Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How many select lines will have a 16 to 1 multiplexer, How many select line...

How many select lines will a 16 to 1 multiplexer will have ?   Ans. For 16 to 1 MUX four select lines will be needed to select 16 (2 4 ) inputs.

Computer network, how Hierarchical Routing implement in c or cpp

how Hierarchical Routing implement in c or cpp

What do you mean by directives, Q What do you mean by Directives? Assem...

Q What do you mean by Directives? Assembly languages support numerous statements. This allows you to control the way in which a source program assembles and list. These stateme

Optical resolution of scanner, Optical resolution or hardware resolution is...

Optical resolution or hardware resolution is mechanical limit on resolution of Scanner. For scanning the sensor has to advance after every line it scans. Smallness of this advancem

Explain topology method used in lan technology in detail, Explain topology ...

Explain topology method used in LAN technology in detail. LAN Topologies: Network topology is a physical schematic that shows interconnection of the various users. There are

What search method would be most appropriate and why, (a) Describe fully in...

(a) Describe fully in your own words the following terms: (i) Turing Test (ii) Agent (iii) Utility-based agent (b) A Mars rover has to leave the lander, collect rock sample

EME, How can i made Carnot engine

How can i made Carnot engine

What is telnet, Telnet It is a terminal emulation program for TCP/IP ne...

Telnet It is a terminal emulation program for TCP/IP networks like as the Internet. The Telnet program runs on your computer and attaches your PC to a server on the network. On

What is a system call, What is a system call? A  system  call  is  a  r...

What is a system call? A  system  call  is  a  request  made  through  any  program  to  the  operating  system  for performing tasks, picked by a predefined set, that the said

What is a pipeline hazard, What is a pipeline hazard? Any condition tha...

What is a pipeline hazard? Any condition that causes the pipeline to stall is known as hazard. They are also known as stalls or bubbles.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd