Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Describe about instruction set, Q. Describe about Instruction set? Inst...

Q. Describe about Instruction set? Instruction set is the boundary where computer designer and computer programmer see the same computer from various viewpoints. From the desig

Classification of parallel computers , Classification Of Parallel Computer...

Classification Of Parallel Computers  Introduction Parallel computers are those that underline the parallel processing among the operations in some way. In the last unit,

Evaluate bandwidth of disk drive, Q. Evaluate Bandwidth of disk drive? ...

Q. Evaluate Bandwidth of disk drive? Bandwidth:  Bandwidth can be measured in bytes per second. Sustained bandwidth is the average data rate at the time of a large transfer w

Explain relative addressing scheme, Q. Explain Relative Addressing Scheme? ...

Q. Explain Relative Addressing Scheme? In this addressing technique the register R is the program counter (PC) which contains the address of current instruction being executed.

Logical user-centered interactive design methodology, Question: Logical...

Question: Logical User-Centered Interactive Design Methodology is a methodology that identifies six clear stages to help in software development while keeping the user in mind.

What is garbage collection and what is it used for, In computer science, ga...

In computer science, garbage collection (GC) is a form of automatic memory management. The garbage collector, or just collector, attempts to reclaim garbage, or memory occupied by

Explain about interlacing, Q. Explain about Interlacing? Interlacing is...

Q. Explain about Interlacing? Interlacing is a procedure in which in place of scanning the image one-line-at-a-time it's scanned alternatelyit implies thatalternate lines are s

Integrating virtual memory, Integrating Virtual Memory, TLBs, and Caches - ...

Integrating Virtual Memory, TLBs, and Caches - computer architecture:   There are 3 types of misses: 1. a cache miss 2. TLB miss 3. a page fault 2 techniqu

Determine the bios function with one illustration, Determine the BIOS funct...

Determine the BIOS function with one illustration BIOS stands for Basic Input Output System. It is a set of programs to provide most basic low-level services like services keyb

Cso, why we don''t use register at the place of ram?

why we don''t use register at the place of ram?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd