Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are advantages and drawbacks of flip-flop, What are advantages and dra...

What are advantages and drawbacks of flip-flop? Usually area of a Flip-flop for features in more than a latch. Power consumption is normally higher, because of the area and

Inspirations of artificial intelligence, Inspirations of artificial intelli...

Inspirations of artificial intelligence: Artificial Intelligence research can be easily understood by following example in terms of how the following question has been answere

What is user defined functions, What is User Defined Functions? User-De...

What is User Defined Functions? User-Defined Functions permit defining its own T-SQL functions that can accept 0 or more parameters and return a single scalar data value or a t

Difference between classical ai and statistical ai, Statistical AI, arising...

Statistical AI, arising from machine learning, tends to be more concerned with "inductive" thought: given a set of patterns, make the trend. Classical AI, on the other hand, is mor

How does cpu know that an interrupt has taken place, How does CPU know that...

How does CPU know that an interrupt has taken place? There needs to be a line or a register or status word in CPU which can be increased on occurrence of interrupt situation.

How to convert binary to octal and hexadecimal, Q. How to convert Binary to...

Q. How to convert Binary to Octal and Hexadecimal? Rules for these conversions are simple. For converting binary to octal binary number is splitted in groups of three, that are

Name various work processes of r/3 system, Name various work processes of R...

Name various work processes of R/3 system? A) Dialog or Online (processes only one request at a time). B) Background (Started at a specific time) C) Update (primary or se

What is scsi, What is SCSI? Ans: It is the acronym for small computer s...

What is SCSI? Ans: It is the acronym for small computer system interface. It refers to a standard bus explained ANSI. Devices such as disks are linked to a computer via 50-wire

What is the function of the correction system, What is the function of the ...

What is the function of the correction system? The correction system handles changes to internal system components. Like as objects of the ABAP/4 Dictionary.

Explain why the ROM is a volatile memory, Is the ROM a volatile memory? Exp...

Is the ROM a volatile memory? Explain Ans. No, ROM is a Non-Volatile memory. Programming of ROM includes making of the needed  interconnections at  the time of fabrication and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd