Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Minimumshelf program in c, At a shop of marbles, packs of marbles are prepa...

At a shop of marbles, packs of marbles are prepared. Packets are named A, B, C, D, E …….. All packets are kept in a VERTICAL SHELF in random order. Any numbers of packets with thes

Explain difference between macro call and macro expansion, Explain differen...

Explain difference between macro call and macro expansion. Macro expansion: While a macro name is used along with a set of actual parameters this is replaced through a code g

Karnaugh maps, Minimisation using Boolean algebra is not always straight fo...

Minimisation using Boolean algebra is not always straight forward and sometimes it is not obvious if a further manipulation would give a simpler circuit. Karnaugh maps are a muc

Datastructure, deque insertion and deletion ..

deque insertion and deletion ..

What do you mean by processor arrangements, Q. What do you mean by Processo...

Q. What do you mean by Processor Arrangements? It is a very common event in data parallel programming to combine many processors to execute specific tasks. To achieve this obje

Rules for calling assembly subroutines from, Q. Rules for calling assembly ...

Q. Rules for calling assembly subroutines from? The rules for calling assembly subroutines from C are: (i)  Memory model: The calling program and called assembly programs sh

How atoms differ from the arrangement of atoms in a liquid, Q. How does the...

Q. How does the preparation of atoms in mainly solids differ from the arrangement of atoms in a liquid? Answer:- The arrangement of atoms in solids are diverse from those

Data stream and instruction stream-flynn’s classification, Data Stream an...

Data Stream and Instruction Stream The term 'stream' refers to an order or flow of either data operated or instructions on by the computer. In the complete chain of instructi

Vector-vector instructions-vector processing, Vector-Vector Instructions ...

Vector-Vector Instructions In this type, vector operands are fetched by the vector register and saved in another vector register. These instructions are indicated with the foll

Shape - elements of composition, Shape : A shape is any area that can b...

Shape : A shape is any area that can be perceived to have height and width. Shapes within an image can be created by the use of line, or by the edges created by variations in c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd