Question-What are three key types of r einforcement used in pre stressing ? Answer- (i) Spalling reinforcement - Spalling stresses are established behind loaded
A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square
1. 130,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%. The final volume of the compacted
Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was
# ???? ..
Absolute pressure is measured from a vacuum (0 PSI) and atmospheric pressure is14.7PSIa or 14.7 PSI above a vacuum 1PSI on a tire pressure gauge is known as 1PSIg = 15.7PSIa 10PSIg
Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish
State an expression for 'zero air-void line' and illustrate the line for a specific gravity of 2.65. What are the various factors that affect the compaction of soil in the field
how does battening differ from lacing?
Construction and working of calomel electrode
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd