Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is a manifest, What is a Manifest?  An assembly manifest contains...

What is a Manifest?  An assembly manifest contains all the metadata required to specify the assembly's version requirements and security identity, and all metadata required to

Workday versus oracle, Workday has set the stage to revolutionize the way c...

Workday has set the stage to revolutionize the way companies manage and facilitatevarious aspects of their business operationsby utilizing cutting-edge cloud-based technologies in

Detrmine pure paging, Which is not a key piece of information, stored in si...

Which is not a key piece of information, stored in single page table entry, assuming pure paging and virtual memory Ans. A reference for the disk block which stores the page is

Illustrate the advantages of encapsulation, Advantages of Encapsulation ...

Advantages of Encapsulation You can also delay the resolution of the details until after the design.  You can keep your code modular.

Advantages and disadvantages of e-commerce, E-commerce is one of the most s...

E-commerce is one of the most significant aspects of the internet. Having emerged recently and growing at a steady state, it becomes essential to look at the advantages and disadva

C++, a program to find the area under the curve y = f(x) between x = a and ...

a program to find the area under the curve y = f(x) between x = a and x = b, integrate y = f(x) between the limits of a and b. The area under a curve between two points can be foun

Smugglers problem, #question.Smugglers are becoming very smart day by day. ...

#question.Smugglers are becoming very smart day by day. Now they have developed a new technique of sending their messages from one smuggler to another. In their new technology, the

4 bit comparator, how to breadboARD THE 4 BIT COMPARATOR

how to breadboARD THE 4 BIT COMPARATOR

Design a bcd to seven segment decoder, Design a BCD to seven segment decode...

Design a BCD to seven segment decoder that accepts a decimal digit in BCS and generates the appropriate output for segments in display indicator. Ans: BCD-TO-seven-Segment

What are the main aspects available in all word processors, What are the Ma...

What are the Main aspects available in all word processors -  Ability to set page size and page orientation -  Ability to change font size and font style (for example Arial,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd