Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Embedded software, Embedded Software Intelligent products have becom...

Embedded Software Intelligent products have become commonplace for all consumer and industrial market. Embedded software stays in read only memory and is utilised to control

Works flowing related technologies influence e-business, How the works do f...

How the works do flowing related technologies influence e-business? Work Flow related Technologies influence e-business: Microsoft CRM automates internal business process

Xor gate, The XOR gate. The exclusive OR or XOR gate is similar to a tw...

The XOR gate. The exclusive OR or XOR gate is similar to a two input OR gate. The output of an XOR gate is logic 1 only when one input or the other input is high and is 0 when

The extra key inserted at the end of the array, The extra key inserted at t...

The extra key inserted at the end of the array is called a Sentinel is the extra key inserted at the end of the array

What is non-repudiation, What is non-repudiation? Non Repudiation: Assu...

What is non-repudiation? Non Repudiation: Assurance that the sender is given with proof of delivery and that the recipient is provided with proof of the sender's identity so th

Explain register marker, Explain Register marker. Register marker: St...

Explain Register marker. Register marker: Strowger selectors doing searching and counting. Conversely, the crossbar switch has no 'intelligence'. Something external to the

Explain difference between macro call and macro expansion, Explain differen...

Explain difference between macro call and macro expansion. Macro expansion: While a macro name is used along with a set of actual parameters this is replaced through a code g

What is meant by hide area, What is meant by hide area? The hide comman...

What is meant by hide area? The hide command temporarily kept the contents of the field at the present line in a system-controlled memory called as the HIDE AREA.  At an intera

Cookies for one page in your site, How do you turn off cookies for single p...

How do you turn off cookies for single page in your site? We can turn off the cookies for one page:- By setting the Cookie. Discard property false.

Acting rationally - artificial intelligence, Acting Rationally: "Al" C...

Acting Rationally: "Al" Capone was finally convicted for tax evasion. Were the police reacting on rationally?? To solve this puzzle, we must first look at how the performance

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd