Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.tion..

Related Discussions:- DW

Give concurrent sub states diagram for the classroom, Give Concurrent sub s...

Give Concurrent sub states diagram for the classroom and exam held. In Figure, simultaneous substrates have been taken. After passing Minor 1 test you could give Minor 2 test. T

What is online transaction processing, What is OLTP (Online Transaction Pro...

What is OLTP (Online Transaction Processing)? In OLTP - online transaction processing systems relational database design use the discipline of data modeling and generally follo

What is the difference between link and reference, What is the difference b...

What is the difference between link and reference? The fundamental difference between links and references is that links are symmetrical on the other hand references refer only

What is deadlock, What is deadlock? Neither of the transaction can ever...

What is deadlock? Neither of the transaction can ever proceed with its normal implementation. This situation is known as deadlock.

What are the objectives of query processing, What are the objectives of que...

What are the objectives of query processing?       Ans: The objectives of query processing is to transform a query written in a high level language into a accurate and efficien

Normalization, a project based on normalization with first, second and thir...

a project based on normalization with first, second and third normalization. There need to be a diagram also

Project, I have a small project that contains 3 deliverable s. I have done ...

I have a small project that contains 3 deliverable s. I have done the first one and I would like you to help me with second one

Define two-phase locking protocol, Define two-phase locking protocol. A...

Define two-phase locking protocol. Ans: Two-phase locking is significance in the context of ensuring that schedules are serializable. The two-phase locking protocol defines a p

What is middleware, Question: a) What is Client/Server and what benefit...

Question: a) What is Client/Server and what benefits can be expected from Client/Server systems? b) Explain what middleware is and what it does. Why would MIS managers be p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd