Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Avl tree rotation and b tree construction in data structure, Elements are g...

Elements are given 3,14,7,1,8,5,11,17,,6,23,12,20,26,4,16,18,24,25,19 We will construct b tree and avl tree And after that delete some integers

Advantages and drawbacks of mealy and moore machine, What are the advantage...

What are the advantages and drawbacks of mealy and moore machine? Advantages and drawbacks: Into Mealy as the output variable is a function both state and input, changes o

What is tri-state logic, What is Tri-state logic ? Ans. Tri-state Logi...

What is Tri-state logic ? Ans. Tri-state Logic: In common logic circuits, there are two states of the output, as LOW and HIGH. If the output is not in the LOW state, this

Illustrate abstract class, What is an abstract class? Please, expand by exa...

What is an abstract class? Please, expand by examples of using both. Explain why?   Abstract classes are closely related to interfaces. They are classes that cannot be instanti

Categorize the cpu scheduling algorithms, Categorize the CPU scheduling alg...

Categorize the CPU scheduling algorithms? The various CPU scheduling algorithms are categorized as given below:

Purpose of pointer phrase in string command, The Purpose of POINTER phrase ...

The Purpose of POINTER phrase is to verify the leftmost position within receiving field where the first transferred character will be kept

Calculate the propagation delay for output, Problem: (a) Consider the ...

Problem: (a) Consider the following combinational circuit: (i) Calculate the propagation delay for each output. Assume each gate has a delay of 10 ns. (ii) The abo

Inverse of exclusive or known as xnor gate, Truth table of NAND and NOR can...

Truth table of NAND and NOR can be made from NOT (A AND B) and NOT (A OR B) correspondingly. Exclusive OR (XOR) is a special gate whose output is one only if two inputs aren't equa

Two ways in which one can retrieve data from tables, In general what are th...

In general what are the two ways in which one can retrieve data from tables? Using Select statements, Database Program.

How to apply color and style, Q. How to Apply Color and Style? 1.  In f...

Q. How to Apply Color and Style? 1.  In first text description layout cell, select heading text from the word "Fly" through the word "Mountains." 2.  In Property inspector,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd