Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Types of classification-classification of parallel computers, Types Of Clas...

Types Of Classification The following classification of parallel computers have been recognized: 1)      Categorization based on the data streams and instruction 2)

Illustrate about the single inheritance, Illustrate about the single inheri...

Illustrate about the single inheritance During inheritance, superclass feature may by override by a subclass defining that feature with the same name. The overriding features (

Explain 32 to 1 multiplexer tree, Why is Multiplexer Tree needed? Draw ...

Why is Multiplexer Tree needed? Draw the block diagram of a 32:1 Multiplexer Tree and explain how input is directed to the output in this system. Ans. One of the possible

Describe the various characteristics of udp protocol, Describe the various ...

Describe the various characteristics of UDP protocol. The characteristics of the UDP are as follows: End to end: UDP is transport protocols that can distinguish between

Explain cpu based exchange, Explain CPU based exchange. CPU Based Exch...

Explain CPU based exchange. CPU Based Exchange: All the control equipment is replaced with a single processor that must be quite powerful, in centralized control. This should

Task gantt, The Task Gantt shows the various tasks being performed i.e., so...

The Task Gantt shows the various tasks being performed i.e., some type of activities by the set of processors attached to the parallel computer as shown in Figure . Task Gantt

What is the meaning of user interaction, a. What is the meaning of user int...

a. What is the meaning of user interaction? What are the dissimilar styles in which forms of interaction can be classified? Give one advantage, disadvantage and an example of every

What is ale and explain the functions of ale in 8085, ALE-> Address latch e...

ALE-> Address latch enable...In the case of microcontroller (8051)& microprocessor 8085 the data line and low order 8 bit address lines are multiplexed. In order to getting address

Page directive include, What is the difference between, page directive incl...

What is the difference between, page directive include, action tag include? Ans) One difference is whereas using the include page directive, in translation time it is making t

What is java awt, An AWT stands for Abstract Window Toolkit. AWT handles pr...

An AWT stands for Abstract Window Toolkit. AWT handles programmers to develop Java applications with GUI components, like windows, and buttons. The Java Virtual Machine (JVM) is re

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd