Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Common problem with hill climbing, Common problem with Hill climbing: ...

Common problem with Hill climbing: An alternative way of justifying the problem is that the states are boards with 8 queens already on them, so an action is a movement of one

Explain concurrent sharing, Explain Concurrent sharing. Concurrent s...

Explain Concurrent sharing. Concurrent sharing: Some number of programs may share a file concurrently. While this is the case, this is essential to ignore mutual interferen

How many flip flops are required to construct decade countr, How many flip ...

How many flip flops are required to construct a decade counter ? Ans. 4 FlipFlop's are required because decade counter counts 10 states from 0 to 9 (that is from 0000 to 1001).

What is exact and approximation algorithm, What is Exact and Approximation ...

What is Exact and Approximation algorithm? The principal decision to choose solving the problem exactly is called exact algorithm. The   principal decision to choose solving th

Explain parallel overhead, Parallel Overhead The amount of time needed ...

Parallel Overhead The amount of time needed to organize parallel tasks, as opposed to undertaking useful work. Parallel overhead may comprise factors like:   1) Task start-u

Why should i use cgi, CGI is significant whenever you require to retain sta...

CGI is significant whenever you require to retain state information about a user, or run an application which communicates with the server. Things like guestbook's, Chat clients, d

Comparison between centralized and distributed spc, Explain the principles ...

Explain the principles of operation of centralized SPC and distributed SPC and compare their performance. All the control equipment is replaced with a single processor that mus

Example on multi-statement forall construct, Q. Example on Multi-statement ...

Q. Example on Multi-statement FORALL construct? The subsequent statements set every element of matrix X to sum of its indices.  FORALL (i=1:m, j=1:n)      X(i,j) = i+j an

Important part of process - canonical genetic algorithm, Important part of ...

Important part of Process - canonical genetic algorithm: In such a scenario evolution or random mutations are often highly deleterious or can say harmful to the organism it me

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd