Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Sorting circuit along with odd-even merging circuit, Q. Sorting Circuit alo...

Q. Sorting Circuit along with Odd-Even Merging Circuit? The merge sort algorithm needs two circuits which imply that one circuit for merging and another circuit for sorting the

First-order inference rules, First-Order Inference Rules: Here now we ...

First-Order Inference Rules: Here now we have a clear definition of a first-order model is that we can define soundness for first-order inference rules in the same way such we

What is the use of urgent pointer in tcp segment, What is the use of urgent...

What is the use of urgent pointer in TCP segment? For accommodation out of band signaling, TCP permits the sender to identify data as urgent, implies that the receiving program

Program level-parallelism based on granularity size, Program Level : It ...

Program Level : It is the next level consisting of independent programs for parallelism. Coarse Granularity  size is used at this level containing ten thousands of instructions.

Define the term web service with example, Define the term web service with ...

Define the term web service with example. A web service is an application that operate over a network-typically, over the Internet. Most typically, a web service is an API that

Find the maximum and minimum number-binary, What is the maximum and minimum...

What is the maximum and minimum number in the range of a 7-digit number for each of the following cases? Express all numerical answers in both the original base and its decimal (ba

Explain the term overlays, Explain the term Overlays. An overlay is an ...

Explain the term Overlays. An overlay is an element of program that has the same load origin as several other part of the program. These are used for reduce the main memory req

Implement the logic of the following gates, Q. Develop a menu driven prog...

Q. Develop a menu driven program to implement the logic of the following gates. I. AND Gate II. OR Gate III. NOT Gate IV. Exit The user has option to give n number

Define logical data as operand data type, Q. Define Logical data as operand...

Q. Define Logical data as operand data type? Every word or byte is treated like a single unit of data. Whenever an n-bit data unit is considered as comprising n 1-bit items of

Identify the process of entering data into a ROM, The process of entering d...

The process of entering data into a ROM is called ? Ans. The process of entering data in ROM is termed as programming the ROM.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd