Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Add references dialog box, What is the difference among "using System.Data;...

What is the difference among "using System.Data;" and directly adding the reference from "Add References Dialog Box"?  When you compile a program using command line, you add th

Principle of locality, Principle of locality: Temporal  base locali...

Principle of locality: Temporal  base locality (locality in time):- If an item is referenced then it will tend to be referenced again soon. Spatial locality (local

What is a accepting computation history, What is a accepting computation hi...

What is a accepting computation history?  An accepting computation history is explained as , Let M be a Turing machine and w be a input string,  for M on w is a sequence of con

What is the maximum number of fragments, What is the maximum number of frag...

What is the maximum number of fragments that can result from a single IP Datagram? Explain. To fragment a datagram for transmission across a network, a router utilizes the netw

Define program counter, Define Program Counter(PC) The Program Counter ...

Define Program Counter(PC) The Program Counter holds the address of the next instruction to be read from memory after the current instruction is implemented.

Define ufd and mfd, Define UFD and MFD.   In the two-level directory st...

Define UFD and MFD.   In the two-level directory structure, every user has own user file directory (UFD). Every UFD has a same structure, but lists only the files of a single u

Define the term ''turn-around'', The "turn-around" time of a user job is th...

The "turn-around" time of a user job is the? Ans. Total time taken to execute the job is called "turn around" time.

What is multiple interrupt lines, Q. What is Multiple Interrupt Lines? ...

Q. What is Multiple Interrupt Lines? Multiple Interrupt Lines: Simplest solution to problems above is to provide multiple interrupt lines that will result in immediate recognit

Describe the three mapping techniques, Describe the three mapping technique...

Describe the three mapping techniques used in cache memories with suitable Example. The cache memory is a fast memory that is inserted among the larger slower main memory and t

What is the gray equivalent of decimal number 25, What is the Gray equivale...

What is the Gray equivalent of  (25) 10 Ans. Gray equivalent of (25) 10 : The Decimal number 25 has binary equivalent as (00100101) 2 The left most bits (MSB) into gray

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd