Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define cache line, Define cache line. Cache block is used to refer to a...

Define cache line. Cache block is used to refer to a set of contiguous address location of some size. Cache block is also referred to as cache line.

Explain about diodes, Q. Explain about Diodes? A single pn-junction wit...

Q. Explain about Diodes? A single pn-junction with appropriate contacts for connecting the junction to external circuits is called a semiconductor pn-junction diode. The fundam

Explain automated and manual systems, Q. Explain Automated and Manual syste...

Q. Explain Automated and Manual systems? Automated and Manual systems: The system that doesn't need human intervention is known as'Automated system'. In this system whole proce

Determine the analog output voltage of 6-bit DAC, Determine the analog outp...

Determine the analog output voltage of 6-bit DAC (R-2R ladder network) with Vref as 5V when the digital input is 011100. Ans. The analog output for 6-bit R-2R DAC ladder network

Asp.net, how work for asp.net

how work for asp.net

What are the techniques of data collection, What are the techniques of Data...

What are the techniques of Data Collection It can be either automatic or manual. Manual techniques can include: -  Keypads/Keyboards to type in data -  touch screens to s

What are packages, What are packages? Package is a group of elements (c...

What are packages? Package is a group of elements (classes, generalizations, associations and lesser packages) with a common theme. Package partitions a model making it simpler

4, Ask question 4#Minimum 100 words accepted#

Ask question 4#Minimum 100 words accepted#

Describe set-associative mapping, Q. Describe Set-Associative Mapping? ...

Q. Describe Set-Associative Mapping? A third type of cache organization known as set-associative mapping is an improvement on direct mapping organization in that every word of

Production-centered virtual manufacturing, Production-Centered Virtual Manu...

Production-Centered Virtual Manufacturing It utilizes simulation ability to manufacturing process models along with the purpose of permitting inexpensive, fast evaluation of va

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd