Draw a network diagram for this problem, Applied Statistics

Assignment Help:

The project of building a backyard swimming pool consists of eight major activities and has to be completed within 19 weeks. The activities and related data are given in the following table:

Activity

Immediate predecessor

Activity time (weeks)

A

-

3

B

-

6

C

A

2

D

B,C

5

E

D

4

F

E

3

G

B,C

9

H

F,G

3

a. Draw a network diagram for this problem. 

b. Determine the critical path and the expected project completion time.


Related Discussions:- Draw a network diagram for this problem

Canonical correlation analysis, Canonical correlation analysis (CC) allows ...

Canonical correlation analysis (CC) allows the investigation of the relationship between two ,sets of variables. For example, a sociologist may want to investigate the Relationship

Sampling error , Sampling Error  It is the difference between the value...

Sampling Error  It is the difference between the value of the actual population parameter and the sample statistic. Samples are used to arrive at conclusions regarding the p

Business reporting and analysis, You are a business analyst working for a c...

You are a business analyst working for a company called Combined Computers Pty Ltd. You have been asked to prepare a business report with statistics in it for the managing director

Normal distribution, Normal Distribution Meaning: According  to ya Lu...

Normal Distribution Meaning: According  to ya Lun Chou  There perfectly smooth and symmetrical  curve, resulting  from the expansion of the binomial (p+q) n    when n approac

Calculate the maximum charge current, For the circuit shown below; Wr...

For the circuit shown below; Write a KCL equation for Node A, Node B, Node C and Node D. Write a KVL equation for Loop 1, Loop 2 and Loop 3.   A simple circ

Determine market interest rate, The interest rate on the three year loan is...

The interest rate on the three year loan is 0.087. Whereas the interest rate on the two year loan is 0.085 as given in A. Suppose that the liquidity premium at t=1 is 0.002 and tha

Physics, fixed capacitor and variable capacitor

fixed capacitor and variable capacitor

Find relative maxima and minima, Q. Find relative maxima and minima? Wh...

Q. Find relative maxima and minima? When finding relative maxima and minima in the Chapters absolute extrema problem, don't forget to use the first or second derivative test to

Box plots, This box plot displays the diversity wfood; the data ranges from...

This box plot displays the diversity wfood; the data ranges from 0.05710 being the minimum value and 0.78900 being the maximum value. The box plot is slightly positively skewed at

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd