Differentiate between Short Column and Slender Column

Short Column

It is a column of  rectangular section, the effective length of which does not exceed 12 times of  its least lateral dimension.

Slender Column

It is a column of  rectangular section, the effective length of which exceeds 12 times of  its least lateral dimension.

 


Related Discussions:- Differentiate between short column and slender column

Concrete, What practical steps can one take to mitigate the adverse effects...

What practical steps can one take to mitigate the adverse effects in using aggregates with higher than specified flakiness index in the production of concrete

Define surface water treatment rule (swtr), Define Surface Water Treatment ...

Define Surface Water Treatment Rule (SWTR) SWTR sets forth primary drinking water regulations requiring treatment of surface water supplies or groundwater supplies under the di

Structural analysis 1, derive equation of radial pressure and loop stresses...

derive equation of radial pressure and loop stresses of thick cylinder

Properties of ordinary portland cement, Properties of Ordinary Portland Cem...

Properties of Ordinary Portland Cement (i) Chemical properties: Portland cement consists chemical compounds are following: (a) Tricalcium silicate          3 CaO.SiO 2 (C

WATER RESOURCES SYSTEM PLANNING AND MANAGEMENT, Two crops are grown on land...

Two crops are grown on land of 20ha.The cost of raising crop 1 is 3unit/ha, while for crop 2 it is 1 unit/ha.The benefit from crop 1 is 5unit/ha and from crop 2, it is 2 unit/ha. A

What do you mean by elastomeric bearings, Q. What do you mean by Elastomeri...

Q. What do you mean by Elastomeric bearings? Steel bearings are good but suffer from problems of corrosion and high level of maintenance. Due to these problems of steel bearing

Calculate the final volume of the compacted soil, 1. 130,000-yd 3 of banke...

1. 130,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%.  The final volume of the compacted

Determine the sweep angles and coordinates, This is more likely in to Aeros...

This is more likely in to Aerospace engineering.. So if there's anyone whose doing his/her major or have any skills regarding that field please help me with this problem. :) a)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd