Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is elapsed time of computer system, What is elapsed time of computer s...

What is elapsed time of computer system? The total time to implement the total program is known as elapsed time. It is affected by the speed of the processor, the disk and the

What are the super computers, SUPER COMPUTER The upper end of state of ...

SUPER COMPUTER The upper end of state of art mainframe machine is the supercomputer. These  are  the  fastest  machines  in  terms  of  processing  speed  and  use multiprocess

Nix commands, reate a directory "Unix" under your home directory. Command(...

reate a directory "Unix" under your home directory. Command(s): ………………………………………….

Full form of www, What do you understand by WWW WWW: The World Wide ...

What do you understand by WWW WWW: The World Wide is an architectural framework for accessing linked documents increase out over thousands of machines all over the world. It

Illustrate working of synchronous counters, Q. Illustrate working of Synchr...

Q. Illustrate working of Synchronous Counters? The main drawback of ripple counter is delay in changing the value. How? To understand this let's take a case when state of rippl

Probabilistic hough transformation, The probabilistic Hough transform uses ...

The probabilistic Hough transform uses random sampling instead of an accumulator array. In this approach the number of random samples r, is not specified in the OpenCV call, but

How to fix an asic-based design from easiest to most extreme, How to fix an...

How to fix an ASIC-based design from easiest to most extreme? There are different ways to fix an ASIC-based design as given below: Initially, assume some reviews fundamentally.

Determine the hardware for multiplication, Determine the hardware for multi...

Determine the hardware for multiplication The hardware for multiplication consists of equipment given in Figure. The multiplier is stored in register and its sign in Q . The se

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd