Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Threads model - parallel programming model, In this model a one process can...

In this model a one process can have multiple, concurrent implementations paths. The major programs are scheduled to run by the native operating system. It loads and obtains all th

Loop level-levels of parallel processing, Loop Level At this level, rep...

Loop Level At this level, repeated loop iterations are the applicants for parallel execution. However, data dependencies among subsequent iterations may limit parallel executio

Explain the linux from scratch system, Problem 1 (a) Explain the RAID ...

Problem 1 (a) Explain the RAID system and explain all possible configurations. (b) Summarize design goals, features and specifications of the Linux ext2 file system. (c

What are the digital certificates of hardware computations, What are the Di...

What are the Digital certificates of hardware computations Digital certificates are highly dependent on hardware computations, it is essential that mechanisms are evolved to i

What is machine.config, What is Machine.config?  Machine configuration ...

What is Machine.config?  Machine configuration file: The machine. config file contains settings that apply to the whole computer.  The machine.config, which can be found in the

Explain height of a tree, Height of a tree The length of the longest pa...

Height of a tree The length of the longest path from root to any node is called as the height of the tree.

Multi-layer artificial neural networks, Multi-Layer Artificial Neural Netwo...

Multi-Layer Artificial Neural Networks - Artificial intelligence: Now we can look at more sophisticated ANNs, which are known multi-layer artificial neural networks because the

Dbms, documentation for dbms report

documentation for dbms report

Terms in propositional model, Terms in Propositional model: There in f...

Terms in Propositional model: There in first-order logic allows us to talking about properties of objects that the first job for our model (Δ, Θ) is to assign a meaning to the

Pipeline, where can I find detailed explanation of 6 stage and 7 stage pipe...

where can I find detailed explanation of 6 stage and 7 stage pipeline ??

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd