Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

State about the object oriented analysis, State about the Object oriented a...

State about the Object oriented analysis Object oriented analysis (OOA) is concerned with developing software engineering specifications and requirements that expressed as a s

What is tri-state logic, What is Tri-state logic ? Ans. Tri-state Logi...

What is Tri-state logic ? Ans. Tri-state Logic: In common logic circuits, there are two states of the output, as LOW and HIGH. If the output is not in the LOW state, this

What is the ccitt standard bandwidth for speech, The CCITT standard bandwid...

The CCITT standard bandwidth for speech is: (A) 20000 Hz                                  (B) 15000 Hz (C) 7000 Hz                                    (D) 3400 Hz Ans:

What are the type of internet connection, What are the type of Internet con...

What are the type of Internet connection When determining requirements for a VPN, carefully estimate the number of systems to be put behind the VPN, the number of concurrent u

Addition NO-SIGNS to the Write statement, Suppressing the number signs (+/-...

Suppressing the number signs (+/-) is carried out using the addition NO-SIGNS to the Write statement. Statement is false.

List-processing without using suppress-dialog, What happens if we use Leave...

What happens if we use Leave to list-processing without using Suppress-Dialog? If we don't use Suppress-Dialog to next screen will be viewed but as empty, when the user presse

What is the working set of a process, What is the working set of a process?...

What is the working set of a process? The set of pages that are referred by the method in the last "n", references, where "n" is called the window of the working set of the pro

Find the generating function, Find the generating function to denote the nu...

Find the generating function to denote the number of ways the sum 9 can be acquired while 2 distinguishable fair dice are tossed and the first shows an even number and the second s

Explain latex in matlab, Matlab already handles naturally easy LaTeX encodi...

Matlab already handles naturally easy LaTeX encodings that permit introducing Greek lettters or modifying the font size and appearance in plots.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd