Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Appropriate name for the superclass, Suppose that your team is then asked t...

Suppose that your team is then asked to expand the system. The publisher now wishes to make other computer science publications. As a team member, you are asked to make a class tha

What is inheritance, What is Inheritance? Inheritance is the method of ...

What is Inheritance? Inheritance is the method of deriving a feature of super class into sub class. Every sub class inherits the attributes, operations and association of its s

Calculate traffic lost in a particular exchange, In a particular exchange d...

In a particular exchange during busy hour 1200 calls were offered to a group of trunks, during this time 6 calls were lost. The average call duration being 3 minutes Calculate Tr

Reprographic technologies, Reprography: Reprography, as a term, has ga...

Reprography: Reprography, as a term, has gained international recognition in 1963. It includes "photocopying , microcopying, duplicating and in-plant printing and is character

What is command prompt interface, Q. What is Command Prompt Interface? ...

Q. What is Command Prompt Interface? Operating System gives a text based interface called command prompt.  With the help of command prompt commands can be issued to perform fil

show bank type , Describe an abstract class 'Bank' having abstract methods...

Describe an abstract class 'Bank' having abstract methods as 'CreateAccount' 'depositAmount' & 'withDrawAmount'.Add method definitions for 'CalculateInterest' and 'SetInterest' as

Documentation introduction, Documentation is done to give others with infor...

Documentation is done to give others with information and ease maintenance. The best documentation is done in the headers (function and scripts) and directly in the code. Any usefu

Explain fundamental models of inter process communication, Explain the two ...

Explain the two fundamental models of inter process communication. Two kinds of message passing system are given as: (a) Direct Communication : Along with direct communicat

The three main elements of ldb, The three main elements of LDB are:- St...

The three main elements of LDB are:- Structure Selections and Database Program.

Define password methods and biometric systems, Define the password methods ...

Define the password methods and Biometric systems for implementing client server network security. In cyberspace, buyers and sellers cannot notice each other. Also within video

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd