Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the advantages of public key cryptography, What are the advantages...

What are the advantages of Public Key Cryptography? Advantages of Public Key Cryptography are illustrated in below: a) Increased convenience and security and b) Electro

Structure of 8086 cpu, 8086 microprocessor comprises two independent units:...

8086 microprocessor comprises two independent units:  1.  Bus Interface unit 2.  Execution unit Please refer to Figure below. Figure: The CPU of INTEL 8086 Microp

Graph has a minimum spanning tree already computed, Assume that a graph has...

Assume that a graph has a minimum spanning tree already computed.  How fastly can the minimum spanning tree be updated if a new vertex and incident edges are added to G? If the

External program components, How does the system handle roll areas for exte...

How does the system handle roll areas for external program components? Transactions run in their own roll areas. Reports run in their own roll areas. Dialog modules run

The concept of process-parallel computing, The Concept of Process Infor...

The Concept of Process Informally, a method is a program in execution, behind the program has been loaded in the main memory. However, a method is more than just a program code

What is trivial file transfer protocol, What is trivial file transfer proto...

What is trivial file transfer protocol? Explain briefly? Trivial File Transfer Protocol (i.e. TFTP) is helpful for bootstrapping a hardware device which does not have a disk on

Works flowing related technologies influence e-business, How the works do f...

How the works do flowing related technologies influence e-business? Work Flow related Technologies influence e-business: Microsoft CRM automates internal business process

What are the advantages of having e-commerce over extranets, What are the a...

What are the advantages of having e-commerce over extranets?     Extranets are about " joining up" the supply chain-suppliers, resellers, distributors, customers, etc.-enabling

gui component handle its own events, A component can handle its own events...

A component can handle its own events by executing the needed event-listener interface and adding itself as its own event listener.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd