A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
how can we increase revenue to raise on fortune 500 list?
causes for decay of timber
define of couple
Bituminous Macadam: Bituminous Macadam (BM) is a base course in which coarse aggregates are mixed with a bituminous binder. The mix is open-graded with 20-25 per cent voids.
LIME It is significant binding material utilized in building construction. Lime has been utilized as the material of construction from ancient time. While it is mixed with san
test in fresh concrete
Concordant Prestressing In this type of prestressing, tendons follow a concordant profile. The concordant profile of tendons does not change the support reactions in a statica
what is the trignomerty leveling
Question What is key function of packing resources in joint of concrete pipes in pipe jacking ? Answer Packing resources are about 10 to 20mm broad and are usually mad
distomat
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd