphism in C++ is the idea that a base c...

Polymorphism in C++ is the idea that a base class can be inherited by various classes. A base class pointer can point to its child class and a base class array can store dissimilar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd