Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain what is defecttracker, DefectTracker from Pragmatic Software - D...

DefectTracker from Pragmatic Software - Defect Tracker is a fully web-based defect tracking and hold up ticket system that manages issues and bugs, customer needs, test cases, a

Subtract the numbers using 2's complements, Subtract -27 from 68 using 2's ...

Subtract -27 from 68 using 2's complements. Ans. By using 2's complement 68-(-27)= 68-(-27) 2's complement representation of 68 = 01000100(64+4) 2's complement representatio

State the various security tools, State the various Security Tools Sec...

State the various Security Tools Securing an Intranet is not a simple task. Just as articles in a house are protected by use of various types of security systems such as lock

The javascript validation not run on the asp.net, Why The JavaScript Valida...

Why The JavaScript Validation Not Run on the Asp.Net? The Asp.Net Button Is post backed on the server & not yet Submit & when it goes to the server its states is lost so if we

Explain the term- wire and register, What is the difference between wire an...

What is the difference between wire and reg? Net types: (wire,tri)Physical connection between structural elements. Value assigned by a continuous assignment or a gate output.

Explain the different fields of an instructions, Explain the significance o...

Explain the significance of different fields of an instruction An instruction is a command given to a computer to perform a particular operation on some given data and the form

Show encoding data options, Q. Show Encoding data options? PVM uses SUN...

Q. Show Encoding data options? PVM uses SUN's XDR library to make a machine independent data format if you request it. Settings for encoding option are:  PvmDataDefault: Use

Execution-modes of a multiprocessor, Q. Explain Execution-modes of a multip...

Q. Explain Execution-modes of a multiprocessor? Execution-modes of a multiprocessor: Several modes of multiprocessing comprise parallel execution of programs at (i) Fine Grain

How many and gates are required to realize Y = CD+EF+G, How many AND gates ...

How many AND gates are required to realize Y = CD+EF+G ? Ans. Y = CD + EF + G for realize this two AND gates are needed (for CD and EF).

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd