Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Control-centered virtual manufacturing, Control-Centered Virtual Manufactur...

Control-Centered Virtual Manufacturing This is the addition of simulations to control actual processes and models, permitting for seamless simulation for optimization throughou

Give the difference between register and counter, Q. Give the difference be...

Q. Give the difference between Register and Counter. Q. Give the difference between Flip-flop and Latch. Q. Draw a set of waveforms for following signal on out-put line.

Use string manipulating functions , Write a script that will first initiali...

Write a script that will first initialize a string variable that will kept x and y coordinates of a point in the form 'x 3.1 y 6.4'.  Then, use string manipulating functions to ext

Breif on loosely coupled systems, Loosely Coupled Systems These s...

Loosely Coupled Systems These systems don't share global memory since shared memory concept increases the problem of memory conflicts, which consecutively slows down the

What are the advantages of using structure in c program, What are the advan...

What are the advantages of using structure in C Program Declaring a struct is a two-stage process. The first stage defines a new data type that has the required structure which

Ai6301 - building blocks and techniques used in ai, The princess (or princ...

The princess (or prince if you're female) has been captured by the Evil Dragon and held prisoner in a tower. The tower is also surrounded by a maze to keep out the riff-raff. You

Microprocesser, explain the bock and pin diagram of 8259 micropocesser

explain the bock and pin diagram of 8259 micropocesser

What do you mean by digital computer, COMPUTER ORGANIZATION & ARCHITECTURE ...

COMPUTER ORGANIZATION & ARCHITECTURE 1. What do you mean by digital computer? Explain the block diagram of a digital computer. 2. What do you mean by Difference Engine? Expl

4bit counter using JK flip flop and unique sequence, Need to build a 4bit J...

Need to build a 4bit JK flip flop counter with a unique patter. 6 4 2 5 3 1 F C B A

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd