Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain the role of a bus arbiter in a multiprocessor, Explain the role of ...

Explain the role of a bus arbiter in a multiprocessor configuration. Bus arbiter: Which functions to resolve priority between bus masters and allows only one device at a time t

What is microcomputer system, Q. What is microcomputer system? The micr...

Q. What is microcomputer system? The microcomputer has a single microprocessor and a number of RAM and ROM chips as well as an interface unit which communicates with several ex

How to access the disk data, Q. How to Access the Disk Data? Disks oper...

Q. How to Access the Disk Data? Disks operate is semi-random mode of operation and generally referenced block wise. The data access time on a disk comprises two major component

What is dialog box, This is a small window that is demanding your attention...

This is a small window that is demanding your attention. You must respond before you can carry on using the program that shown the dialog box. A dialog box does not have a minimize

Explain the benefits of interpreter, Explain the Benefits of Interpreter? ...

Explain the Benefits of Interpreter? The benefit of an interpreter though is that it doesn't need to go through the compilation stage during which machine instructions are gene

Define end directive and assume directive, END DIRECTIVE: ENDS directive e...

END DIRECTIVE: ENDS directive ends a segment and ENDP directive ends a procedure and END directive ends whole program which appears as last statement. ASSUME Directive:   An .

What is the use of urgent pointer in tcp segment, What is the use of urgent...

What is the use of urgent pointer in TCP segment? For accommodation out of band signaling, TCP permits the sender to identify data as urgent, implies that the receiving program

How a pointer variable declared in c, How a pointer variable declared in C ...

How a pointer variable declared in C ? Why is it sometimes desirable to pass a pointer to a function as an argument? A pointer is a variable which contains the address in memor

Define the term busy hour, Define the term busy hour Busy Hour: Conti...

Define the term busy hour Busy Hour: Continuous 1- hour period lying completely in the time interval concerned, for that the traffic volume or the number of calls attempts is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd