Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Why eprom chips are mounted in packages, Why EPROM chips are mounted in pac...

Why EPROM chips are mounted in packages that have transparent window? Since the erasure needs dissipating the charges trapped in the transistors of memory cells. This can be co

Sosail studies, whitch goods did the new england colonies exportto england ...

whitch goods did the new england colonies exportto england and what did they get in return

What is the task of the pass 2 in a two-pass assembler, In a two-pass assem...

In a two-pass assembler, the task of the Pass II is to? Ans. The task of the Pass II is to synthesize the target program in a two-pass assembler.

Define memory access time, Define memory access time? The time needed t...

Define memory access time? The time needed to access one word is known as the memory access time. Or It is the time that elapses among the initiation of an operation and the co

Functions of an operating system, Question a) In multitasking Operatin...

Question a) In multitasking Operating Systems, there are two kinds of multitasking such as the "Preemptive Multitasking" and the "Cooperative Multitasking". Explain the two me

Convert the following into sop form, Q. Convert the following into SOP form...

Q. Convert the following into SOP form   1. (A+B) (B'+C) (A'+ C) 2. (A+C) (AB'+AC) (A'C'+B) 3. (A'+B') (C'+B)   Q.Convert the following into POS form   1. WYZ + XYZ + W'X'

Internal structure of agents - artificial intelligence, Internal Structure ...

Internal Structure of Agents: We have looked at agents in terms of their external influences and behaviors: they put in from the surroundings and perform rational actions to a

Explain definition of fibonacci, Explain definition of fibonacci Where ...

Explain definition of fibonacci Where an input value gives a trivial result, it is returned directly, otherwise the function calls itself, passing a changed version of the inpu

What is uml, ? UML is called as Unified Modeling Language. ? it is used...

? UML is called as Unified Modeling Language. ? it is used to Graphical language for visualizing artifacts of the system. ? It Allow to make a blue print of all the aspects

How e-commerce website works, Procedure The only difference between e-...

Procedure The only difference between e-commerce and conventional commerce is that goods in e-commerce are purchased over the internet using a credit card. Also buying and sel

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd