Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Observing the existing system first hand, Observing the existing system fir...

Observing the existing system first hand This involves watching personnel using the existing system to find out precisely how it works. There are a number of disadvantages as

Commutativity of connectives, Commutativity of Connectives : In this y...

Commutativity of Connectives : In this you will be aware of the fact that some arithmetic operators that have a property which it doesn't matter that way around you give the o

Explain the for loop, Explain The for loop The for loop is frequently ...

Explain The for loop The for loop is frequently used, usually where the loop will be traversed a fixed number of times. It is very flexible, and novice programmers should take

Floating point format, consider the 8 bit floating point format including s...

consider the 8 bit floating point format including support for normalised nimbers and nonnumeric values.it included 3 bits for mantissa and 4 bitys for excess 7 exponent

Show the internet protocols, A communication protocol is an agreement which...

A communication protocol is an agreement which specifies a common language two computers use to exchange messages. For instance, a protocol specifies exact format and meaning of ev

What is said to be side effect, What is said to be side effect? When a ...

What is said to be side effect? When a location other than one explicitly named in an instruction as a destination operand is affected, the instruction is said to have a side e

#title., REPRESENTATION OF POYNOMIAL OF 2 OR MORE VARIABLES USING ARRAY

REPRESENTATION OF POYNOMIAL OF 2 OR MORE VARIABLES USING ARRAY

Send a report to the printer, How to send a report to the printer instead o...

How to send a report to the printer instead of displaying it on the screen? We can send a report to the printer instead of displaying it on the screen.  To do this, use the key

What is difference between cgi and java, CGI and JAVA are fundamentally dis...

CGI and JAVA are fundamentally dissimilar, and for most applications are NOT interchangable. CGI is a protocol for running programs on a WWW server. Whilst JAVA can also be us

What is assembly condition codes, Condition codes are the list of possible ...

Condition codes are the list of possible conditions that can be tested through conditional instructions. Typical conditional instructions have: conditional branches, conditional ju

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd