Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Determine the simplified sop boolean expression, The Karnaugh map for a SOP...

The Karnaugh map for a SOP function is given below in figure. Determine the simplified SOP Boolean expression. Ans. F= B'C' + A'C'D + B'D'

Integrating virtual memory, Integrating Virtual Memory, TLBs, and Caches - ...

Integrating Virtual Memory, TLBs, and Caches - computer architecture:   There are 3 types of misses: 1. a cache miss 2. TLB miss 3. a page fault 2 techniqu

And-elimination-introduction rule - artificial intelligence, And-Eliminatio...

And-Elimination-Introduction rule - Artificial intelligence: And-Elimination In English, this says that "if you know that many things are all true, then you know that any

Feature Extraction and clustering, Hi, I have a CSV file that has numbers ...

Hi, I have a CSV file that has numbers data set. The data set contains images of handwritten digits. Recognizing handwritten digits is already a mature technology By using R code

Convert the decimal number into its equivalent binary number, Write a progr...

Write a program to convert the given Decimal number into its equivalent Binary number.

Explain indirect cycle in control unit, Q. Explain Indirect Cycle in contro...

Q. Explain Indirect Cycle in control unit? Once an instruction is fetched the subsequent step is to fetch the operands. The instruction may have indirect and direct addressing

Why do we need dma, Why do we need DMA? DMA is used to transfer the blo...

Why do we need DMA? DMA is used to transfer the block of data directly among an external device and the main memory without the continuous intervention by the processor.

How to clear a datagrid on a button click, How to clear a datagrid on a but...

How to clear a datagrid on a button click? You require to Clear the DataSource of the dataGrid. So try this: dataSet1.Clear(); dataGrid1.DataSource = dataSet1.TableNam

Dynamic memory allocation function, Name the dynamic memory allocation func...

Name the dynamic memory allocation function? Three dynamic memory allocation functions are: a) malloc, b) calloc and c) free.

How to execute an instruction, Execution: Now instruction is ready for exec...

Execution: Now instruction is ready for execution. A different opcode will need different sequence of steps for execution. Hence let's discuss a few illustrations of execution of s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd