Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

A sorting algorithm is stable, A sorting algorithm is stable if  Preser...

A sorting algorithm is stable if  Preserves the original order of records with equivalent keys.

Multiple instruction and multiple data stream (mimd), Multiple Instruction ...

Multiple Instruction and Multiple Data stream (MIMD) In this association, multiple control units and multiple processing elements are prepared as in MISD. But the discrepancy i

Why cmos circuits are extensively used for On-chip computers, CMOS circuits...

CMOS circuits are extensively used for ON-chip computers mainly because of their extremely ? Ans. Since CMOS circuits have large packing density, so these are extensively use

Explain the term- macro, Explain the term- macro? A term macro is a set...

Explain the term- macro? A term macro is a set of instructions, which can be executed repeatedly. It is useful for automating certain routine tasks like printing reports etc. T

Artificial intelligence agents, Artificial Intelligence Agents: We int...

Artificial Intelligence Agents: We introduced what we'll be conversation about in Artificial Intelligence and why those things are necessary. This discussion is of course abou

Quick sort exhibit its worst-case behaviour, In which input data does the a...

In which input data does the algorithm quick sort exhibit its worst-case Behaviour? The Quick Sort method exhibits its worst-case behavior when the input data is " Already Comp

Describe the working of components of i-way infrastructure, Describe the wo...

Describe the working of components of I-way Infrastructure. Working of I-way Infrastructure components: a. Consumer access equipment shows a critical category, it is the abs

What is model view controller (mvc), Model-View-Controller (MVC) is a desig...

Model-View-Controller (MVC) is a design pattern in which "the user input, the modelling of the external world and the visual feedback to the user are explicitly splitted and handle

What is the meaning of aliasing, a. What is the meaning of aliasing? What a...

a. What is the meaning of aliasing? What are its drawbacks? Describe a method to remove aliasing, using post filtering. b. How can you copy a Pixmap from one place to another

Handling a page in memory - computer architecture, Handling a Page: ...

Handling a Page: Typical page size today are 4 kb to 16 kb ,having tendency to use even larger page sized Organization that reduce the page fault rate are striking (comp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd