Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is wireless transmission systems, What are wired and wireless transmis...

What are wired and wireless transmission systems? Transmission Systems: Modern type long distance transmission systems can be placed in three wide categories: 1. Radio Sy

Problems.., what are the different types of tablets?

what are the different types of tablets?

Define edge triggered d flip flop, Define Edge Triggered D flip-flop? D...

Define Edge Triggered D flip-flop? D latch has only two inputs C(control) and D(data). The operation of a D flip-flop is a lot simpler and it has only one input addition to the

Bit serial associative processor (bsap), Bit Serial Associative Processor (...

Bit Serial Associative Processor (BSAP) : When the associative processor accepts bit serial memory organization then it is known as bit serial associative processor. While only one

Explain multihomed host, Write short notes on the Multihomed host. A ho...

Write short notes on the Multihomed host. A host computer that connects to multiple networks is termed as multi-homed host. Multihoming is occasionally used to raise reliabilit

Explain complex instruction set computer, CISC (Complex Instruction Set Com...

CISC (Complex Instruction Set Computer) CISC stands for Complex Instruction Set Computer. If the control unit having a number of micro-electronic circuitry to make a set of con

State the data flow diagramming conpects, State the data flow diagramming c...

State the data flow diagramming conpects The approach to data flow diagramming is as follows: Create a data flow diagram for each of major outputs of system Work ba

Explain dial tone and ringing tone in strowger telephony, Explain Dial Tone...

Explain Dial Tone and Ringing Tone in strowger telephony. Dial Tone: it is used to indicate that the exchange is ready to recognize dialed digits by the subscriber. The subsc

Classification of digital computer, CLASSIFICATION  OF DIGITAL COMPUTER ...

CLASSIFICATION  OF DIGITAL COMPUTER Computer are classified under a number of factors.Some people classify them according to their processing speed.main memory,technology used

Name the widely used language processor development tool, Name the widely u...

Name the widely used Language Processor Development Tools ( LPDTs). Widely used Language processor development tools are: Lex - A Lexical Analyzer Generator Lex assi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd