Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Name the languages introduced in second generation, Name the languages intr...

Name the languages introduced in second  generation During  the time of  second  generation  many  high  level  programming  languages  were introduced, such as FORTRAN (1956),

Find out lowest propagation delay time in logic family, Which the digital l...

Which the digital logic family has the lowest propagation delay time ? Ans. ECL is the digital logic family that has the lowest propagation delay time. In ECL lowest propagati

Overview of the dreamweaver work area, Q. Overview of the Dreamweaver work ...

Q. Overview of the Dreamweaver work area? Let's start with a brief overview of the Dreamweaver work area. If you haven't already launched Dreamweaver, double-click Dreamweaver

What are the features of cisc processors, What are the Features of CISC Pro...

What are the Features of CISC Processors The standard features of CISC processors are listed below:  CISC chips have a large amount of dissimilar and complex instructions.

Users to run programs at same time, A computer system that allows multiple ...

A computer system that allows multiple users to run programs at similar time   Multi tasking system

What is difference between cgi and java, CGI and JAVA are fundamentally dis...

CGI and JAVA are fundamentally dissimilar, and for most applications are NOT interchangable. CGI is a protocol for running programs on a WWW server. Whilst JAVA can also be us

Calculate traffic lost in a particular exchange, In a particular exchange d...

In a particular exchange during busy hour 1200 calls were offered to a group of trunks, during this time 6 calls were lost. The average call duration being 3 minutes Calculate Tr

What is memory mapped i/o, What is memory mapped I/O? When the I/O devi...

What is memory mapped I/O? When the I/O devices share the similar address space, the arrangement is known as memory mapped I/O.

Why we need web browser, Q. why we need Web Browser? A Web browser is s...

Q. why we need Web Browser? A Web browser is software program which allows you to easily display Web pages and navigate the Web. The first graphical browser, Mosaic, was develo

Representation of real-system, Maria opened her authentic Mexican restauran...

Maria opened her authentic Mexican restaurant MiCazuela in Tucson inthe 1980s. It quickly became popular for the tasty food and use of fresh organicproduce and all-natural meats. L

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd