Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What is combinational circuits, Q. What is Combinational circuits? Comb...

Q. What is Combinational circuits? Combinational circuits are interconnected circuits of gates according to definite rules to generate an output relying on its input value. A w

Explain the different sub-functions of process scheduling, Explain the diff...

Explain the different sub-functions of Process Scheduling. Process scheduling contains the subsequent sub-functions: 1. Scheduling: Chooses the process to be executed next

Find max conversion time of 6-bit dual slope A/D converter, A 6-bit Dual Sl...

A 6-bit Dual Slope A/D converter uses a reference of -6V and a 1 MHz clock. It uses a fixed count of 40 (101000). Find Maximum Conversion Time.         Ans. The time T 1 specifie

Functions for message passing, Functions for Message Passing: MPI proc...

Functions for Message Passing: MPI processes don't share memory space and one process can't directly access other process's variables. Therefore they need some form of communi

Expalin the history of parallel computers, Expalin the History Of Parallel ...

Expalin the History Of Parallel Computers The researches with and implementations of use of the parallelism started long back in the 1950's by IBM Corporation. The IBM STRETCH

What is the benefit of using linq on dataset, The main aim of using LINQ to...

The main aim of using LINQ to Dataset is to run strongly typed queries on Dataset. Assume we want to combine the results from two Datasets, or we need to take a distinct value f

The field sy-dynr, The field SY-DYNR refers to Number of the current sc...

The field SY-DYNR refers to Number of the current screen.

How to add a wait state when creating a verification point, 1. Start to mak...

1. Start to make the verification point. 2. In the confirmation Point Name dialog box, select Apply wait state to confirmation point. 3. Type values for the following option

Characteristics of input- output channels, Q. Characteristics of input- out...

Q. Characteristics of input- output channels? The I/O channel represents an extension of DMA concept. An I/O channel has ability to execute I/O instructions that gives complete

Explain the use of ssl to secure the network, Explain the use of SSL to sec...

Explain the use of SSL to secure the network.  SSL (Secure Sockets Layer) is a protocol developed by Netscape for transferring private documents by the Internet. SSL works by u

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd