Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Implementing protection with virtual memory, Implementing Protection with V...

Implementing Protection with Virtual Memory - computer architecture: To enable the operating system to implement protection in the VM system, the HW have to: I. Support at

What is dialog module, What is dialog Module? A dialog Module is a call...

What is dialog Module? A dialog Module is a callable sequence of screens that does not belong to a certain  transaction. Dialog modules have their module pools, and can be know

Interpreter, difference between pure and impute inter preter

difference between pure and impute inter preter

Important points of simulations, Important points of simulations In thi...

Important points of simulations In this simulation it is essential to consider: (1)  What and how data is gathered (2)  How simulation is done (3)  How system would wo

What is macro, A series of keystrokes and mouse clicks that can be abbrevia...

A series of keystrokes and mouse clicks that can be abbreviated into a one keystroke or mouse click.

What is synchronous reset, What is Synchronous reset? Synchronous reset...

What is Synchronous reset? Synchronous reset: Synchronous reset logic will synthesize to smaller flip-flops, mainly when the reset is gated along with the logic generating t

Explain about server synchronization, Q. Explain about Server synchronizati...

Q. Explain about Server synchronization? Server synchronization: It updates atom by server process of requesting process. In this method an atom acts as a unique update server.

Show example of copy command, Q. Show example of COPY command? This COP...

Q. Show example of COPY command? This COPY command copies the REPORT file from the drive C to the disk in drive A. after copying the file in drive A, it will name the new file

What do you mean by information system, Q. What do you mean by Information ...

Q. What do you mean by Information System? An information system is an planned combination of hardware, people, communication networks, software and data resources that transfo

Explain the concept of thread, The Concept of Thread A thread is a sequ...

The Concept of Thread A thread is a sequential flow of control within a process. A process is able to have one or more threads. Threads have their own register-values and progr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd