Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Explain the role of a bus arbiter in a multiprocessor, Explain the role of ...

Explain the role of a bus arbiter in a multiprocessor configuration. Bus arbiter: Which functions to resolve priority between bus masters and allows only one device at a time t

Testing project, Design and test the functions that are needed: a.  Test...

Design and test the functions that are needed: a.  Test Main  in the Testing project add a new file main.c. b.  Test Drivers  in the Testing project add 2 new files, testDriver

Structure tensor, what is structure tensor?how we calculate for image pixel...

what is structure tensor?how we calculate for image pixel?

Loop used to show properties, Normal 0 false false false ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4  A loop invariant is

What are different adder circuits you studied, Half Adder (for addition of ...

Half Adder (for addition of two bits) Full Adder (for addition of three bits) Carry look ahead adder Carry save adder Carry propagate adder

What is virtual memory, What is virtual memory? Method that automatical...

What is virtual memory? Method that automatically move program and datablocks into the physical main memory when they are needed for execution are known as virtual memory.

Why should you use bugzilla?, Bugzilla can dramatically enhance the product...

Bugzilla can dramatically enhance the productivity and accountability of individual employees by giving a documented workflow and positive feedback for good performance.

What start bit and stop bit, What start bit and stop bit The first bit ...

What start bit and stop bit The first bit known as the Start bit is always a zero and it is used to show the beginning of the character The last bit is known as the stop bit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd