Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What do you mean by best fit, What do you mean by best fit?  Best fit a...

What do you mean by best fit?  Best fit allocates the smallest hole that is big enough. The whole list has to be searched, unless it is sorted by size. This method makes the sm

Explain what is the difference among isr & function call, In ISR there is n...

In ISR there is no return value but in function call there is return value

Characteristics of the id process, The following is taken from the first ed...

The following is taken from the first edition of the Set Book. We have included this because we find these characteristics helpful. We will refer to them later. In addition to t

What is critical section problem, What is critical section problem? A ...

What is critical section problem? A race condition at data item occurs when many processes simultaneously update its value data consistency, needs that only one process should

Information system for strategic advantage, Q. Describe short note on Infor...

Q. Describe short note on Information system for strategic advantage? Ans. Strategic role of information systems engage using information technology to develop products or serv

What is precloud computing, What is precloud computing? Precloud comput...

What is precloud computing? Precloud computing is an email access was through a single computer, which also keeps all email messages. Example: Microsoft Outlook or Outlook Expr

Distinguish between e-mode and depletion mode mosfet, Distinguish between e...

Distinguish between enhancement mode and depletion mode metal oxide semiconductor field effect transistors giving their characteristics. Ans. Enhancement mode and depleti

What is a message in mqseries, A message is a string of bytes that has mean...

A message is a string of bytes that has meaning to the applications that use it Message = Header(s) + Application Data A message having of a header and the attached applicat

What are the main aspects available in all word processors, What are the Ma...

What are the Main aspects available in all word processors -  Ability to set page size and page orientation -  Ability to change font size and font style (for example Arial,

Explain j2ee, With respect to security, which one is the better choice? ...

With respect to security, which one is the better choice? .Net or J2EE? Explain? As per majority programmers .NET is the best one which have single vendor compare to, the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd