Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What are the types of smart cards used in e-commerce, What are the types of...

What are the types of Smart cards used in e-commerce? Generally there are 2 types of smart cards. Memory smart cards, which can be sighted as minuscule removable read/ write

Set screen and leave screen, What happens if only one of the commands SET S...

What happens if only one of the commands SET SCREEN and LEAVE SCREEN is used without using the other? If we use SET SCREEN without LEAVE SCREEN, the program ends processing for

What is load-through or early restart, What is load-through or early restar...

What is load-through or early restart? When a read miss happens for a system with cache the needed word may be sent to the processor as soon as it is read from the main memory

.., 1mechanism of artificial satellite

1mechanism of artificial satellite

Multiple valued logics, Multiple valued logics: Multiple valued logics...

Multiple valued logics: Multiple valued logics, where altered types of truth value such as "unknown" are may be allowed. These have some of the particular advantages of fuzzy

Direct addressing and immediate addressing mode , Direct Addressing and  I...

Direct Addressing and  Immediate Addressing mode - computer architecture:  Immediate Addressing: It is the simplest form of addressing. Here, the operand is itself given

Difference between commit-work and rollback-work tasks, What is the differe...

What is the difference between Commit-work and Rollback-Work tasks? Commit-Work statement "performs" many functions relevant to synchronized execution of tasks.  Rollback-work

Control of program, Example:                         CMP    AX,BX    ;...

Example:                         CMP    AX,BX    ; compare instruction: sets flags JE        THERE    ; if equal then skip the ADD instruction  ADD  AX, 02    ; add 02

Data analysis and results in e-commerce, There were 50 respondents to our s...

There were 50 respondents to our survey. The first component of the data examined here focuses on student's preference (ecommerce or traditional commerce). The Second compone

Formal analysis of visual elements, Formal Analysis: The second step o...

Formal Analysis: The second step of the art critiquing process often begins with an analysis of the artworks formal elements and how they are the organised. The formal elem

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd