Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Common tasks to accomplish - artificial intelligence, Common Tasks to Accom...

Common Tasks to Accomplish: Once you've worried about what and why you're doing "AI", what has inspired you and how you're going to approach the job, then you just start to th

Instruction issue degree in superscalar processing, Q. Instruction Issue de...

Q. Instruction Issue degree in superscalar processing? The major concept in superscalar processing is how many instructions we are able to issue per cycle. If we are able to is

What are the major characteristics of a pipeline, What are the major charac...

What are the major characteristics of a pipeline? The major characteristics of a pipeline are: a) Pipelining cannot be executed on a single task, as it works by splitting mu

Can we convert the column data into row data, We download data which arrive...

We download data which arrives to me in a column. I need to use it in a complex sheet that requires data in a row. How can we convert the column data into row data?   Ans) H

Explain single instruction and multiple data stream (simd), Normal 0 ...

Normal 0 false false false EN-US X-NONE X-NONE Figure: SIMD Organisation

Software estimation, Software Estimation The statement of scope helps t...

Software Estimation The statement of scope helps the planner to established estimates using one or more method which fail into two wide categories: empirical modeling and decom

Rdbms relational database system, RDBMS relational database system - Re...

RDBMS relational database system - Relational databases are composed of relations and managed through relational operations, and governed through data integrity constraints.

Give the difference between register and counter, Q. Give the difference be...

Q. Give the difference between Register and Counter. Q. Give the difference between Flip-flop and Latch. Q. Draw a set of waveforms for following signal on out-put line.

Self knowledge - characteristics of an experts system, An experts system ...

An experts system has knowledge that lets it reason about its own operations plus a structure that simplifies this reasoning process. For example if an expert system

What is system-software, What is System-software? System-software is co...

What is System-software? System-software is collection of system programs which perform a variety of functions, name are: file editing, IO management, recourse accounting and s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd