Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How to get the column count of a report, How to get the column count of a r...

How to get the column count of a report? SY-LINSZ system variable gives the column count (line size) and SY-LINCT for line count.

Explain about ip access, Explain about IP Access. IP access on the netw...

Explain about IP Access. IP access on the network by: • Intranets onto Virtual IP Networks and • Extranets onto Virtual IP Networks.

Show encoding data options, Q. Show Encoding data options? PVM uses SUN...

Q. Show Encoding data options? PVM uses SUN's XDR library to make a machine independent data format if you request it. Settings for encoding option are:  PvmDataDefault: Use

Find out how many words can be formed from daughter, Find out how many word...

Find out how many words can be formed out of the letters of the word DAUGHTER such that (i)  The vowels are all time together. (ii)  The vowels occupy even places.   Ans:

What are the objectives of uml, What are the Objectives of UML tra...

What are the Objectives of UML trace development of UML; recognize and describe notations for object modelling using UML; describe a variety of structural and be

How to create dlq rules table, DLQ - Dead Letter Queue If an applicati...

DLQ - Dead Letter Queue If an application tries to put a message to one more application and if it is not delivered then it goes to the DLQ. So DLQ is not anything but all und

What are the data types of the abap/4 layer, What are the Data types of the...

What are the Data types of the ABAP/4 layer? Possible ABAP/4 data types: C: Character. D: Date, format YYYYMMDD. F: Floating-point number in DOUBLE PRECISION (8 bytes)

Operating characteristics for master-slave s-r flip-flop, Define the Operat...

Define the Operating Characteristics for master-slave S-R flip-flop? 1. Propagation Delay Time - is the interval of time required subsequent to an input signal has been applied

Explain firewall, A firewall is Software or hardware used to separate a...

A firewall is Software or hardware used to separate a private network from a public network.

Advantages of mpi, Advantages of MPI: Every process has its own loc...

Advantages of MPI: Every process has its own local variables It can be used on a broader range of problems than OpenMP It runs on either distributed or shared memor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd