Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Uml, what is uml ?

what is uml ?

Compute minimum value of the horizontal force, Compute minimum value of the...

Compute minimum value of the horizontal force: Block A of weight 520N rest on horizontal top of block B having weight of 700N as shown in the figure given below. Block A

Scoreboards- constrained-random verification methodology, Scoreboards- Cons...

Scoreboards- Constrained-Random Verification Methodology Scoreboards are used to verify that data has successfully reached its destination whereas monitors snoop the interfaces

Digital electronics, Explain the principle of duality with examples.

Explain the principle of duality with examples.

Defines a macro, Defines a macro Defines a macro with the given name, h...

Defines a macro Defines a macro with the given name, having as its value the given replacement text. After that (for the rest of the current source file), wherever the preproce

Find traffic offered and lost, Discuss grade of service. During busy hour, ...

Discuss grade of service. During busy hour, 1500 calls were offered to a group of trunks and 8 calls were lost. The average call duration was 120 seconds. Calculate the traffic off

What does a socket having of, The combination of an IP address and a port n...

The combination of an IP address and a port number is known as a socket.

Physical characteristics and access mode of disk drive, Q. Physical charact...

Q. Physical characteristics and access mode of disk drive? Access Time: Access time is time needed between requests made for a read or write operation until the time data are

Which address is specially used by transport layer, The addressing speciall...

The addressing specially used by Transport Layer is? The addressing particularly used through transport layer is application port address.

Characteristics of storage - computer architecture, Characteristics of comp...

Characteristics of computer storage: Storage technologies at all of levels of the storage hierarchy may be distinguished by evaluating particular core characteristics and alon

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd