Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain about the term- video conferencing, Video Conferencing Video co...

Video Conferencing Video conferencing continues to grow in popularity. Why is this? Some reasons are listed below: - Communication links are now much faster thus sound quali

Discuss about the electronic computer, Discuss about the Electronic compute...

Discuss about the Electronic computer The first general function programmable electronic computer was the Electronic Numerical Integrator and Computer (ENIAC), built by John V

Explain the number unobtainable tone in strowger telephony, Explain the num...

Explain the number unobtainable tone in strowger telephony with waveforms and the timings. In the following figure illustrates the number unobtainable tone that is continuous

Define the firewall design policy, Define the Firewall Design Policy ...

Define the Firewall Design Policy A lower-level policy that describes how the firewall will handle prevention of access and filtering of services as defined in the above net

Difference between panel and group box classes, Difference between Panel an...

Difference between Panel and Group Box classes? Panel & Group box both can used as container for other controls like radio buttons & check box. The dissimilarity in panel & gro

What is compound statement, What is compound statement If we wish to ha...

What is compound statement If we wish to have more than one statement following the if or the else, they should be grouped together between curly brackets. Such a grouping is c

How are the function code handles in flow logic, How are the function code ...

How are the function code handles in Flow Logic? When the User selects a function in a transaction, the system copies the function code into a           specially   designated

C programming, There is a pebble merchant. He sells the pebbles, that are u...

There is a pebble merchant. He sells the pebbles, that are used for shining the floor. His main duty is to take the length of the room’s sides. But he sometimes mistakes doing that

Explain about hyper-threading, Q. Explain about Hyper-threading? Non th...

Q. Explain about Hyper-threading? Non threaded program instructions are executed in a single order at a time until the program completion. Presume a program have four tasks nam

What are the advantages of store program control, What are the Advantages o...

What are the Advantages of store program control (I) Easy to maintain (II) Easy to control (III) Wide range of services can be provided to customers (IV) Flexible

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd