Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Characteristics of decision support system, Q. Characteristics of decision ...

Q. Characteristics of decision support system? Characteristics of DSS- The qualities of the DSS are as follows: - 1. DSS focus on towards providing assistance in analyzing s

Convert number to hexadecimal and decimal, Perform the following calculatio...

Perform the following calculations assuming that all numbers are stored in 16-bit registers as 2's complement binary numbers with no overflow provision. Convert each of the numbers

Show the importance of risc processors, Q. Show the Importance of RISC Proc...

Q. Show the Importance of RISC Processors? Reduced Instruction Set Computers recognize a comparatively limited number of instructions. One benefit of a reduced instruction set

Difference among activity and sequence diagram, a. Activity diagram: Activi...

a. Activity diagram: Activity diagram is used for functional modelling. Captures the process flow. b.  Sequence diagram :  Sequence diagram is  used for dynamic modeling.

Displaying the towers of hanoi solution, Once you have a solution to the To...

Once you have a solution to the Towers of Hanoi problem, we want to improve the display of the solution. The details of the implementation are up to you. At a minimum, your impleme

What is control store, What is control store? The microroutines for all...

What is control store? The microroutines for all the instructions in the instruction set of a computer are kept in a special memory known as the control store.

Explain the biometric systems and biometric authentication, Explain the Bio...

Explain the Biometric Systems in brief. Biometrics: It is the science of measuring physical properties of living beings. Biometric Authentication: (a) This authenticati

Main features of TCP, The main features of TCP are: Reliability: TCP...

The main features of TCP are: Reliability: TCP makes sure that any data sent by a sender arrives at destination as it was sent. There can't be any data loss or change in the

Which memory can not be accessed randomly, Which of following can not be ac...

Which of following can not be accessed randomly DRAM, SRAM, ROM or Magnetic tape ? Ans. Magnetic tape cannot be accessed randomly; it can only be accessed sequentially.

Components of magnetic disk, Q. Components of magnetic disk? Disk itsel...

Q. Components of magnetic disk? Disk itself is mounted in a disk drive that comprises arm which is a shaft that rotates disk and the electronics required for input and output b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd