Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is public, * Public, protected and private are 3 access specifier in C...

* Public, protected and private are 3 access specifier in C++. * Public data members and member functions are accessible outside the class. * Protected data members and memb

What is assembly, What is assembly Assemblies are the building blocks o...

What is assembly Assemblies are the building blocks of .NET Framework applications; they variety the fundamental unit of deployment, version control, reuse, activation scoping,

Explain briefly how firewalls protect network, Explain briefly how firewall...

Explain briefly how firewalls protect network.       A firewall is simply a program or hardware device that filters the information coming by the Internet connection into your

Assembly Language program, How to get an output: Please enter a number betw...

How to get an output: Please enter a number between 0 and 6 (Enter to stop): 2 The Day of Week is Tuesday Please enter a number between 0 and 6 (Enter to stop): 9 Input Invalid Ple

Illustration of parallel programming environments, Q. Illustration of paral...

Q. Illustration of parallel programming environments? Let's discuss illustrations of parallel programming environments of Intel paragaon XP/S and Cray Y-MP software. The Cra

Example of weight training calculations, Example of Weight training calcula...

Example of Weight training calculations: Through having calculated all the error values associated with such each unit like hidden and output then we can now transfer this inf

Explain about flip-flops, Explain about Flip-Flops  Flip-Flops are also...

Explain about Flip-Flops  Flip-Flops are also called bistable multivibrator.  A flip-flop is capable of storing 1 bit of binary data.  It has two stable states- 'one' and 'zero

What is co-operative process, What is co-operative process? A process i...

What is co-operative process? A process is co-operating if it can affect or be affected by the other processes implementing in the system. Any process that share data with othe

Determine about the intranet server, Determine about the Intranet server ...

Determine about the Intranet server The success or usage of the Intranet server is measured by the number of operations it handles per Unit time. The selection of a good server

Binary tree can be converted in to its mirror image, A binary tree can be c...

A binary tree can be converted in to its mirror image By traversing it in Preorder

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd