Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain about multidimensional features present in olap, Multidimensional s...

Multidimensional support is very necessary if we are to contain multiple hierarchies in our data analysis. Multidimensional feature permits a user to examine business and organizat

Define a register, Define a register. Ans:  Register:   A register...

Define a register. Ans:  Register:   A register contain a group of flip-flops and gates which effect their transition. The flip flops hold the binary information and the g

Why sram are said to be volatile, Why SRAM are said to be volatile? Bec...

Why SRAM are said to be volatile? Because their contents are lost when power is interrupted. So SRAM are said to be volatile.

What is modem?, A device, usually linked to a serial port of a computer, th...

A device, usually linked to a serial port of a computer, that transfer data over regular phone lines. Modem stands modulator demodulator; it changes a digital stream of data into s

Failures, FAILURES Since reliability engineering is focused on the surv...

FAILURES Since reliability engineering is focused on the survivability or absence of failures, it is more concerned about failures,  understanding  their causes and defining re

Explain management information base variables, Explain MIB (Management Info...

Explain MIB (Management Information Base) variables. MIB is a set of named items which an SNMP agent knows. To control or monitor a remote computer, a manager should fetch or s

Explain a binary semaphore, Explain a binary semaphore with the help of an ...

Explain a binary semaphore with the help of an example? An abstract data type (ADT) is a semaphore which defines a nonnegative integer variable that apart from initialization i

What is vector processing, What is vector processing?  There is ...

What is vector processing?  There is a class of computational problems that are beyond the capabilities of a conventional computer. These problems are characterized by t

Explain moores law and amdahls law, Question (a) Imagine you need to mo...

Question (a) Imagine you need to move people through a distance of 10 miles, with the following specifications. • Car: capacity = 5, speed = 60 miles/hour • Bus: capacity

What is a multitape tm, What is a multitape TM?  A  multi-tape  Turing ...

What is a multitape TM?  A  multi-tape  Turing  machine  having  of  a  finite  control  with  k-tape  heads  and k-tapes each tape is infinite in both directions. On a one mov

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd