Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is the security vulnerabilities for vba, Microsoft Visual basic has it...

Microsoft Visual basic has its host of problems one such being macros, Macros can be formed which can make havoc for a programmer with good intentions. Also the security issue rest

Define the example client-server implementations, Define the Example Client...

Define the Example Client-server Implementations Once you accept the client-server mindset, the process of architecting and developing applications becomes rather easy. Clearly

Explain about dual in line memory modules, Q. Explain about Dual In line Me...

Q. Explain about Dual In line Memory Modules? A DIMM is capable of delivering 64 data bits right away. Usual DIMM capacities are 64MB and up. Every DIMM has 84 gold patted conn

Versions of small computer systems interface, Q. Versions of small computer...

Q. Versions of small computer systems interface? SCSI-1 calls for a cable with 8 data wires plus one for parity. SCSI-2 allows use of multiple cables to support 16- or

Information system today, What is the benefit of MITRE''s evolutionary appr...

What is the benefit of MITRE''s evolutionary approach to KM?

Explain in detail about the random scan display, Explain in detail about th...

Explain in detail about the Random Scan Display   This device using CRT directs the electron beam only to the parts of the screen where a picture is to be drawn. This kind of d

Differentiate between sequential access and direct access, Question: (a...

Question: (a) Briefly explain how the functionality of the WWW has been enhanced, after its birth at CERN site. Use examples to illustrate your answer. (b) Many modern com

Fitness function - canonical genetic algorithm, Fitness function - canonica...

Fitness function - canonical genetic algorithm: Conversely the fitness function will use an evaluation function to calculate a value of worth for the individual accordingly th

Describe the micro programmed control unit in detail, Describe the micro pr...

Describe the micro programmed control unit in detail. A micro programmed control unit is built around a storage unit is known as a control store where all the control signals a

What is an avl tree, What is an AVL tree? AVL Tree An AVL tree is...

What is an AVL tree? AVL Tree An AVL tree is a binary tree in which the dissimilarity in heights among the left and the right subtree is not more than one for each node.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd