Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.tion..

Related Discussions:- DW

What is meant by heuristic optimisation, What is meant by heuristic optimis...

What is meant by heuristic optimisation?  Discuss the main heuristics that are applied during query optimisation.  Ans:  In heuristic optimization, heuristics are employed to r

Conversion of er diagram to relational database, Conversion of entity sets:...

Conversion of entity sets: I)   For  every  strong  entity  type  E  in  the  ER  diagram,  we  make  a  relation  R containing all the easy attributes of E. The relation R pri

Discuss along with examples about several types of er model, Discuss along ...

Discuss along with examples about several types of attributes present in the ER model? Types of Attributes are: • SIMPLE attributes are attributes which are drawn from the ato

Mention the various user privileges, Mention the various user privileges ...

Mention the various user privileges All privileges directly granted to the user or role. All privileges granted to roles that have been granted to the user or role.

Sql, Events4Fun is an event management company in Europe with branches in S...

Events4Fun is an event management company in Europe with branches in South America as well. The company is well-known for its efficiency, good-quality services, and affordable char

Define rotational latency time, Define rotational latency time. The ti...

Define rotational latency time. The time spent waiting for the sector to be accessed to appear under the head is known as the rotational latency time.

Design and building a distributed information system, The scenario You ...

The scenario You have been approached to design and implement a prototype of a distributed information system for a national car part retail outlet chain. The company comprises

Outer join, Outer Join: The use of Outer Join is that it still joins those...

Outer Join: The use of Outer Join is that it still joins those tuples that do not have matching values in common columns are also contained in the result table. Outer join places

Data mining, 1.Why we need data mining? Give an example to illustrate your ...

1.Why we need data mining? Give an example to illustrate your answer. 2. Why data mining is considered as "misleading name"? 3. Distinguish the difference between database an

Describe in brief about object oriented design, Describe about Object orien...

Describe about Object oriented design Object oriented design is concerned with developing an object oriented model of a software system to implement known requirements. Many OO

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd