Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is wap, What is WAP? WAP is stands for Wireless Application Proto...

What is WAP? WAP is stands for Wireless Application Protocol. It is a global, open standard which gives mobile users access to Internet services by handled devices. Wireless A

Mathcad solution to compute the ellipsoid radii , Question: Write a Mat...

Question: Write a MathCad solution to compute the ellipsoid radii at a point. Use the defining parameters for the GRS80 ellipsoid - a and f - in table 19.1. Program Equation 19

Distinguish between complex type and simple type elements, Problem: (a)...

Problem: (a) (i) Distinguish between Complex Type and Simple Type elements. (ii) List two benefits while using XSDs in XML data modeling. (b) Both XML schema and XSL u

Where shared resources are accessed, A critical section is a program segmen...

A critical section is a program segment? Ans. A critical section is a program segment where shared resources are accessed.

Principles of composition, PRINCIPLES OF COMPOSITION The principles of ...

PRINCIPLES OF COMPOSITION The principles of composition are the way that the elements of composition are used to achieve a particular purpose. Some of the main principles of co

What is constrained-random verification, What is Constrained-Random Verific...

What is Constrained-Random Verification ? As ASIC and system-on-chip (SoC) designs continue to increase in size and complexity, there is an equal or greater increase in the si

How video effects alters a video, Question : (a) What are the main aspe...

Question : (a) What are the main aspects that should be considered when dealing with green screen? (b) Explain clearly how these video effects alters a video using an illust

Coupling and cohesion, Coupling and cohesion can be shown using a:- Dep...

Coupling and cohesion can be shown using a:- Dependence matrix

Describe key features of the von neumann architecture, Q. Describe key feat...

Q. Describe key features of the von Neumann Architecture? Describe key features of the von Neumann Architecture: The mainly basic function performed by a computer is exe

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd