Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

How enterprises are using bpr in their e-business processes, One of the mos...

One of the most important competitive strategies for E-Businesses today is business process reengineering. BPR is more than automating business processes to make modest improvement

What are the steps followed in testing, What are the steps followed in test...

What are the steps followed in testing? i. Unit testing - The individual components are tested in this method of testing. ii. Module testing - Related collection of independ

What is micro programmed control, What is micro programmed control? Mic...

What is micro programmed control? Micro programmed control is a scheme in which control signals are formed by a program same to machine language program.

What is a pre-processor, What is a pre-processor? A pre-processor is a ...

What is a pre-processor? A pre-processor is a program that procedure the source code before it passes by the compiler. It handles under the control of pre-processor directive.

What is switched mode power supply, Q. What is Switched Mode Power Supply? ...

Q. What is Switched Mode Power Supply? SMPS is the unit into which electric supply from the mains is connected to your PC and this supplies DC to internal circuits. It is more

Internal structure of agents - artificial intelligence, Internal Structure ...

Internal Structure of Agents: We have looked at agents in terms of their external influences and behaviors: they put in from the surroundings and perform rational actions to a

Find the magnetic declination, Question Use the National Geophysical Da...

Question Use the National Geophysical Data Center software tool to find the magnetic declination. The link to the web site is in Useful Links on the course Blackboard home page

Explain the process of inter-register signalling, Explain the process of in...

Explain the process of inter-register signalling. Registers are utilized in common control exchanges to store and analyze routing data. They are given on a common basis is a

What is non-volatile bios, Nonvolatile BIOS memory refers to a small memory...

Nonvolatile BIOS memory refers to a small memory on PC motherboards that is used to kept BIOS settings. It was traditionally known as CMOS RAM because it used a volatile, low-power

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd