Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

I2c protocol bus , I²C TECHNOLOGIES The I2C protocol bus is two bi-dire...

I²C TECHNOLOGIES The I2C protocol bus is two bi-directional wires, serial data (SDA) and serial clock (SCL), that transmit information between the devices connected to the bus.

How to correctly apply the graphics patches in matlab, Open a LOCAL MACHINE...

Open a LOCAL MACHINE window and type: xhost +ashland # Add the following code sequence just before the plot command that was giving you problems: figure; set(gcf,'renderer','zbuffe

Same reg variable in an always block, What value is inferred when multiple ...

What value is inferred when multiple procedural assignments made to the same reg variable in an always block? When  there  are  multiple  nonblocking  assignments  made  to  th

What is guard bits, What is guard bits? Guard bits are extra bits which...

What is guard bits? Guard bits are extra bits which are produced while the intermediate steps to yield maximum accuracy in the final results.

Select-options and parameters statement, The fields specified by select-opt...

The fields specified by select-options and parameters statement cannot be grouped together in the selection screen.  No, It can be grouped together in the selection screen

Difference between a window and a frame?, The Frame class extends Window to...

The Frame class extends Window to describe a main application window that can have a menu bar. A window can be modal.

Advantages and disadvantages of mealy - moore state machine, What are the a...

What are the advantages and disadvantages of Mealy and Moore state machine? Advantage and Disadvantage of Mealy and Moore state machine: In Mealy as the output variable is a

What are the advantages of public key cryptography, What are the advantages...

What are the advantages of Public Key Cryptography? Advantages of Public Key Cryptography are illustrated in below: a) Increased convenience and security and b) Electro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd