The project of building a backyard swimming pool consists of eight major activities and has to be completed within 19 weeks. The activities and related data are given in the following table:
Activity
Immediate predecessor
Activity time (weeks)
A
-
3
B
6
C
2
D
B,C
5
E
4
F
G
9
H
F,G
a. Draw a network diagram for this problem.
b. Determine the critical path and the expected project completion time.
Grouped data For grouped data, the formula applied is σ = Where f = frequency of the variable, μ= population mea
The project of building a backyard swimming pool consists of eight major activities and has to be completed within 19 weeks. The activities and related data are given in the follow
how much that cost ?
A researcher was interested lowering the high school dropout level in his county. He measured the reading level of students entering middle school (based on a standard test) and th
velocity of a particle which moves along the s-axis is given by v=2-4t+5t then find position velocity,acceleration
Hi There, I have a question regarding R, and I am wondering if anyone can help me. Here is a code that I would like to understand: squareFunc g f(x)^2 } return(g) } sin
Q. Find the inverse Laplace transform of Y (s) = s-4/s 2 + 4s + 13 +3s+5/s 2 - 2s -3. Q. Use the Laplace transform to solve the initial value problem y''+ y = cos(3t), y(0) =
Try different numbers of clusters in your program (K=2...15) and build a plot that shows the dependency between number K and value of RSS function on the last iteration. What is th
Consider the following game: (a) If (top, left) is a Weakly Dominant Strategy Equilibrium, then what inequalities must hold among (a, ..., h)? (b) If (top, left) is a Na
The box plot displays the diversity of data for the totexp; the data ranges from 30 being the minimum value and 390 being the maximum value. The box plot is positively skewed at 1.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd