Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How do you add a developer to a trusted publishers list, Whenever a develop...

Whenever a developer is signing into the code project you will have three options they are disable the macro, enable the macro and explicitly trusting the publisher. You can trust

Micooperation, please suggest me ,how to write microopertions,and study for...

please suggest me ,how to write microopertions,and study for computer architecture

Determine the factor consider when selecting digital encoder, 1. What facto...

1. What factors should be considered when selecting a digital encoder (line codes)? Briefly mention five of those factors. Use sketches and additional text to describe the followin

Show mpi functions, Q. Show MPI functions? MPI comprises hundreds of fu...

Q. Show MPI functions? MPI comprises hundreds of functions which are a small subset of which is enough for most practical purposes. We will discuss some of them here. Int M

Basic of C, write algorithm and draw flowchart for exchange the values of t...

write algorithm and draw flowchart for exchange the values of two variables.

Describe about the protection features present in ms access, If a programme...

If a programmer doesn't wish to make modifies to the document he can lock the document data and its code from more changes by changing the extension of the file system to .MDE. Cha

Subtract, Write the Add/subtract rule for floating point numbers. Ans:...

Write the Add/subtract rule for floating point numbers. Ans: a. Select the number with the smaller exponent and shift its mantissa right a number of steps equal to the differe

Perform binary subtraction on following, Q Perform Binary Subtraction on fo...

Q Perform Binary Subtraction on following: 1) 1101-1000 2) 111.11-101.1 3) 1101.1-1010.01 Q Perform Binary Multiplication & Division on following: 1) 16*2.75 2) 1

Programming for arithmetic and string operations, Advanced aspects of assem...

Advanced aspects of assembly language programming in this section. A number of these aspects give assembly an edge over high level language programming as far as efficiency is conc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd