Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

When gravity is the merely force acting on an object, Q. When gravity is th...

Q. When gravity is the merely force acting on an object the object is in what? Answer:- One respond is that it is in free-fall in a vacuum to eliminate atmospheric drag.

What is the meaning of rigging, Rigging is use for if we need to give anima...

Rigging is use for if we need to give animation for any object or character then we apply to character or object internal bone setting(like our bones).that is known as rigging. Whe

What is artificial intelligence recognition, There are two goals to AI; the...

There are two goals to AI; the major one is to produce an artificial system that is about as good as or good than a human being at dealing with the actual world. The second goal is

Explain about ALU organisation, ALU ORGANISATION An ALU performs simple...

ALU ORGANISATION An ALU performs simple arithmetic and logic operation as well as shift operations. Complexity of an ALU relies on the type of instruction set for that it has b

Calculate grade of service in a particular excahange, In a particular excha...

In a particular exchange during busy hour 1200 calls were offered to a group of trunks, during this time 6 calls were lost. The average call duration being 3 minutes Calculate

State the relative addressing, State the Relative addressing The locati...

State the Relative addressing The location of data is specified relative to current value of the program counter. This is helpful for specifying location of data which is given

Explain time switching, Explain Time Switching. Time Switches: The ...

Explain Time Switching. Time Switches: The principle of a time switch is demonstrated in figure. This connects an incoming n channel PCM highway to an outgoing n channel PC

4 bit comparator, how to breadboARD THE 4 BIT COMPARATOR

how to breadboARD THE 4 BIT COMPARATOR

Security, We now consider the relation between passwords and key size. For ...

We now consider the relation between passwords and key size. For this purpose consider a cryptosystem where the user enters a key in the form of a password. Assume a password consi

Explain a TTL NAND gate and its operation, Give the circuit of a TTL NAND g...

Give the circuit of a TTL NAND gate and explain its operation in brief. Ans: Operation of TTL NAND Gate: Fig.(d) Demonstrates a TTL NAND gate with a totem pole output.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd