Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Why eprom chips are mounted in packages, Why EPROM chips are mounted in pac...

Why EPROM chips are mounted in packages that have transparent window? Since the erasure needs dissipating the charges trapped in the transistors of memory cells. This can be co

Explain the configuration of a step-by-step switching system, With neat dia...

With neat diagrams explains the configuration of a step-by-step switching system. The schematic diagram for an exchange is specified in figure. Each subscriber is associated to

Calculate traffic offered in erlangs in a particular exchang, In a particul...

In a particular exchange during busy hour 1200 calls were offered to a group of trunks, during this time 6 calls were lost. The average call duration being 3 minutes Calculate Traf

Applications of microprogramming - computer architecture, Applications of M...

Applications of Microprogramming: Microprogramming application:: emulation o   Use of a micro program on 1 machine to execute programs initially written to run on ano

When the get cursor command used in interactive lists, When the get cursor ...

When the get cursor command used in interactive lists? If the hidden information is not enough to uniquely recognize the selected line, the command GET CURSOR is used.  The GET

Design-centered virtual manufacturing, Design-Centered Virtual Manufacturin...

Design-Centered Virtual Manufacturing This gives manufacturing information to the designer throughout the design phase. In this observing the short term and long time definitio

Illustrate the execute cycle, Q. Illustrate the Execute Cycle? The fetc...

Q. Illustrate the Execute Cycle? The fetch and indirect cycles include a small, fixed sequence of micro-operations. Every one of these cycles has fixed sequence of micro-operat

Dbms, Find a 3NF decomposition of the following relation scheme: University...

Find a 3NF decomposition of the following relation scheme: University (Faculty, Dean, Department, Chair, Professor, Rank, Student}. The University relation satisfies the following

Various phases of consumer merchantile model, What are the various phases o...

What are the various phases of consumer merchantile model and also differentiate between prepurchase interaction & post purchase interaction.    There are three phase of consumer

What is gustafsons law, Q. What is Gustafsons Law? Amdahl's law is app...

Q. What is Gustafsons Law? Amdahl's law is appropriate for applications where response time is significant. On the other hand there are numerous applications that necessitate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd