Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate the list of key differences to word processors, Illustrate the l...

Illustrate the list of key differences to word processors The following is a list of key differences to word processors: -  Most word processors force users to work on a doc

The advantage of using a database management system, The advantage of using...

The advantage of using a Database Management System The advantage of using a Database Management System for a data store is that databases have mechanisms for describing data,

How can we minimize problems occurring because of branch., Q. How can we mi...

Q. How can we minimize problems occurring because of the branch instructions? We may use various mechanisms which may minimize the effect of branch penalty. To keep mult

Define briefly about extranet, Define briefly about Extranet. Extrane...

Define briefly about Extranet. Extranet: Extranet is Extension of an Intranet which makes the latter available to outside companies or individuals along with or without

Mathematical applications, The current 32 and 64 bit machines can represent...

The current 32 and 64 bit machines can represent integers of around 9 digits and 30 digits respectively, while various scientific and mathematical applications have to represent in

Show organisation of clos network, Q. Show Organisation of Clos network? ...

Q. Show Organisation of Clos network? Clos network: This network was designed by Clos (1953).  It's a non-blocking network and offers full connectivity similar to crossbar netw

Two parallel fetch-implement, Take a CPU that shows two parallel fetch-impl...

Take a CPU that shows two parallel fetch-implement pipelines for superscalar processing. Determine the performance improvement over scalar pipeline processing and no-pipeline proce

Reprographic methods for information distribution, Reprographic Methods ...

Reprographic Methods i) Thermography ii) Dyeline jii) Microfiche iv) Fax In this unit you have learnt that: Used for Methods of reprography are used for the

What is redundant array of independent disks, What is Redundant Array of In...

What is Redundant Array of Independent Disks? Researchers are constantly trying to improve secondary storage media by raising their, performance, capacity as well as reliabilit

Describe memory and memory unit, Q. Describe Memory and Memory unit? In...

Q. Describe Memory and Memory unit? Input devices can fetch instructions or data only sequentially though a program may or may not be executed sequentially because looping, jum

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd