Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate about first generation computers, Q. Illustrate about First Gene...

Q. Illustrate about First Generation Computers? It is certainly ironic that scientific inventions of great impact have frequently been linked with supporting a very sad as well

Give difference between top down and bottom up parsing, Give difference bet...

Give difference between top down parsing and bottom up parsing. Top down parsing: Specified an input string, top down parsing tries to derive a string identical to this by s

What are difference between mealy and moore state machine, What are differe...

What are difference between Mealy and Moore state machine? Difference between Mealy and Moore state machine: 1) Mealy and Moore models are the fundamental models of state ma

List one advantage & disadvantage of having large block size, List one adva...

List one advantage and one disadvantage of having large block size. Ans: Advantage: By using a huge block of memory is maximum process's accommodation that resulting is less no

Illustrate 16-bit isa, Illustrate 16-bit ISA?  Compare it with 8-bit ISA bu...

Illustrate 16-bit ISA?  Compare it with 8-bit ISA bus.  The only difference between 8 and 16-bit ISA bus is that an extra connector is attached behind the 8-bit connector. 16-b

Implement and - or- not gates using bit wise operator, Q. Develop  a menu d...

Q. Develop  a menu driven program to implement AND, OR, NOT gates using and without using  Bit wise operator. The menu  should  be  as follows: I.  Using Bit Wise operator I

General principles of pruning, General principles of pruning: The gene...

General principles of pruning: The general principles are such that: 1. Given a node N that can be chosen by player one, thus if there is another node, X, along any path,

Explain direct addressing mode with example, Q. Explain Direct Addressing M...

Q. Explain Direct Addressing Mode with example? Direct Addressing Mode A direct operand signifies to contents of memory at an address referred by the name of the variable.

Define overflow, Define Overflow.  An overflow is a problem in digital ...

Define Overflow.  An overflow is a problem in digital computer due to the width of registers is finite. A result that contains n+ 1 bit cannot be accommodated in a register wit

Explain the functioning of firewall using screening router, Explain the fun...

Explain the functioning of Firewall Using Screening Router. Firewall Using Screening Router: The risk of break-within is large along with this form of firewall: Eve

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd