Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define the don''t care states - simplifying k maps, Define the Don't Care S...

Define the Don't Care States - Simplifying K Maps? The Truth table specifications for a logic function may not to include all possible combinations of the input binary digits for

What is FIFO, What is FIFO? FIFO is used as buffering element or queui...

What is FIFO? FIFO is used as buffering element or queuing element into the system that is by common sense, is needed only while you slow at reading than the write operation.

Show the Features of parallel virtual machine, Q. Show the Features of para...

Q. Show the Features of parallel virtual machine? Easy to install; Easy to configure; Multiple users each can use PVM concurrently; Multiple applications fro

Explain how presentation layer helps in establishing, Explain how presentat...

Explain how presentation layer helps in establishing and processing data in End to End layers. The idea of the presentation layer is to stand for information to the communicati

Array processing, Array Processing We have seen that for performing vec...

Array Processing We have seen that for performing vector operations, the pipelining concept has been taken. There is another method for vector operations. If we have an array o

Static memories - computer architecture, Static memories Circuits c...

Static memories Circuits capable of receiving their state as long as power is applied volatile Static RAM(SRAM)

Describe the interpretation features of vba, VBA is licensed to Microsoft a...

VBA is licensed to Microsoft and this compatible with and only Microsoft products. Code written is compiled by an intermediate language known as P-code and this is stored in hostin

Compare electromechanical and electronic switching system, Compare electrom...

Compare electromechanical switching system with electronic switching system. Comparison of electromechanical switching system with electronic switching systemgiven below:

How does multiplexer know which line to select, How does multiplexer know w...

How does multiplexer know which line to select? This is managed by select lines. The select lines provide communication among different components of a computer. Now let's see

What is data in computers, Q. What is data in computers? In modern digi...

Q. What is data in computers? In modern digital computers data is signified in binary form by employing two symbols 0 and 1. These are known as binary digits or bits however da

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd