Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Floating point format, consider the 8 bit floating point format including s...

consider the 8 bit floating point format including support for normalised nimbers and nonnumeric values.it included 3 bits for mantissa and 4 bitys for excess 7 exponent

Measure of speed in page or line printer, Q. Measure of speed in Page or li...

Q. Measure of speed in Page or line Printer? Measure of speed relies on whether the printer is a Page Printer or Line. Printer: Let's understand these:  Line Printer:

Explain the term- tracker ball and braille printers, Explain the term- Trac...

Explain the term- Tracker ball and Braille printers Tracker ball Easier to use than a mouse if people have problems using their arms and hands or if they have a coordinati

Illustrate the uses of assembly language, Q. Illustrate the Uses of Assembl...

Q. Illustrate the Uses of Assembly Language? Uses of Assembly Language Assembly language is used mainly for writing short, efficient, specific interfacing modules/ subrou

Explain about cluster computing, The idea of clustering is defined as use o...

The idea of clustering is defined as use of multiple computers naturally multiple storage devices, PCs or UNIX workstations and their interconnections to make what emerges to users

What is instruction register, Q. What is Instruction Register? Instruct...

Q. What is Instruction Register? Instruction Register (IR): Here instructions are loaded before execution. Comments on figure above are as below: All representations are

Detail explanation of cryptographic modules, Detail explanation of Cryptogr...

Detail explanation of Cryptographic modules Physical security of the cryptographic modules is also built in order to provide total security of the whole system and protect from

Shm, composition of two shm in right angles to each other to havingg time p...

composition of two shm in right angles to each other to havingg time period in the ratio 1:2

State a simple pull transaction, a. Explain the future of mobile commerce i...

a. Explain the future of mobile commerce in world? b. 'Push and Pull' are two ways of transferring information to and from a phone, through WAP. Now, with the help of diagram, s

A full binary tree with ''n'' non-leaf nodes, A full binary tree with 'n' n...

A full binary tree with 'n' non-leaf nodes have  2n+l nodes.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd