Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the counters, What are the Counters? 1. The Counter is a seque...

What are the Counters? 1. The Counter is a sequential circuit which consists of a set of flip flops connected in a appropriate manner to count the sequence of input pulses.

Explain advantages and disadvantages of macro pre-processor, What are the a...

What are the advantages and disadvantages of macro pre-processor? Advantages Any of existing conventional assembler can be improved in this way to incorporate macro proces

Working on dreamweaver, Write your text, format text, insert picture throug...

Write your text, format text, insert picture through Object window or INSERT -> IMAGE. Insert Menu provides you all features which are available under the Object window. Modify men

How is transaction processing system affected, How is Transaction Processin...

How is Transaction Processing System affect performance of e-commerce sites? Transaction Processing System influences performance of e-commerce sites: Transaction-Processing

#title.sequential circuit, design modulo 12 up synchronous counter using t ...

design modulo 12 up synchronous counter using t flip flop

What is a user diagram protocol, UDP (User Diagram Protocol) is? It is ...

UDP (User Diagram Protocol) is? It is both Connectionless and Message Oriented.

Rule in a single direction - equivalences rules, Rule in a single direction...

Rule in a single direction - equivalences rules: Hence there the power to replace  sub expressions always allows use to prove theorems with equivalences: as given in the above

What are universal gates, What  are  universal  gates.  Construct  a  lo...

What  are  universal  gates.  Construct  a  logic  circuit  using  NAND  gates  only  for  the expression x = A . (B + C). Ans. Universal Gates: NAND and NOR Gates both are t

Physics, #questionabut diffraction ..

#questionabut diffraction ..

Explain the concept of concurrent and parallel execution, The Concept of Co...

The Concept of Concurrent and Parallel Execution Real world systems are concurrent in nature and computer science is about modeling the real world. Illustrations of real world

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd