Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate when are intermolecular forces the strongest, Q. Illustrate when...

Q. Illustrate when are intermolecular forces the strongest? Answer:- Intermolecular forces dispersion and dipole-dipole and hydrogen bonds. These forces are feeble than ch

Forall statement in fortran, Q. FORALL Statement in fortran? The FORALL...

Q. FORALL Statement in fortran? The FORALL statement permits for more common assignments to sections of an array. A FORALL statement has general form.   FORALL ( triplet, ..

Show the hypothetical instruction format of 32 bits, Q. Show the Hypothetic...

Q. Show the Hypothetical Instruction Format of 32 bits? A sample instruction format is shown in figure below. Figure: A Hypothetical Instruction Format of 32 bits

What are the benefits of web-based spreadsheets, What are the Benefits of W...

What are the Benefits of Web-Based Spreadsheets? The spreadsheets can be accessed from any Internet-connected computer, not just the computer originally formed the spreadsh

Explain bitwise-and operator, Bitwise-AND Operator: & AND-expression : ...

Bitwise-AND Operator: & AND-expression : relational-expression AND-expression & equality-expression The bitwise-AND operator (&) compares each bit of its first operand t

System programming, concurrentisation and vectorisation of program

concurrentisation and vectorisation of program

Project on adaptive concept map, to develop an adaptive concept map providi...

to develop an adaptive concept map providing personalized learning for Operating System subject with text file(in any form like html,ppt,txt,doc,pdf)as input

What are universal gates, What  are  universal  gates.  Construct  a  lo...

What  are  universal  gates.  Construct  a  logic  circuit  using  NAND  gates  only  for  the expression x = A . (B + C). Ans. Universal Gates: NAND and NOR Gates both are t

An algorithm, find cos(x) and sin(x) an pseudocode (while loop

find cos(x) and sin(x) an pseudocode (while loop

Explain the storage class extern, Explain The Storage Class extern The...

Explain The Storage Class extern The Storage Class extern : One method of transmitting information across blocks and functions is to use external variables. When a variable is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd