Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Program size for different instruction set approaches, Q. Program size for ...

Q. Program size for different Instruction Set Approaches? Assumptions: Complex Instruction is: Add C, A, B having 16 bit addresses and 8 bit data operands All opera

Vector, Explain the characteristics of vector processing

Explain the characteristics of vector processing

Explain what are the different hazards, There are situations, called hazard...

There are situations, called hazards that stop the next instruction in the instruction stream from implementing during its designated clock cycle. Hazards decrease the performance

Difference between absolute and relative path, What is the difference betwe...

What is the difference between absolute and relative path name of a file? Absolute path name: This is listing of the directories and files from the root directory to the i

difference among primary and secondary storage device, In primary storage ...

In primary storage device the storage capacity is fixed. It has a volatile memory. In secondary storage device the storage capacity is not limited. It is a nonvolatile memory. Prim

Control unit (cu)-array processing, Control Unit (CU)  : Every PEs are unde...

Control Unit (CU)  : Every PEs are under the control of one control unit. CU controls the inter communication among the PEs. There is a local memory of CU also known as CY memory.

Develop a regular expression for real number and identifier, Develop a regu...

Develop a regular expression for Real number with optional fraction and Identifier. (i) A regular expression for real number with optional fraction is [+ | -] (d) +. (d)* (i

Udp, udp connection establishment and termintion

udp connection establishment and termintion

How do you find out if a linked-list has an end, By 2 pointers you can find...

By 2 pointers you can find it. One of them goes 2 nodes each time. The second one goes at 1 node each time. If there is a cycle, the one that goes 2 nodes every time will eventuall

Define the edge-triggered flip-flops, Define the Edge-Triggered Flip-flops?...

Define the Edge-Triggered Flip-flops? An edge-triggered flip-flop changes states either at the negative edge (falling edge) or at the positive edge (rising edge) of the clock p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd