Q. Diffrence between Hudsons and Van der Meer formula?

Hudson's formula is usually adopted in preliminary design to attain rough initial estimate of rock size. This formula is derived from the results of regular wave tests. Though this formula doesn't take into account the following elements which Van der Meer formula does: damage level, wave period, permeability of structure and storm duration. Furthermore Hudson's formula deals with the use of regular waves only. 

Compared with Hudson's formula, Van der Meer formula is more complex and it's derived from results of a series of physical model tests. They comprise the consideration of wave period, storm duration, permeability and clearly-defined damage level of structure. The choice of appropriate formula is dependent on the design purpose (which is preliminary design or detailed design).


Related Discussions:- Diffrence between hudsons and van der meer formula

Define the hazardous waste, Define the Hazardous Waste 1. Any waste or ...

Define the Hazardous Waste 1. Any waste or combination of waste that poses a substantial danger now or future to humans, plants, and animals without special precautions. 2.

Principle of adding cooling pipes, Question What is key principle of a...

Question What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation? Answer These methods aim at reducing placing tem

Shear stress, difference between bending stress and shear stress

difference between bending stress and shear stress

Cost-volume-profit and break even analysis, Cost-Volume-Profit and Break Ev...

Cost-Volume-Profit and Break Even Analysis: Cost-volume-profit analysis helps us to learn the behaviour of cost and profit in response to varying level of business activity. I

#title difference, Write difference between the working stress method and l...

Write difference between the working stress method and limit step methode

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Back fill behind the abutments of bridges, Q. Back fill behind the abutment...

Q. Back fill behind the abutments of bridges? Dry Rubble - At the bank of all bridge abutments and wing walls, the space next to the masonry is to be filled in by a hand-pack

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd