Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate simple ALU organisation, Q. Illustrate Simple ALU Organisation? ...

Q. Illustrate Simple ALU Organisation? An ALU comprises circuits which perform data processing micro-operations. Though how are these ALU circuits used in conjunction of other

Classify scheduler, Classify Scheduler. Scheduler is a kernel function ...

Classify Scheduler. Scheduler is a kernel function decide which method  be  thought to be implemented by the processor: the scheduler scans the list of processes in the ready s

Explain in detail about the dynamic timing, Explain in detail about the Dyn...

Explain in detail about the Dynamic timing a. Design is simulated in full timing mode. b. Not all possibilities tested, as it is dependent on input test vectors. c. Simul

Internal organization of memory chip - computer architecture, Internal Orga...

Internal Organization of memory chip: Word line & bit lines 16x8 organization : 16 words of 8 bits per Form of an array

Application using shift operations, Application Using Shift Operations ...

Application Using Shift Operations Rotate and Shift instructions are helpful even for division andmultiplication. These operations are not normally available in high-level lang

What is synchronous message passing, Q. What is Synchronous message passing...

Q. What is Synchronous message passing? In Synchronous message passing is executed on synchronous communication network.  In that case sender and receiver processes should be

Find fiber distributed data interconnect is an example of, FDDI (Fiber Dist...

FDDI (Fiber Distributed Data Interconnect) is an example of? Fiber Distributed Data Interconnect is an illustration of token ring.

Explain use of mpi functions with an example, Q. Explain use of MPI functio...

Q. Explain use of MPI functions with an example? include int main(int argc, char **argv) { int i, tmp, sum, s, r, N, x[100]; MPI_Init(&argc, &argv); MPI_Comm_size

Compiling and running the pvm program, Now we will learn how to compile and...

Now we will learn how to compile and run PVM programs. To compile the program change to directory pvm/lib/archname where archname is architecture name of your computer. Then the su

What is core dump, Raises when accessing an unassigned memory location acce...

Raises when accessing an unassigned memory location accessing a null pointer

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd