Draw a 3-sigma p-chart using this information, Operation Management

Assignment Help:

The results of inspection of DNA samples taken over the past 10 days are given below. Sample size is 100.

Days: 1 2 3 4 5 6 7 8 9 10

Defectives: 7 6 6 9 5 6 0 8 9 1

a) Construct a 3-sigma p-chart using this information

b) If the number of defectives on the next three days are 12, 5 and 13, is the process in control?


Related Discussions:- Draw a 3-sigma p-chart using this information

A computerised payroll package, A computerised payroll package is an exampl...

A computerised payroll package is an example of a   Data processing system

Explain how many customers could be served per hour, Greg Davis, a business...

Greg Davis, a business major at the University of South Carolina (USC), has opened Six Points Saco (SPS), a specialty subs-taco restaurant, at the rim of the USC campus. SPS has gr

Order winners - operations strategy, Order Winners - Operations Strategy ...

Order Winners - Operations Strategy These are operational capabilities that directly contribute to winning business. They are generally cited as the reasons for the purchase o

Explain income levels and income distribution among nations, How do differe...

How do differences in income levels and income distribution among nations affect international businesses?

Process flow and layouts, process flow and layout flows are at the core of ...

process flow and layout flows are at the core of lean manufacturing, do you agree or disagree?

Explain neutral facilitator between employees, A(n) _____ is a neutral faci...

A(n) _____ is a neutral facilitator between employees and managers who assists in resolving workplace disputes

Hospital management requirement, The local hospital's emergency department ...

The local hospital's emergency department has 5 trauma bays. On average, patients requiring a trauma bay arrive every 50 minutes (with a coefficient of variation of 1, no seasonali

Explain what recommendations would you make and why, 1. Draw a process flow...

1. Draw a process flow diagram of the process described in the case. Be sure to identify the key resources involved and the task times at each step. 2. What is utilization at ea

Find the critical path, Using the information given in the following table:...

Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration. Activities Precedes Duration Start a,b,c - a d 5 d f 6

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd