Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define object oriented modelling, Object oriented modelling Object ori...

Object oriented modelling Object oriented modelling is entirely a new way of thinking about queries. This methodology is all about visualizing the things by using models organ

Which technique are used to gain on the number pairs, Explain the technique...

Explain the techniques, which are used to gain on the number pairs. In rural areas, subscribers are usually dispersed. This is both unessential and expensive to give a dedicate

What is the mips assembly code, Question: (a) Using an appropriate dia...

Question: (a) Using an appropriate diagram, illustrate the structure of an instruction used for branching purposes and state the purpose of each part. (b) Given the number

Duplicating processes, DUPLICATING PROCESSES : As we mentioned earlier dup...

DUPLICATING PROCESSES : As we mentioned earlier duplicating is a process whereby a master copy is prepared from which a large number of other copies are obtained with the help of

How many chips will be required in a microprocessor , A microprocessor uses...

A microprocessor uses RAM chips of 1024 × 1 capacity. (i) How many chips will be required and how many address lines will be connected to provide capacity of 1024 bytes. (ii) How

What are the address-sequencing capabilities, What are the address-sequenci...

What are the address-sequencing capabilities required in a control memory? i. Incrementing the control address register ii. Unconditional branch as specified by address fiel

Planning too much up front a mistake in an oosad, You can't plan only for t...

You can't plan only for the present phase of the project as your future activities are still coarse granular. To have good planning you require to have fine granularity w.r.t the t

Basic working of semiconductors, Q. Basic working of Semiconductors? Se...

Q. Basic working of Semiconductors? Semiconductors are crystalline solid materials whose resistivities have values between those of conductors and insulators. Conductivity rang

Determine about the authoring software, Determine about the Authoring Softw...

Determine about the Authoring Software Also termed as author ware; this is a program which helps in the writing of hypertext or multimedia applications. Authoring tools general

Explain signed binary number system, Explain signed binary number system. ...

Explain signed binary number system. Ans. Signed Binary Numbers: In decimal number system positive numbers are signified by (+) sign and negative numbers are represented b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd