Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Manipulate the presentation and attributes interactive list, How can you m...

How can you manipulate the presentation and attributes of interactive lists? ---Scrolling by Interactive Lists. ---Setting the Cursor from within the Program. ---Changing

Define micro operation, Define Micro operation. The operations implemen...

Define Micro operation. The operations implemented on data stored in the registers are called Micro operation. A microperation is an elementary operation performed on the infor

Define top-down parsing techniques, Define Top-down parsing Techniques ...

Define Top-down parsing Techniques Top-down parsing can be observed as an attempt to find left-most derivations of an input-stream through searching for parse trees using a top

Which algorithm is used to solve computational problems, Which algorithm is...

Which algorithm is used to solve computational problems If we want to solve any problem then we use a series of well-defined steps. These steps are collectively known as algori

Explain data warehousing, data warehousing Data warehouse means  ...

data warehousing Data warehouse means  Subject oriented Integrated Time variant Non-volatile collection of data for management's decisions. It is h

Is the data bus is bi-directional, The data bus is Bi-directional because t...

The data bus is Bi-directional because the similar bus is used for transfer of data among Micro Processor and memory or input / output devices in both the direction.

C programming, There is a pebble merchant. He sells the pebbles, that are u...

There is a pebble merchant. He sells the pebbles, that are used for shining the floor. His main duty is to take the length of the room’s sides. But he sometimes mistakes doing that

I2c protocol bus , I²C TECHNOLOGIES The I2C protocol bus is two bi-dire...

I²C TECHNOLOGIES The I2C protocol bus is two bi-directional wires, serial data (SDA) and serial clock (SCL), that transmit information between the devices connected to the bus.

Work in standard view, Layout view is helpful for laying out Web pages. How...

Layout view is helpful for laying out Web pages. However you can adjust most of your design elements in Layout view, certain changes should be completed in Standard view. When you

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd