Differentiate between short column and slender column, Civil Engineering

Assignment Help:

Differentiate between Short Column and Slender Column

Short Column

It is a column of  rectangular section, the effective length of which does not exceed 12 times of  its least lateral dimension.

Slender Column

It is a column of  rectangular section, the effective length of which exceeds 12 times of  its least lateral dimension.

 


Related Discussions:- Differentiate between short column and slender column

Hydraulics, The atmospheric pressure is given 680 mm Hg at a certain mounta...

The atmospheric pressure is given 680 mm Hg at a certain mountain location of elevation 2000 m. air density is 1.007 kg/m3. Find the pressure in kPa.

What is material at site return, Q. What is Material at site Return? Th...

Q. What is Material at site Return? The authority is executive charge of a work should be responsible for holding in safe custody for controlling the consumption and to the ext

Explain rigging , In sailing, the ropes used to move the sails around so th...

In sailing, the ropes used to move the sails around so the boat will move in the right direction when the wind blows.

Retaining walls, Retaining Walls: Needed to retain the fill portion, a...

Retaining Walls: Needed to retain the fill portion, and generally constructed in dry stone masonry with pucca bunds (Figure). Figure: Typical Design for a Retaining

Calculation of crack widths arising from thermal movement, Q. Calculation o...

Q. Calculation of crack widths arising from thermal movement In the calculation of thermal movement, the below formula is used in most codes: w max =s x a x (T 1 +T 2 )/2

Analysis of prestress and bending stresses, Normal 0 false fa...

Normal 0 false false false EN-IN X-NONE X-NONE

Railway bridge, how to measure the waterways of railway bridges

how to measure the waterways of railway bridges

Define project schedule financial analysis, The 6 monthly payment applicati...

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14

Steel tubular marine piles, Question Give genuine reason that why are ...

Question Give genuine reason that why are steel tubular marine piles often driven open-ended? Answer In marine structure where piles are constantly topic to major la

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd