Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

External communication interfaces, External interface is interface between ...

External interface is interface between I/O interface and peripheral devices. Interface can be characterised into 2 main categories: (a) parallel interface and (b) serial interface

What do you mean by software poll, Q. What do you mean by Software Poll? ...

Q. What do you mean by Software Poll? In this scheme on occurrence of an interrupt, processor jumps to an interrupt service program or routine whose job is to poll (roll call

Explain scripts and libraries introduction, Scripts A script within Rati...

Scripts A script within Rational Robot is a file that haves a sequence of SQABasic code. The extension of the file is always ".REC". Typically the script have an automated testc

Sound and complete, Dictator Dim wants to replace counting, in particular, ...

Dictator Dim wants to replace counting, in particular, counting the population of his land. To keep an accurate population count, Dictator Dim has instructed his secretary to add o

Architecture of artificial neural networks, Architecture of Artificial neur...

Architecture of Artificial neural networks: Presumably "Artificial Neural Networks" consist of a number of units that are mini calculation devices. But they take in real-value

Commutativity of connectives, Commutativity of Connectives : In this y...

Commutativity of Connectives : In this you will be aware of the fact that some arithmetic operators that have a property which it doesn't matter that way around you give the o

What is graceful degradation, What is graceful degradation? In multipro...

What is graceful degradation? In multiprocessor systems, failure of one processor will not halt the system, but only slow it down by sharing the work of failure system by other

Microprocessor MIPS Full Adder and Divider with overflow, I need to write a...

I need to write a 32 bit adder in MIPS without using the Add command and a divider as well.

Project, write a programme to simulate a train station to automate

write a programme to simulate a train station to automate

Interpolation search, Interpolation Search The next task is to implemen...

Interpolation Search The next task is to implement a variable size decrease-and-conquer solution to search. See Levitin [2007] pp 190 for a detailed description of the interpol

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd