Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Computer networks, distributed & centralized system in computer network

distributed & centralized system in computer network

With what symbolic names can be associated, Symbolic names can be associate...

Symbolic names can be associated with? Ans. With data or instruction symbolic names associated.

Support for high-level language, With the increasing use of more and higher...

With the increasing use of more and higher level languages manufacturers had offered more powerful instructions to support them. It was claimed that a stronger instruction set will

Computer Architecture, As an advocate of CISC architecture to RISC architec...

As an advocate of CISC architecture to RISC architecture, what are the merits and demerits of CISC to RISC architecture

Differentiate between string constants & character constants, Computer Conc...

Computer Concepts & C Programming 1. Write a program to read four floating point numbers and find their sum and average. 2. What is the difference between string constants a

Approach to reasoning - first-order logic, Approach to reasoning - first-or...

Approach to reasoning - first-order logic: The formal approach to reasoning has bigger return and disadvantages. In generally we notice, if a computer program has proved somet

Workday versus oracle, Workday has set the stage to revolutionize the way c...

Workday has set the stage to revolutionize the way companies manage and facilitatevarious aspects of their business operationsby utilizing cutting-edge cloud-based technologies in

Hypothetical reliable data transfer protocol, the c code for hypothetical r...

the c code for hypothetical reliable data transfer protocol

Show the features of hyper-threading, Q. Show the Features of Hyper-threadi...

Q. Show the Features of Hyper-threading? The significant characteristics of hyper threading are: i) Improved response time and reaction, as well as increased number of users

Synchronous sequential circuits, Q. Differentiate the Multiplexer and Demul...

Q. Differentiate the Multiplexer and Demultiplexer with respect to their concept, block diagram and circuit. Q. What is the difference between Synchronous sequential circuits an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd