Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Linux, Explain about unix file system architecture

Explain about unix file system architecture

Which electro mechanical switch had fewer moving parts, The             el...

The             electro mechanical switch (developed in 1938) had fewer moving parts than earlier switches. (A)  No. 1ESS                                 (B)  Strowger (

What do you mean by resolution, Q. What do you mean by Resolution? Reso...

Q. What do you mean by Resolution? Resolution is parameter which defines possible sharpness or clarity of a video image.  Resolution is defined as number of pixels which make u

Define print resolution of printers, Q. Define Print Resolution of printers...

Q. Define Print Resolution of printers? Print Resolution is the detail which a printer can give considered by how many dots a printer can put in each inch of paper.  So the uni

Example of input a single digit, Q. Example of Input a Single Digit? I...

Q. Example of Input a Single Digit? Input a Single Digit for example (0,1, 2, 3, 4, 5, 6, 7, 8, 9)  CODE SEGMENT   ... ; Read a single digit in BL register with ech

Incorporate exception handling, Assignment (to be published later) will req...

Assignment (to be published later) will require you to extend the menu-driven application developed in Assignment 2B, to incorporate the recording details of the doctors who will b

Optimal number of disks , John Lindsay sells disks that have 25 software pa...

John Lindsay sells disks that have 25 software packages that show a variety of financial functions, including net present value, internal rate of return, and other financial progra

different versions of microsoft access to open the database, What format s...

What format should my database be saved in to allow different versions of Microsoft Access to open the database? Ans) MS Access is not backwards compatible. To share tables amon

Networking, compare 2g , 3g , and 4g also with advantage of 3g and 4g.

compare 2g , 3g , and 4g also with advantage of 3g and 4g.

3D rotation, Magnify a triangle with vertices A = (0,0), B = (3,3) and C = ...

Magnify a triangle with vertices A = (0,0), B = (3,3) and C = (6,4) to twice its size in such a way that A remains in its original position.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd