Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate what is pascal''s principle, Illustrate what is pascal's princip...

Illustrate what is pascal's principle? Answer:- Pascal's Principle declares that the pressure is transmitted evenly through a liquid. That's why when you pump up a balloon

explain compiler, Compiler is used to change the high-level language progr...

Compiler is used to change the high-level language program into machine code at a time. It doesn't needs special instruction to store in a memory, it keeps automatically. The imple

Realize x-nor gate using nand gate, Q. A. Which gates are called Universa...

Q. A. Which gates are called Universal Gates? Why? B. State and prove any one of the DeMorgen's Laws. Show that these theorems can be extended up to any number of variables.

Security analysis, Security Analysis: Suppose you are a young securiti...

Security Analysis: Suppose you are a young securities analyst, working in a small brokerage firm. You have access to publicly available information relevant to valuation of th

Observations of high level language program, Q. Observations of High Level ...

Q. Observations of High Level Language Program? Observations Integer constants appeared nearly as frequently as structures or arrays. Most of the scalars were foun

How a typical dma controller can be interfaced to an 8086, Demonstrate how ...

Demonstrate how a typical DMA controller can be interfaced to an 8086/8085 based maximum mode system.  For 8088 in maximum mode: The RQ/GT0 and RQ/GT1 pins are used to is

Illustrate minimization of gates, Q. Illustrate Minimization of Gates? ...

Q. Illustrate Minimization of Gates? The generalization of Boolean expression is much useful for combinational circuit design. The subsequent three techniques are used for this

Different types of layers in tcp/ip protocol stack, What are the different ...

What are the different types of layers in TCP/IP protocol stack? Layers into the TCP/IP protocol architecture are as given below: • Application Layer, • Host-to-Host Tra

Explain hypertext transfer protocol, Explain Hypertext Transfer Protocol. ...

Explain Hypertext Transfer Protocol. HTTP is used mainly in today's society like a set of rules for exchanging files (graphic images, text, sound, other multimedia files or vid

What is application software, What is application software? Give example. ...

What is application software? Give example. Application programs are usually written in a high level programming language, in which the programmer states mathematical or text p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd