Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define encapsulation- object oriented technology, Define Encapsulation- obj...

Define Encapsulation- object-oriented technology Encapsulation also called as information hiding, is the characteristic of separating the external aspects of an object, from t

Data phases - computer architecture, Data phases: After the address ph...

Data phases: After the address phase (particularly, starting with the cycle that DEVSEL# goes low) comes a burst of one or more data phases. In all the cases, initiator drives

Micooperation, please suggest me ,how to write microopertions,and study for...

please suggest me ,how to write microopertions,and study for computer architecture

How address resolution is performed with table lookup, How address resoluti...

How address resolution is performed with table lookup? Explain with the help of a suitable example. The approach of table lookup to address resolution needs a data structure wh

Credit line, The Credit Line The Credit Line is a set of informational f...

The Credit Line The Credit Line is a set of informational facts usually found below or beside a picture of a work of art. Should the picture appear in a book, magazine, poster,

Hardware design of a typical system, Motorola 68HC11 series is a family of ...

Motorola 68HC11 series is a family of micro controllers , each device contains slightly different  functional blocks , however they are all based around the same microprocessor nam

Define the types of software life cycle, Define the types of software life ...

Define the types of software life cycle Any system progress refers to the initial part of the software life cycle: analysis, design, and implementation. During object oriented

Define syntax of barrier directive, Q. Define syntax of barrier directive? ...

Q. Define syntax of barrier directive? Barrier Directive  The syntax of barrier directive is  #pragma omp barrier When a thread attains barrier it waits till all threa

What is double entry - verification, What is Double entry - Verification ...

What is Double entry - Verification In this approach, data is entered twice (using two different people); data is only accepted if both versions match up. Generally used to ve

Computer graphics, What is intractive graphics and user dialouge in comput...

What is intractive graphics and user dialouge in computer graphics

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd