Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Write a subroutine in c which toggles the cursor, Q . Write a subroutine in...

Q . Write a subroutine in C which toggles the cursor? Write a subroutine in C which toggles the cursor. It takes one argument which toggles the value between on (1) and off (0)

I printout the formulas in an excel spreadsheet, How can I printout the for...

How can I printout the formulas in an Excel spreadsheet - rather than the results? Ans) The trick is to change the way Excel shows the worksheet before you choose to print. Ch

Why floating point numbe process than integer, Why floating point number mo...

Why floating point number more difficult to represent and process than integer? In floating point numbers we have to show any number in three fields sign, exponent and mantissa

What is an orthogonal base class in c++, If two base classes have no overla...

If two base classes have no overlapping methods or data they are said to be independent of, or orthogonal to each other. Orthogonal in the sense means that two classes function in

What are two reasons for using layered protocol, What are two reasons for u...

What are two reasons for using layered protocol? Layered protocol implies protocols used into each layer are the layer's own business that is they don't influence protocol of a

Features of mpi-1, Features of MPI-1 Binding for FORTRAN and C ...

Features of MPI-1 Binding for FORTRAN and C Collective communication Communication domains and Process groups Point-to-point communication Virtual process

.bus, clasification of bus

clasification of bus

What is sensitivity list, What is sensitivity list? A list of signals w...

What is sensitivity list? A list of signals which trigger execution of the block when they change value. Sensitivity list  indicates that when a change occurs to any one of

Discuss the important characteristics of 8237, Question 1 Discuss the w...

Question 1 Discuss the working principle of an interrupt and hardware actions in interrupt handling 2 Discuss the important characteristics of 8237 3 Describe the format

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd