Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Operating characteristics for master-slave s-r flip-flop, Define the Operat...

Define the Operating Characteristics for master-slave S-R flip-flop? 1. Propagation Delay Time - is the interval of time required subsequent to an input signal has been applied

Sap security audit log, You are required to use software of your choice (sp...

You are required to use software of your choice (spreadsheet, database, statistical package etc) to analyze the provided SAP security audit log data ( Userdata.xls ), generate appr

ECS, what is ecs?

what is ecs?

Public key infrastructure solutions, Public Key Infrastructure solutions ...

Public Key Infrastructure solutions The use of public-key based security systems requires great attention and due care in design and management of security features. The secur

Three firm capabilities that are performance in e-commerce, Three firm capa...

Three firm capabilities that are critical for superior firm performance in e-commerce are:- 1.  Information technology capability,  2.  Strategic flexibility, and  3.  Tr

How many words can be acquired by the word universal, How many words can be...

How many words can be acquired by arranging the letters of the word 'UNIVERSAL' in different way? In how many of them  (i)  E, R, S takes place together (ii)  No two of the

What is line option explicit, What is line option explicit Line explici...

What is line option explicit Line explicit function makes the compiler to recognize all the variables which are not particular by the dim statement. This command significantly

Approaches for development of information systems, Q. Approaches for develo...

Q. Approaches for development of information systems? Numerous approaches are available for development of Information Systems. They are as below: • Model Driven: It put e

Describe program control instructions, Q. Describe Program Control Instruct...

Q. Describe Program Control Instructions? These instructions specify conditions for altering the sequence of program execution or we can say in other words that the content of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd