Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Utility functions - artificial intelligence, Utility Functions - artificial...

Utility Functions - artificial intelligence: A goal based on an agent for playing chess is infeasible: at every moment it decides which move to play next, it sees whether that

Example multi-layer ann with sigmoid units, Example Multi-layer ANN with Si...

Example Multi-layer ANN with Sigmoid Units - Artificial intelligence: We will discuss ourselves here with ANNs containing only 1 hidden layer, as this makes describing the back

TITLE: Signals for digital communications, DETERMINE ANALYTICALY IF THE SIG...

DETERMINE ANALYTICALY IF THE SIGNAL IS PERIODIC OR NOT - X[n] = 4Cos(Pi n)

Evaluate fixed execution time, The statement of Gustafson's law can be desc...

The statement of Gustafson's law can be described with the help of an illustration. Let us take a problem, say P, which has to be solved using a parallel computer. Let Ts be the ti

Design a 32:1 multiplexer, Design a 32:1 multiplexer using two 16:1 multipl...

Design a 32:1 multiplexer using two 16:1 multiplexers and a 2:1 multiplexer Ans. Design a 32 X 1 MUX by using two 16 X 1 MUX and one 2 X 1. Now here total 32 input lines

And-elimination rule, And-Elimination rule: In generally English says ...

And-Elimination rule: In generally English says that "if you know that lots of things are all true, so you know like any one of them is also true". Because you can specify a c

Types of buses, different types of buses with diagram

different types of buses with diagram

Illustrate working of synchronous counters, Q. Illustrate working of Synchr...

Q. Illustrate working of Synchronous Counters? The main drawback of ripple counter is delay in changing the value. How? To understand this let's take a case when state of rippl

State the basic properties of this analytical engine, State the basic prope...

State the basic properties of this analytical engine The basic properties of this analytical engine are: It was a common purpose programmable machine. It had provisi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd