Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

A graph ''g'' with ''n'' nodes is bipartite, A graph 'G' with 'n' nodes is ...

A graph 'G' with 'n' nodes is bipartite if it have  no cycle of odd length.

Explain about interrupt servicing routines, Q. Explain about Interrupt serv...

Q. Explain about Interrupt servicing routines? First the situation is to be checked as to why the interrupt has happened. That includes not only device but also why the device

Reprography of information distribution, Reprography In order to dissem...

Reprography In order to disseminate information widely some method of reprography is invariably used. Reprography is the science and practice of copying documents by photograph

Illustrate the uses of assembly language, Q. Illustrate the Uses of Assembl...

Q. Illustrate the Uses of Assembly Language? Uses of Assembly Language Assembly language is used mainly for writing short, efficient, specific interfacing modules/ subrou

What do you mean by decoders, Q. What do you mean by Decoders? Decoder ...

Q. What do you mean by Decoders? Decoder transforms one kind of coded information to other form. A decoder has n inputs and one enable line (sort of selection line) and 2 n ou

Illustrate the ftp commands, Q. Illustrate the FTP commands? FTP includ...

Q. Illustrate the FTP commands? FTP includes many commands however only few are used to retrieve a file. A user is required to understand the three basic commands to connect to

Future of hyper threading, Current Pentium 4 based MPUs use Hyper-threading...

Current Pentium 4 based MPUs use Hyper-threading, but the next-generation cores, Woodcrest and Merom, Conroe will not. While some have alleged that this is because Hyper-threading

What is serial mouse, Q. What is Serial Mouse? Mice that use standard s...

Q. What is Serial Mouse? Mice that use standard serial port are known as 'serial'. Because Serial ports 1 and 4 (COM1, COM4 under DOS, /dev/ttyS0 and /dev/ttyS3 under Unix/GNU-

Basic tradeoff of concerns for instruction set design, Q. Basic Tradeoff of...

Q. Basic Tradeoff of concerns for instruction set design? Basic Tradeoff: Smaller instruction (less space) vs. desire for more powerful instruction repertoire. Generally p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd