Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Determine the 2's complement subtraction, Perform 2's complement subtractio...

Perform 2's complement subtraction of (7) 10 - (11) 10 . Ans. 2's Complements Subtraction of (7) 10 - (11) 10 Firstly convert the decimal numbers 7 and 11 to there binary e

What is rdram, Direct Rambus DRAM or DRDRAM (sometimes just known as Rambus...

Direct Rambus DRAM or DRDRAM (sometimes just known as Rambus DRAM or RDRAM) is a type of synchronous dynamic RAM. RDRAM was formed by Rambus inc., in the mid-1990s as a replacement

What is a demultiplexer, What is a Demultiplexer ? Ans. Demultiplex...

What is a Demultiplexer ? Ans. Demultiplexer has similar circuit as decoder but here E is obtained as the particular input line, the output lines are similar as decode

Goals and design principles, This is an applied unit that shows you how to ...

This is an applied unit that shows you how to assess interactive products against a selection of usability and user experience goals. It also introduces a selection of design princ

Menu driven program with following menu, Q.  Develop a Menu driven program ...

Q.  Develop a Menu driven program with following menu: 1.  Gray code 2.  BCD 3.  Excess-3 code 4.  Exit I/P must be a valid Binary number. Fractional numbers are all

Probabilistic hough transformation, The probabilistic Hough transform uses ...

The probabilistic Hough transform uses random sampling instead of an accumulator array. In this approach the number of random samples r, is not specified in the OpenCV call, but

System software, System Software System software is a group of progr...

System Software System software is a group of programs written to service another programs. Some system software (e.g., compilers editors and file management utilities) proc

Draw a diagram to illustrate the design pattern, Problem: (a) What show...

Problem: (a) What shows a Pattern a Pattern? (b) Which pattern is given below? Justify your answer. public class A { private static A instance = null; private A() {

Find the minimum sop and pos expression, Find the minimum SOP and POS expre...

Find the minimum SOP and POS expression for the following functions using Karnaugh Map and realize the expression using appropriate gates. Also realize SOP form using NAND-to-NAND

What is garbage collection and what is it used for, In computer science, ga...

In computer science, garbage collection (GC) is a form of automatic memory management. The garbage collector, or just collector, attempts to reclaim garbage, or memory occupied by

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd