Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Determine the example of timescale, Determine the Example of timescale ...

Determine the Example of timescale 'timescale 10ns / 1ps Indicates delays are in 10 nanosecond units with 3 decimal points of precision (1 ps is 1/1000ns which is .001 ns).

Calculate traffic lost in a particular exchange, In a particular exchange d...

In a particular exchange during busy hour 1200 calls were offered to a group of trunks, during this time 6 calls were lost. The average call duration being 3 minutes Calculate Tr

Conversion of bcd number to binary using a procedure, Q. Conversion of BCD ...

Q. Conversion of BCD number to binary using a procedure? Conversion of BCD number to binary using a procedure. Algorithm for conversion procedure: Take a packed BCD digit

Illustrate what is universal law of universal gravitation, Q. Illustrate wh...

Q. Illustrate what is the universal law of universal gravitation? Answer:- Declaration that any particle of matter in the universe attracts any other with a force varying

What are different queues used, 1.Local queue -is a actual queue 2.Clus...

1.Local queue -is a actual queue 2.Cluster queue -is a local queue that is called as throughout a cluster of queue managers 3. Remote queue -structure explaining a queue

Explain the term electronic data interchange (edi), Explain the term Electr...

Explain the term Electronic Data Interchange (EDI). Electronic Data Interchange (EDI) may be generally easy to understand as the replacement of paper-based purchase orders alon

How to develop an object model, How to develop an object model To deve...

How to develop an object model To develop an object model firstly identify classes and their associations, as they affect overall problem structure and approach. Then prepare

What is home shopping, Home Shopping TV broadcast of goods for purchase...

Home Shopping TV broadcast of goods for purchase, sent directly to a viewer . This online shopping is available because of e-commerce.

Dynamic programming, Given: • A sequence of n arrival times t0, t1, ..., ...

Given: • A sequence of n arrival times t0, t1, ..., tn-1, • a library of mlogically equivalent gates {(d0, c0), (d1, c1), ..., (dm-1,cm-1)} where d is delay and c is cost • a

What is parsing in grammatical structure, What is Parsing? Parsing: ...

What is Parsing? Parsing: It is the process of analyzing a text, made of an order of tokens, to find out its grammatical structure regarding a given formal grammar. Parsing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd