Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define looping in assembly language, Q. Define looping in assembly language...

Q. Define looping in assembly language? LOOPING  ; Program: Assume a constant inflation factor that is added to a series of prices ; stored in the memory. The program

Convert binary number in two''s compliment form, Convert binary number in t...

Convert binary number in two's compliment form 0100 1000. Converting the binary number into 2's compliment from 0100 1000 is given below: 01001000 => 10111000

Explain about floating-executive model, Q. Explain about Floating-Executive...

Q. Explain about Floating-Executive model? Floating-Executive model: The master-slave kernel model is too restrictive in sense that only one of processors viz designated master

The periodic table of elements, Make a data structure to store information ...

Make a data structure to store information about the elements in the periodic table of elements.  For each element, store the name, atomic number, chemical symbol, class, atomic we

Define syntax of mpi_bcast function, Q. Define syntax of MPI_Bcast function...

Q. Define syntax of MPI_Bcast function? MPI_Bcast(msgaddr, count, datatype, rank, comm):   This function is used by a process ranked rank in group comm to transmit messag

Determine the nand gate, If  the input to T-flipflop is 100 Hz signal, the ...

If  the input to T-flipflop is 100 Hz signal, the final output of the three T-flipflops in cascade is ? Ans. The  final  output  of  the  three  T-flip-flops in cascade is 12

Write-allocate and no-write-allocate policy in a cache, (a) How does a da...

(a) How does a data cache take advantage of spatial locality? Give an suitable example. (b) What are the basic differences between a write-allocate and no-write-allocate po

Explain two dimensional array, Explain two dimensional array In two dim...

Explain two dimensional array In two dimensional arrays, array is a pointer-to-pointer-to-data type.: at the first level, it points to a block of pointers, one for each row. Th

Techniques are used to increase the clock rate r, What techniques are used ...

What techniques are used to increase the clock rate R? Ans: The 2 techniques used to increase the clock rate R are: 1. We can reduce the amount of processing done in one basi

Terms in propositional model, Terms in Propositional model: There in f...

Terms in Propositional model: There in first-order logic allows us to talking about properties of objects that the first job for our model (Δ, Θ) is to assign a meaning to the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd