Diffrence between hudsons and van der meer formula, Civil Engineering

Assignment Help:

Q. Diffrence between Hudsons and Van der Meer formula?

Hudson's formula is usually adopted in preliminary design to attain rough initial estimate of rock size. This formula is derived from the results of regular wave tests. Though this formula doesn't take into account the following elements which Van der Meer formula does: damage level, wave period, permeability of structure and storm duration. Furthermore Hudson's formula deals with the use of regular waves only. 

Compared with Hudson's formula, Van der Meer formula is more complex and it's derived from results of a series of physical model tests. They comprise the consideration of wave period, storm duration, permeability and clearly-defined damage level of structure. The choice of appropriate formula is dependent on the design purpose (which is preliminary design or detailed design).


Related Discussions:- Diffrence between hudsons and van der meer formula

Designing 10 story building, Hi need help with designing a 10 story concret...

Hi need help with designing a 10 story concrete building with basement car park. Need help with calculations in line with eurocodes. Is this something you can help with?

Define pressure on an inclined plane, Define Pressure on an Inclined Plane ...

Define Pressure on an Inclined Plane Similar to a vertical plane, fluid pressure increases linearly with increasing depth. The average pressure on an inclined plane occurs at t

Compaction to freshly placed concrete piles, Compaction to freshly placed c...

Compaction to freshly placed concrete piles  In general practice, reliance is placed on the self-compaction of particularly designed concrete mixes to achieve adequate compact

Estimate the net present worth - construction management, Three alternative...

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection wi

Draw the variation in total stress, Draw the variation in total stress, eff...

Draw the variation in total stress, effective stress, and pour water pres- sure up to a depth of 6 m below ground level, given the following data. The water table is 2 m below grou

Back fill behind the abutments of bridges, Q. Back fill behind the abutment...

Q. Back fill behind the abutments of bridges? Dry Rubble - At the bank of all bridge abutments and wing walls, the space next to the masonry is to be filled in by a hand-pack

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Computer programming, compare 2 numbers and print either the message identi...

compare 2 numbers and print either the message identifying the greater than number(or) the message starting that both number are equal

Process to calculate the initial tension, Process to calculate the Initial ...

Process to calculate the Initial Tension The maximum stress induced in the prestressing tendon at the time of the stressing operation is known as initial tension in tendons. T

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd