Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Mathlab , Windy Grid World This assignment is to use Reinforcement Learni...

Windy Grid World This assignment is to use Reinforcement Learning to solve the following "Windy Grid World" problem illustrated in the above picture. Each cell in the image is a

Compare pre-emptive and non-preemptive scheduling policies, Compare pre-emp...

Compare pre-emptive and non-preemptive scheduling policies. We preempt the currently executing process in preemptive scheduling. In non-preemptive we permit the current process

Dbms, documentation for dbms report

documentation for dbms report

Why digital computers use complemented subtraction method, The chief reason...

The chief reason why digital computers use complemented subtraction is that it ? Ans. By using complemented subtraction method negative numbers can easily be subtracted.

Comparison between centralized and distributed spc, Explain the principles ...

Explain the principles of operation of centralized SPC and distributed SPC and compare their performance. All the control equipment is replaced with a single processor that mus

Show the decimal representation in computers, Binary number system is most ...

Binary number system is most common for computer due to two stable states of its components. However unfortunately this isn't a very natural system for us as we deal with decimal n

What is synchronous reset, What is Synchronous reset? Synchronous reset...

What is Synchronous reset? Synchronous reset: Synchronous reset logic will synthesize to smaller flip-flops, mainly when the reset is gated along with the logic generating t

What search method would be most appropriate and why, (a) Describe fully in...

(a) Describe fully in your own words the following terms: (i) Turing Test (ii) Agent (iii) Utility-based agent (b) A Mars rover has to leave the lander, collect rock sample

Safety argument for good design, So far we have considered the problems of ...

So far we have considered the problems of poor ID in terms of the loss of productivity and efficiency to business. There is another important aspect to consider: the issue of safet

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd