Diffrence between hudsons and van der meer formula, Civil Engineering

Assignment Help:

Q. Diffrence between Hudsons and Van der Meer formula?

Hudson's formula is usually adopted in preliminary design to attain rough initial estimate of rock size. This formula is derived from the results of regular wave tests. Though this formula doesn't take into account the following elements which Van der Meer formula does: damage level, wave period, permeability of structure and storm duration. Furthermore Hudson's formula deals with the use of regular waves only. 

Compared with Hudson's formula, Van der Meer formula is more complex and it's derived from results of a series of physical model tests. They comprise the consideration of wave period, storm duration, permeability and clearly-defined damage level of structure. The choice of appropriate formula is dependent on the design purpose (which is preliminary design or detailed design).


Related Discussions:- Diffrence between hudsons and van der meer formula

Determine the expected extension at the jack, A cylindrical concrete tank,...

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  10 5   N/mm 2 )  jacked  at 4 points, 9

Non uniform flow in open channel, #ques5. A rectangular channel is 3 m in w...

#ques5. A rectangular channel is 3 m in width and draws water from a lake. The channel slope is 0.001 and the Manning’s n is 0.0013. What will be the discharge in the channel when

Movement accommodation factor for joint sealant, Movement accommodation fac...

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint

Advantages and dis advantages of timber, WHAT ARE THE ADVANTAGES AND DISADV...

WHAT ARE THE ADVANTAGES AND DISADVANTAGES OF TIMBER FOR CIVIL ENGINEERING

Building classification, Why I is the missing after h and J is written in t...

Why I is the missing after h and J is written in the classification of building

Calculate the final volume of the compacted soil, 1. 130,000-yd 3 of banke...

1. 130,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%.  The final volume of the compacted

Determine the ruthann graphical method, A retaining wall with a vertical ba...

A retaining wall with a vertical back 5 m high supports cohesion less backfill of unit weight of 19 kN/m 3 . The upper surface of the backfill rises at an angle of 10° with the hor

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd