Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Describe about pascaline, Q. Describe about Pascaline? Blaise Pascal ma...

Q. Describe about Pascaline? Blaise Pascal made very first attempt in the direction of automatic computing. He invented a device that comprised lots of gears and chains that us

What is the efficient data structure used in rdbms, In RDBMS, what is the e...

In RDBMS, what is the efficient data structure used in the internal storage representation? B+ tree. Because in B+ tree, all the data is kept only in leaf nodes, that makes sea

How atoms differ from the arrangement of atoms in a liquid, Q. How does the...

Q. How does the preparation of atoms in mainly solids differ from the arrangement of atoms in a liquid? Answer:- The arrangement of atoms in solids are diverse from those

Define structural classification, Structural Classification Flynn's cla...

Structural Classification Flynn's classification explains the behavioural idea and doesn't take concern into the computer's structure. Parallel computers can be categorized bas

What is a spanning tree, What is a spanning Tree? A spanning tree is a ...

What is a spanning Tree? A spanning tree is a tree associated with a network. All the nodes of the graph appear on the tree once. A minimum spanning tree is a spanning tree

Instruction set architecture - computer architecture, Instruction Set Archi...

Instruction Set Architecture:                             Instruction set architecture cycle-it is smallest unit of time in a processor. superscalar processor

What is structural hazard, What is structural hazard? Structural hazard...

What is structural hazard? Structural hazard is the situation when two instructions needs the use of a given hardware resource at the similar time. The most common case in whic

Describe about the forms-DBMS, Describe about the Forms- DBMS Forms ar...

Describe about the Forms- DBMS Forms are generally known as data entry screens as they are user interface that allows data in the tables to be viewed, edited or entered. Forms

What is single program multiple data, Q. What is Single Program Multiple Da...

Q. What is Single Program Multiple Data? A general style of writing data parallel programs for MIMD computers is SPMD (single program, multiple data) means all processors execu

Calculate the propagation delay for output, Problem: (a) Consider the ...

Problem: (a) Consider the following combinational circuit: (i) Calculate the propagation delay for each output. Assume each gate has a delay of 10 ns. (ii) The abo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd