Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Predicates, Fred, Barney and Ralph belong to the La Trobe Mountain Club. Ev...

Fred, Barney and Ralph belong to the La Trobe Mountain Club. Every member of the Club is either a skier or a hiker. Anyone that doesn't like snow does not like skiing. No hikers li

Characteristics of magnetic disk, Q. Characteristics of Magnetic disk? ...

Q. Characteristics of Magnetic disk? Tracks and Sectors: Disk is divided in concentric rings known as tracks. Thus a track is one complete rotation of disk underneath read/wr

Related to Project, PROCEDURE TO CREATE PROJECT IN COLLABORATION SYSTEM

PROCEDURE TO CREATE PROJECT IN COLLABORATION SYSTEM

Computer arcticture, what is the main goal of parallel processing

what is the main goal of parallel processing

Determine the bios function with one illustration, Determine the BIOS funct...

Determine the BIOS function with one illustration BIOS stands for Basic Input Output System. It is a set of programs to provide most basic low-level services like services keyb

State the disadvantages of interviewing, State the Disadvantages of  inter...

State the Disadvantages of  interviewing -  can be expensive to carry out    -  can be a very time consuming exercise -  Unable to remain anonymous

Explain region, What is a Region? A Region is a continuous area of a p...

What is a Region? A Region is a continuous area of a process's address space (like text, data and stack). The kernel in a "Region Table" that is local to the process mainta

Define emulation, Define emulation. Given a computer with a particular ...

Define emulation. Given a computer with a particular instruction set, it is possible to explain additional machine instructions and execute them with extra micro routines. Emul

Calculate the blocking probability of three stage network, A three stage ne...

A three stage network is designed with the following parameters: M=N=512, p = q = 16 and α = 0.65. Calculate the blocking probability of the network, if s=16. Symbols carry th

How is the connectivity established in verilog, How is the connectivity est...

How is the connectivity established in Verilog when connecting wires of different widths? When connecting wires or ports of different widths, connections are right-justified, S

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd