Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Task gantt, The Task Gantt shows the various tasks being performed i.e., so...

The Task Gantt shows the various tasks being performed i.e., some type of activities by the set of processors attached to the parallel computer as shown in Figure . Task Gantt

Determine the use of loop instruction, Q. Determine the use of LOOP instruc...

Q. Determine the use of LOOP instruction? Program: This program prints the alphabets (A-Z) ; Register used: AX, CX, DX CODE SEGMENT ASSUME: CS: CODE.     MAINP:

Interpolation search, Interpolation Search The next task is to implemen...

Interpolation Search The next task is to implement a variable size decrease-and-conquer solution to search. See Levitin [2007] pp 190 for a detailed description of the interpol

Determine the minimum configuration of the decoder, The following switching...

The following switching functions are to be implemented using a Decoder f 1   = ∑ m(1, 2, 4, 8, 10, 14)   f 2   = ∑ m(2, 5, 9, 11)   f 3   = ∑ m(2, 4, 5, 6, 7) The minimum configur

Two ways of converting a two input nand gate to an inverter, 1)      Short ...

1)      Short both I/Ps of NAND gate & use the gate as an inverter. 2)      Connect any one of the two I/Ps to VCC & use the remaining I/P & use the gate as an inverter.

Define the method of implementation, Define the method of Implementation ...

Define the method of Implementation Once "final" system has been designed it is then essential to put together the software and hardware and introduce the new system. There ar

What is meant by questionnaires, What is meant by Questionnaires This ...

What is meant by Questionnaires This includes sending out questionnaires to the work force or/and to customers to find out their views of existing system and to find out how.

Illustrate memory read operation, Q. Illustrate Memory Read operation? ...

Q. Illustrate Memory Read operation? Memory unit receives the address from a register known as the memory address register designated by MAR. Data is transferred to another re

What are the phases of video production, Question 1: a) What are the p...

Question 1: a) What are the phases of video production? b) What do you mean by storyboards? c) What are the differences between Point and Area (or Paragraph) Text?

What is shadow ram, Shadow RAM is a copy of Basic Input/Output Operating Sy...

Shadow RAM is a copy of Basic Input/Output Operating System (BIOS) routines from read-only memory (ROM) into a particular area of random access memory (RAM) so that they can be acc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd