Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Conversion of decimal number 10.625 into binary number, Conversion of decim...

Conversion of decimal number 10.625 into binary number ? Ans. There is integer part is 10 and fractional part is 0.625. Firstly convert the decimal number 10 in its equal bina

What are the general security issues, What are the General Security Issues ...

What are the General Security Issues Many issues exist when linking a computer system to the Internet or indeed to an external link via a network set up. There are numerous way

Explain different system calls for performing different task, Write down di...

Write down different system calls for performing different kinds of tasks. The major types of system calls are given as: Process Control: These kinds of system calls are

What do you mean by first fit, What do you mean by first fit? First fi...

What do you mean by first fit? First fit allocates the first hole that is big enough. Searching can either begin at the beginning of the set of holes or where the last first-f

What are the reasons for feedback in a control system, Question: a) Wha...

Question: a) What are the reasons for feedback in a control system? b) What are the roles of the configuration and fault managers in a real-time system? c) What are stimu

What are the parts of a deployment diagram, ? Nodes: A node shows any hardw...

? Nodes: A node shows any hardware component. The configuration of hardware is shown by attributes of nodes. ? Components: A component shows software. Every component straight

Evaluate total expense of algorithm, Q. Evaluate Total expense of algorithm...

Q. Evaluate Total expense of algorithm? Lastly, the total expense of algorithm is a product of the total number of processors required for computation and time complexity of th

Floating point format, consider the 8 bit floating point format including s...

consider the 8 bit floating point format including support for normalised nimbers and nonnumeric values.it included 3 bits for mantissa and 4 bitys for excess 7 exponent

Types of reasoning - first-order logic, Types of reasoning - First-order lo...

Types of reasoning - First-order logic: Atleast five types of reasoning can be acknowledged here. • Firstly, why and how do we will think for the killer usually left a silk

Explain scientific applications and image processing, Scientific Applicatio...

Scientific Applications/Image processing Major of concurrent processing applications from science and other academic disciplines, are mostly have based on numerical simulations

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd