Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Types of classification-classification of parallel computers, Types Of Clas...

Types Of Classification The following classification of parallel computers have been recognized: 1)      Categorization based on the data streams and instruction 2)

Difference between external and global variables, Global variables are acce...

Global variables are accessible only to the batch program while external variables can be referenced from any batch program residing in the similar system library.

Explain the potential role of information technology, Question 1: Descr...

Question 1: Describe the five maturity levels of KM that an organization faces when adopting the Frid's KM framework. Question 2: (a) Describe three major issues that

Functions for message passing, Functions for Message Passing: MPI proc...

Functions for Message Passing: MPI processes don't share memory space and one process can't directly access other process's variables. Therefore they need some form of communi

How to clear a datagrid on a button click, How to clear a datagrid on a but...

How to clear a datagrid on a button click? You require to Clear the DataSource of the dataGrid. So try this: dataSet1.Clear(); dataGrid1.DataSource = dataSet1.TableNam

What do you mean by best fit, What do you mean by best fit?  Best fit a...

What do you mean by best fit?  Best fit allocates the smallest hole that is big enough. The whole list has to be searched, unless it is sorted by size. This method makes the sm

Children''s game of rock, Design a game application that plays the children...

Design a game application that plays the children's game of rock, paper, scissors. The user enters a letter indicating a choice. The Math.random method is then used to pick a value

Illustrate decimal fixed point representation, Q. Illustrate Decimal Fixed ...

Q. Illustrate Decimal Fixed Point Representation? The point of this representation is to keep the number in decimal equivalent form and not binary as above. A decimal digit is

Illustrate the text area, specifies a form field where user can enter large...

specifies a form field where user can enter large amounts of text. In most respects, works like an field. It can have a name as well as a def

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd