Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Hazard (computer architecture), Hazard (computer architecture): In the...

Hazard (computer architecture): In the computer architecture, a hazard is a possible problem that can occurs in a pipelined processor. It concern to the possibility of erroneo

Database system, What are the three data anomalise that are likely to occur...

What are the three data anomalise that are likely to occur as a result of data redundancy?

Illustrate the execute cycle, Q. Illustrate the Execute Cycle? The fetc...

Q. Illustrate the Execute Cycle? The fetch and indirect cycles include a small, fixed sequence of micro-operations. Every one of these cycles has fixed sequence of micro-operat

Explain the probability of availability of free lines, How does one arrive ...

How does one arrive at the probability of availability of free lines during the busy hour? One can arrive at the possibility of free lines throughout busy hour using the delay

Define polling, Define Polling. A Polling process is used to recognize...

Define Polling. A Polling process is used to recognize the highest priority source by software means. In this process there is one common branch address for all interrupts.

Differentiate between time sharing & batch operating system, Differentiate ...

Differentiate between Batch Operating System and Time Sharing Operating System? Batch operating systems : A batch is a sequence of jobs. Such batch is submitted to batch proce

Explain the race around condition, Explain the Race Around Condition? C...

Explain the Race Around Condition? Consider the inputs of the JK flipflop j=1 and k=1 and Q=0 when a clock pulse of width tp is applied the output will change from 0 to 1 after

Name the processes of oom, Name the processes of OOM In OOM the modelli...

Name the processes of OOM In OOM the modelling passes through the given processes: System Analysis System Design Object Design, and Final Implementation.

By which digits are represented, In a DTMF phone, digits are represented by...

In a DTMF phone, digits are represented by: (A)  Orthogonal frequencies. (B)  Orthogonal Phases. (C)  Orthogonal codes. (D)  Orthogonal pulses. Ans: Di

Discuss different mode of centralized stored program control, Explain SPC. ...

Explain SPC. Also discuss the different modes of Centralized SPC In stored program control systems, set of instructions or a program to the computer is stored into its memory a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd