Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain the working of a half subtractor, With the help of a truth table ex...

With the help of a truth table explain the working of a half subtractor. Draw the logic diagram using gates. Ans: Half Subtractor: For the subtraction of B (subtrahend) f

What are attributes, What are Attributes?  Attributes are declarative ...

What are Attributes?  Attributes are declarative tags in code that insert additional metadata into an assembly. There exist two types of attributes in the .NET Framework: Pred

Add multiple layout cells, Q. Add Multiple Layout Cells ? Next you will...

Q. Add Multiple Layout Cells ? Next you will add three layout cells below the logo cell you just created. Afterwards you will insert page's navigation buttons in these cells.

#artificial intelligence, does matlab contain procedures for knoledge repre...

does matlab contain procedures for knoledge representation? if yes where can i find it?

What is flag, Flag is a flip-flop used to kept the information about the st...

Flag is a flip-flop used to kept the information about the status of a processor and the status of the instruction implemented most recently A software or hardware mark that si

Execution of a program in cpu, Execution of a program in CPU is completed e...

Execution of a program in CPU is completed employing different set of registers and their individual circuitry. As CPU registers are used for execution of interrupt service routine

What are the layers of data description in r/3, What are the layers of data...

What are the layers of data description in R/3? There layesr are there:- The external layer. The ABAP/4 layer. The database layer.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd