Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is status control and registers, Q. What is Status Control and Registe...

Q. What is Status Control and Registers? Status Control and Registers: These registers can't be used by programmers though are used to control CPU or execution of a program.

Why does dma have priority over the cpu, Why does DMA have priority over th...

Why does DMA have priority over the CPU when both request a memory transfer? The data transfer monitored by DMA controller which is called as DMA channel. The CPU is included o

Vliw architecture, Vliw Architecture Superscalar architecture was desig...

Vliw Architecture Superscalar architecture was designed to develop the speed of the scalar processor. But it has been realized that it is not easy to execute as we discussed pr

What are the objectives of usb, What are the objectives of USB? a) Simp...

What are the objectives of USB? a) Simple b) Low cost c) Easy to use d) Supports wide range of data transfer characteristics e) Plug and play mode of operation

Explain about the cathode ray tube technology, Cathode Ray Tube Technology ...

Cathode Ray Tube Technology (CRT) CRT is an analog device that is used by a digital device - computer. The interface between these two devices is described. The major component

Explain in details the various standard i/o interfaces, Explain in details ...

Explain in details the various standard I/O interfaces. The various standard I/O interfaces are:  1. The Peripheral component interconnect(PCI) bus is a standard that suppor

State the term- interviewing, State the term- Interviewing This involv...

State the term- Interviewing This involves a one to one question & answer session between analyst and customer/employee. A good method if analyst wants to probe deeply into on

Design a nand-to-and gate network, Q Use as few gates as possible, design a...

Q Use as few gates as possible, design a NAND-to-AND gate network that realize the following Boolean algebra expression. ABCD + A'BC'D + A'BC'D' + A'BCD + (A'B'C'D' + A'BCD')

Explain the configuration of a step-by-step switching system, With neat dia...

With neat diagrams explains the configuration of a step-by-step switching system. The schematic diagram for an exchange is specified in figure. Each subscriber is associated to

Pd controller, PD controller Student should aim for Kp and Kd value that...

PD controller Student should aim for Kp and Kd value that will minimize the steady error with improved rise time and settling time. The amount of over shoot should not be more t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd