Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Find the conversion time & conversion rate of A/D converter, Find the conve...

Find the conversion time of a Successive Approximation A/D converter which uses a 2 MHz clock and a 5-bit binary ladder containing 8V reference. What is the Conversion Rate? An

Application of Theory of computation in DBMS, Sir/Mam, I want to know the a...

Sir/Mam, I want to know the application of Theory of computation in DBMS

Computer graphics, what is boundary filling explain with example

what is boundary filling explain with example

Buses - computer architecture, Buses: Execution of 1 instruction ne...

Buses: Execution of 1 instruction need the following 3 steps to be performed by the CPU: I.  Fetch the contents of the memory location pointed at by the computer syst

Explain vector reduction instructions, Vector reduction Instructions Wh...

Vector reduction Instructions When operations on vector are being decreased to scalar items as a result then these are vector reduction instructions. These instructions are ref

When recursion functions are declared inline, Describe what happens when re...

Describe what happens when recursion functions are declared inline? Ans) Inline functions property says whenever it will call; it will copy the whole definition of that functi

Iot, what is ardiuno explain its working

what is ardiuno explain its working

Spirit duplicating of information, Spirit Duplicating Equipment Requir...

Spirit Duplicating Equipment Required Spirit Duplicator (also known as hectograph) Thermal copier (optional) Materials Masters Hectographic carbon COPY pa

Overview of the dreamweaver work area, Q. Overview of the Dreamweaver work ...

Q. Overview of the Dreamweaver work area? Let's start with a brief overview of the Dreamweaver work area. If you haven't already launched Dreamweaver, double-click Dreamweaver

Compare a decoder and a demultiplexer with block diagram, Compare a decoder...

Compare a decoder and a demultiplexer with suitable block diagrams. Ans. Demultiplexer has similar circuit as decoder but here e is obtained as the particular input line, the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd