Differentiate between iso and cmm, Software Engineering

Assignment Help:

Q. Differentiate between ISO and CMM?

Ans) The difference between CMM and ISO are as follows :-

- ISO 9000 is awarded by an international standards body. Thus, ISO 9000 certification can be quoted by an organization in official documents. Therefore, SEI CMM assessment is purely for internal use.

- SEI CMM was developed particularly for software industry and thus addresses many issues which are specific to software industry alone.

- SEI CMM goes beyond quality assurance and makes an organization to ultimately achieve Total Quality Management (TQM). In fact, ISO 9001 aims at level 3 of SEI CMM model.

- SEI CMM model gives a list of key process areas (KPAs) on which an organization at any maturity level requires to concentrate to take it from one maturity level to the next. Therefore, it gives a way for achieving gradual quality improvement.


Related Discussions:- Differentiate between iso and cmm

Compute act and the total cost of the system, a) Define Annual Change Traff...

a) Define Annual Change Traffic (ACT) and Annual Maintenance Effort (AME) of Boehm model. b) For a software system of 90 KLOC, 5KLOC of code was added. The initial development

What is intrusive testing, Testing that collects timing and processing info...

Testing that collects timing and processing information during program implementation that might change the behavior of the software from its behavior in a actual environment. Usua

What are version management tools, What are Version management tools? ...

What are Version management tools? Version and release identification Systems assign identifiers automatically when a new version is submitted to the system. St

Determine the shared mode of QTP, Determine the Shared mode of QTP - ...

Determine the Shared mode of QTP - Best used in subsequent cases: - When there are numerous tests which correspond to interface, objects, or application - When test obj

Determine the current failure intensity, Q. Presume a program will experien...

Q. Presume a program will experience a total of 200 failures. Preliminary failure intensity is 16 failure/ CPU hr. It has currently experienced 50 failures. Determine the following

What are the different architectures developed during bpe, What are the dif...

What are the different architectures developed during BPE? Data architecture framework for the information requires of a business. Application architecture incorporates the

Data Flow Diagram, I need help creating a DFD for an assignment. Is there a...

I need help creating a DFD for an assignment. Is there anyway you could help?

What are the aims of analysis modelling, What are the aims of Analysis mode...

What are the aims of Analysis modelling? i. To make apparent what the customer wants. ii. To set up a basis for the creation of software design. iii. To devise a set of v

Describe the different types of frequency hoping, Question: (a) What i...

Question: (a) What is a piconet in a Bluetooth context? (b) Discuss the concept of Master, slave, stand-by and parked devices with respect to a Bluetooth piconet. (c)

Define the computer based system, Define the computer based system. The...

Define the computer based system. The computer based system can be explained as "a set or an arrangement of elements that are organized to accomplish some predefined goal by pr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd