Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Network, Give an intuitive explanation of why the maximum throughput, for s...

Give an intuitive explanation of why the maximum throughput, for small beta, is approximately the same for CSMA slotted Aloha and FCFS splitting with CSMA. Show the optimal expecte

Which device changes from serial data to parallel data, Which device change...

Which device changes from serial data to parallel data ? Ans. Demultiplexer is the device that changes from serial data to parallel data. Demultiplexer takes data in from on

Ellipse follows the perimeter of the window, A) Execute a program where an ...

A) Execute a program where an ellipse follows the perimeter of the window. B)  Execute a program that can draw graphs, possibly following your plan from last week. Have it graph

What is analysis iteration, Analysis Iteration   To understand any prob...

Analysis Iteration   To understand any problem completely you have to repeat task which implies that analysis requires repetition. First, just get overview of problem, make a r

What is a pointer, What is a pointer? The register or memory location t...

What is a pointer? The register or memory location that having the address of an operand is known as a pointer.

How does vb.net achieve polymorphism, How does VB.NET/C# achieve polymorphi...

How does VB.NET/C# achieve polymorphism?  VB.Net / C# provide polymorphism through the following mechanisms: 1. Inheritance - base class gives overridable methods which ar

Define interrupts and instruction cycle, Q. Define Interrupts and Instructi...

Q. Define Interrupts and Instruction Cycle? Let's precise the interrupt process, on the event of an interrupt, an interrupt request (in form of a signal) is concerned to CPU. T

Explain the language processors, Name the language processors are? Asse...

Name the language processors are? Assembler, Compiler and Interpreter are the language processors.

State about the mainframe computer, Mainframe computer Mainframe comput...

Mainframe computer Mainframe computers are very large, often can fill an entire room. They can store a large amount of information, can execute many tasks at the same time, can

What is supply chain management, What is Supply Chain Management? Sup...

What is Supply Chain Management? Supply Chain Management: Supply Chain Management involves developing the performance of an organization’s supply chain from its supplier

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd