ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to expand its product range, moving into high quality cakes and desserts. 

ST has identified a number of activities that must be undertaken to set up the latest bakery production plant. He now intends to construct a network analysis to assist ST in the planning of the project. This will also enable him to give an answer for the HR manager who has asked him to provide advice on when she can begin the recruitment campaign to select new employees required to work in the new part of the bakery.

256_managemnet.png

Identify the earliest time the recruitment campaign can start.

The recruitment campaign can start in week 24. 


Related Discussions:- Earliest time the recruitment campaign can start

Can surprises be reduced, Q. Can surprises be reduced? Yes absolutely! ...

Q. Can surprises be reduced? Yes absolutely! By their vary nature projects are uncertain business and uncertainty can lead to both risk and opportunities. As a result a very im

What do you mean by the term dependency, What do you mean by the term depen...

What do you mean by the term dependency? How can project dependencies be shown for planning reasons? Dependency arises when, for illustration, task or deliverable 'A' should be

What are its core features of mpmm, MPMM is a body of project management co...

MPMM is a body of project management content, wrapped in an easy, simple to use software tool. This tool contains such core features as a Navigation Panel, Display Panel, Page Summ

National competitive bidding (ncb) , Steps for National Competitive Bidding...

Steps for National Competitive Bidding (NCB)  Similar to ICB, we have two ways involved in NCB: one with pre-qualification, another without prequalification. Steps for NCB are

How to, i get stuck being on time and orginzed. please help. is this money?...

i get stuck being on time and orginzed. please help. is this money? thanks isabella

Explain about the process of managing risk, Explain about the process of ma...

Explain about the process of managing risk. A process of managing risk: 1. Risk committee establish to address risk issues categorised for example usual risk audits, to estimat

Leading lean project-Fifa Cup 2018, I want this assignment befor the due de...

I want this assignment befor the due deate of 7 sept..if some one over there than contact me.

What are the benefits of work study?, Question 1) Describe any ten overall...

Question 1) Describe any ten overall functions of the purchasing department Question 2) Describe any five principles of plant layout Question 3) Describe the any

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd