Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Show system call for cloning, Show System call for cloning.  Standard f...

Show System call for cloning.  Standard form of Clone function is as follows: Int clone (Int (*FN) (), void *child stack, Int flag, intargs,); Parameter FN is Pointer fro

Detail explanation of cryptographic modules, Detail explanation of Cryptogr...

Detail explanation of Cryptographic modules Physical security of the cryptographic modules is also built in order to provide total security of the whole system and protect from

What is orientation- object-oriented technology, What is Orientation-  obj...

What is Orientation-  object-oriented technology There are many characteristics of object-oriented technology. A few of these characteristics have been discussed in cour

What is the different between index and subscript, Subscript refers to the ...

Subscript refers to the array of occurrence, whereas Index shown an occurrence of a table element. An index can only modified using perform, search & set. Require to have an index

Types of bus - computer architecture, Types of Bus: Synchronous Bus ...

Types of Bus: Synchronous Bus All devices gain timing information from a common clock line. Each of these intervals constitutes a bus cycle at the time duration w

Network properties, Network Properties There are many properties are as...

Network Properties There are many properties are associated with interconnection networks:- 1) Topology: It signify how the nodes a network are organised. A variety of top

Explain about registers, Q. Explain about Registers? A register is a gr...

Q. Explain about Registers? A register is a group of flip-flops that store binary information and gates that controls when and how information is transferred to register. An n-

State the term organizational structure, State the term Organizational Stru...

State the term Organizational Structure. A business organization might be structured in many various ways, depending on the environment in that this operates. There are alwa

Define colspan and rowspan, Q. Define Colspan and Rowspan? Now let's se...

Q. Define Colspan and Rowspan? Now let's see how to work with COLSPAN (Column Span) and ROWSPAN (Row Span). If we want cell containing Ajay in Figure to be extended to the next

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd